Operations Management: Sustainability and Supply Chain Management (12th Edition)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
12th Edition
ISBN: 9780134130422
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
Question
Book Icon
Chapter E, Problem 9P
Summary Introduction

To determine: The time taken to prepare the 15th lecture.

Introduction:

Learning curve:

Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.

Blurred answer
Students have asked these similar questions
Providence Assessment Center screens and trains employees for a computer assembly firm in Boston. The progress of all trainees is tracked, and those not showing the proper progress are moved to less demanding programs. By the tenth repetition, trainees must be able to complete the assembly task in 1 hour or less. Susan has just spent 5 hours on the fourth unit and 4.5 hours completing her eighth unit, while another trainee, Julie took 4 hours on the third and 2.8 hours on the sixth unit. Should you encourage either or both of the trainees to continue? Why? Present calculation steps.   [Hint: For each trainee, 1) Determine the learning rate (%) – use doubling concept. 2) Calculate time for the 1st unit (T1) – use table, 3) Calculate time for the 10th Unit (T10) –use table]     Susan Julie Learning rate (%) – doubling concept     Time for the 1st unit     Time for the 10th unit
Critically examine the potential negative impacts of poor time management on your academic life. NB: This question must be detailed to meet online examination standard.
local market research fim has just won a contract for several thousand small projects involving   data gathering and statistical analysis. In the past, the firm has assigned each project to a single member of its highly trained professional staff. This person would both gather and analyze the data Using this approach, an experienced person can complete an average of 10 such projects in an eight-hour day. The firm's management is thinking of assigning two people to each project in order to allow them to specialize and become more efficient The process would require the data gatherer to fill out a matrix on the computer, check it and transmit it to the statistical analysis program for the analyst   to complete. Data can be gathered on one project while the analysis is being completed on   another, but the analysis must be complete before the statistical analysis program can accept the   new data. After some practice, the new process can be completed with a standard time of 20   minutes…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.