The Farmer’s American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as follows:
Determine the earliest and latest activity times, the expected completion time and standard deviation, and the probability that the project will be completed in 40 weeks or less.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management, Binder Ready Version: An Integrated Approach
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Business in Action (8th Edition)
- A new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6. в 4 6 А, В A, B 5 6 7 D 7 9 10 E в 2 4 6 F 1 2 3 G D 5 8 10 H D, F 6 8 10 I E, G, H 3 4 5 a) What is the…arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 2 4 6 A, B A, B 5 6 7 D 7 9 10 E B 2 4 6 F 1 2 3 G D 5 8. 10 H D, F 6. 8. 10 I E, G, H 3 4 5 a) What is the…arrow_forwardQUESTION 7 The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following Table 6: Table 6 Activity Description A B с D E F G H I J K Activity Description Order new machinery Plan new physical layout Determine safety changes in existing machinery Receive equipment Hire new employees Make plant alterations Make changes in existing machinery Train new employees Install new machinery…arrow_forward
- The ABC Manufacturing Company has set up a weighted scoring matrix for evaluating some potential projects. Following are five projects under consideration. Using the scoring matrix below which project would you rate highest? Lowest? If the weight for “Sponsor Support” is changed from 2.0 to 5.0, will the project selection change? What are the three highest-weighted project scores with this new weight? Why is it important that the weights mirror critical strategic factors? Project Screening Matrix Criteria Weight Project 1 Project 2 Project 3 Project 4 Project 5 Sponsor Support 2 9 3 6 1 3 Strategic Alliance 5 5 7 8 0 10 Urgency 4 2 2 2 5 10 Fills a market gap 3 0 0 3 10 1 Sales 3 2 5 6 6 8 Competition 1 5 1 8 9 0arrow_forwardThe Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following table: Construct the project network for this project and determine the following: a. Expected activity times b. Earliest and latest activity times and activity slack c. Critical path d. Expected project duration and variance e. The probability that the mill will be fined $300,000arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forward
- Construct a PERT network from the following table. Find the critical path and variance for each event, if tō, tp, and to represent most optimistic, most pessimistic, and most likely times respectively. Activity 1 - 2 1 3 to 4 1 tp tm 1 3 2-4 2 7 1 3 5 7 3 4 3- 6 4 - 5 2 9 2 5 3 4-6 5 6 3 - 1 3 6-7 7 6 2arrow_forwardA farm owner is going to erect a maintenance building with connecting electrical gen- erator and water tank. The activities, activity descriptions and estimated durations are given in the following table. Construct the AOA network for this project, identify the critical path and construct a Gantt chart for the project. Description Excavate Erect building Install generator Install tank Activity A Predecessor Duration 2 B A 6 A 4 D A E Install maintenance equipment В 4 F Connect generator and tank building B,C,D 5 G Paint finish В 3 H Check out facility E,F 2arrow_forwardProblem 9-14 (Algorithmic) Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network: B F H Start C G Finish D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows: Activity Optimistic Most Probable Pessimistic A 4 9 14 B 5 7 3 4 D 8 11 14 7 17arrow_forward
- On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager and approved by the customer is the following: NETWORK LOGIC / ACTIVITY TIME (Weeks) AB 7 AC 10 AD 8 BC 4 BE 2 CF 3 DF 5 EF 2 FG 1 On August 27, 2013, the executive steering committee received the following report indicating the status of the project as of this time (end of week 8) ACTIVITY % COMPLETE ACTUAL COST TIME REMAINING (Weeks) AB 100 $23,500 0 AC 60 $19,200 4 AD 87.5 $37,500 1 BC 50 $8,000 2 BE 50 $5,500 1 Is the project ahead of schedule or behind schedule and over budget or under budget? What recommendations would you make for this project?arrow_forwardDavison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 42-week completion date requested by the owner. The Davison project manager prepared the following project network. H Start A Finish E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable Pessimistic A 4. 8 12 В 6. 8 12 18 D 3 5 7 18 8 17 G 10 15 20 H 5 13 (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) (d) Based only on the critical path, what is the estimated…arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are presented in Table 3. Draw a project network. Develop an activity schedule. What are the critical activities, and what is the expected project completion time? What is the probability that the swimming program will be ready in 13 weeks?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.