Select an everyday “project” you are familiar with such as a class project, preparing a meal, making a pizza, or repairing your car. Develop a list of the activities, a CPM/PERT network (with time estimates), and a work breakdown
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management, Binder Ready Version: An Integrated Approach
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Operations Management: Processes and Supply Chains (11th Edition)
Operations Management
- You may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Start Optimistic Time (hr) Most Probable Time (hr) Start Floor Buffing Paint Mixing Naturally, paint mixing precedes the painting activities. Also, (a) Construct the PERT/CPM network for this problem. Floor Sanding 4 Paint Mixing 4 0.5 3 3 Paint Wall Paint Ceiling Paint Ceiling Paint Wall 5 5 1 4 7.5 Floor Sanding Pessimistic Time (hr) Floor Buffing Finish 6 Finish 6 ceiling painting and floor sanding must be dor 1.5 11 9 i Start Start prior to floor buffing. Floor Sanding Paint Mixing Floor Buffing Paint Mixing Paint Ceiling Paint Wall Paint Wall Paint Ceiling Floor Buffing Floor Sanding Finish Finisharrow_forwardBelow matrix shows one of the important data used in project management, identify the name of the matrix and explain the roles of each person involved in this matrix.arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?arrow_forward
- Given the following data:ActivityPredecessorDuration (days)a-10b-15ca17db5eb4fc15gd7he8if12jg,h,i104.1 Draw the network (AON) and calculate and calculate the Critical Path. 4.2 Your organization has been appointed to co-ordinate the local government elections.Develop a Work Breakdown Structure (WBS) – graphical format for this project.arrow_forwarda) Draw the network diagram showing ES, EF, LS, LF, and the critical path. b) Perform CPM calculations and complete the table below. c) Crash the schedule one day at time and show the effect of crashing each activity on the network by crossing out values and writing the new ones immediately above or below it. d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. e) Draw the graph of the total cost corresponding to the crashing exercise: Activity IPA A B H Activity A B с D E F G A B B, C C D, F E, F G, H IPA A A B B, C C D, F Duration Normal 7 6 18 10 6 + 7 Duration 7 6 10 6 4 4 Crash 5 7 4 3 2 14 2 ES Cost $ Normal $500 $550 $800 $1,200 $600 $500 $700 $650 $300 EF Crash $640 $630 $935 $1,440 $700 $590 $1,000 $950 $300 LS LF TF FFarrow_forwardWhy is it critical to determine the sequence of activities in a project? Discuss diagrams that resemble network diagrams that you have seen. Compare and contrast their characteristics.arrow_forward
- Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks Compute the expected time for the task.arrow_forwardA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forwardPlease review this Gantt chart it should consist a minimum of 10 tasks Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks). Can you do it in excel format please Part 1 To prepare a Gantt chart for the FAO-funded Aquaponics Project in Barbados, we need to break down the project into individual tasks and then arrange them in a logical order based on their dependencies. Here is a table format Gantt chart for the project: Task Start Date End Date Duration Dependencies Project planning and initiation 01/01/2021 01/15/2021 15 days - Site selection and preparation 01/16/2021 02/15/2021 30 days Project planning and initiation Design and construction of facility 02/16/2021 04/15/2021 60 days Site selection and preparation Procurement of equipment and tools 04/16/2021 05/15/2021 30 days Design and construction of facility Training program development 05/16/2021 06/15/2021 30 days Procurement of equipment and tools Training program…arrow_forward
- Make a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardDraw a network diagram that represents the following activities of a project: Activity ImmediatePredecessor A - B A C A D C E B F D,E G F H D,E I G,Harrow_forwardDescribe your approach to tracking a project. What kinds of issues would you focus on if you were a project manager? Whyarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.