Concept explainers
The management of a factory is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table:
Construct the network for this project, identify the critical path, and determine the project duration time.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Additional Business Textbook Solutions
Operations Management
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management, Binder Ready Version: An Integrated Approach
Business in Action
Operations Management: Sustainability and Supply Chain Management (12th Edition)
- The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time? Activity Activity description Immediate predecessor Optimistic time (days) Most likely time (days) Pessimistic time (days) 1 Initiate move - 0 0 0 2 Prepare new building space 1 2 4 6 3 Pack faculty files and books 1 3 4 5 4…arrow_forwardThe Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table. Use POM- QM to analyze this project. According to the result of POM-QM, the expected project completion time is (type number only, no text) Activity a b C d C f 8 k Activity Description Position recruiting System development System training Equipment training Manual system test Preliminary system changeover Computer-personnel interface Equipment modification Equipment testing System debugging and installation Equipment changeover Activity Predecessor a a b, c b, c d, e d, e h f.g a 5 3 4 5 I 1 3 Time Estimates (weeks) 1 1 2 5 m 8 12 7 8 I 4 6 2.5 1. 2 8 b 17 15 10 23 1 13 9 7 1 2 11arrow_forwardThe table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities. Activity Expected Time (weeks) Preceding activities A 5 None B 4 None C 10 A D 8 B E 14 B F 6 C, D G 7 D, E, F H 3 F, G Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram. Calculate the slack time for each activity.arrow_forward
- You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities. ID Description A Prepare site BCDEFCHT G I J K Pour foundation Erect frame Roof Windows Doors Electrical с Rough-in frame D, E, F, G F, G H, I J Door opener Paint Cleanup The project will take The critical activities are Predecessor None A B с C The early start on Activity Dis The late start on Activity E is The slack on Activity E is The slack on Activity Fis Time (days) 6 1 5 2 3 3 5 2 1 5 days. days. days. days. days.arrow_forwardGiven the following network and activity time estimates, determine: The expected time and variance for each activity Complete the chart showing bout the EF and LFarrow_forwardThe table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?arrow_forward
- 11-16 Jean Walker is making plans for spring break at the beaches in Florida. In applying techniques she learned in her quantitative methods class, she has identified the activities that are necessary to prepare for her trip. The following table lists the activities and the immediate predecessors. Draw the network for this project. 11-17 The following are the activity times for the project in Problem 11-16. Find the earliest, latest, and slack times for each activity. Then find the critical path. These problems go together and are deterministic times.arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 4 6 А, В А, В 5 6 7 D 7 9 10 E B 4 6 F 1 2 G 5 8 10 H D, F 8 10 I E, G, H 3 4 5 a) What are the critical…arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6. в 4 6 А, В A, B 5 6 7 D 7 9 10 E в 2 4 6 F 1 2 3 G D 5 8 10 H D, F 6 8 10 I E, G, H 3 4 5 a) What is the…arrow_forward
- A new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 2 4 6 A, B A, B 5 6 7 D 7 9 10 E B 2 4 6 F 1 2 3 G D 5 8. 10 H D, F 6. 8. 10 I E, G, H 3 4 5 a) What is the…arrow_forwardA farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Description Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building Paint finish Check out facility Activity Predecessor b, c, d b e, f a. Draw a complete network for the above problem. b. Determine the critical path and the expected completion time. c. Show a table of detailed activity schedule. Activity Duration (weeks) 2 6 4 3 2arrow_forwardDraw the project network chart. Show ES, EF, LS, LF, and Slack on the project activity node for all activitiesarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.