Chapter 9, Problem 12P
Given the following network and probabilistic activity time estimates, determine the expected time and variance for each activity and indicate the critical path:
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Duration and requirement of workforce for each activity is tabulated below for a network
Activity
Duration
Number of men
1-2
3
5
2-4
2
3
2-3
3
7
3-4
0
0
3-5
3
2
4-5
7
2
3-6
2
1
5-6
6
6
4-6
5
5
(i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce
(ii) Indicate the maximum crew size in each case
(iii) Re-schedule the activities for smooth development
(iv) Find the project schedule if only 4 men are available
Given the following network and probabilistic activity timeestimates, determine the expected time and variance foreach activity and indicate the critical path:
Construct a PERT network from the following table. Find the critical path and variance for each
event, if tō, tp, and to represent most optimistic, most pessimistic, and most likely times
respectively.
Activity 1 - 2 1 3
to
4
1
tp
tm
1
3
2-4 2
7
1
3
5
7
3 4 3- 6 4 - 5
2
9
2
5
3
4-6 5
6
3
-
1
3
6-7
7
6
2
Chapter 9 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 9 - Why is CPM/PERT a popular and widely applied...Ch. 9 - What is the purpose of a CPM/PERT network?Ch. 9 - Why are dummy activities used in a CPM/PERT...Ch. 9 - What is the critical path, and what is its...Ch. 9 - What is slack, and how is it computed?Ch. 9 - How are the mean activity times and activity...Ch. 9 - How is total project variance determined in...Ch. 9 - What is the purpose of project crashing analysis?Ch. 9 - Describe the process of manually crashing a...Ch. 9 - Which method for determining activity time...
Ch. 9 - Explain how a Gantt chart differs from a CPM/PERT...Ch. 9 - Discuss the relationship of direct and indirect...Ch. 9 - Describe the limitations and disadvantages of...Ch. 9 - Describe the difference between activity-on-node...Ch. 9 - Identify and briefly describe the major elements...Ch. 9 - Select an everyday project you are familiar with...Ch. 9 - Prepare a WBS for a spaghetti with meatballs...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Use the project activities that follow to...Ch. 9 - Construct a network from the information in the...Ch. 9 - For the network in Problem 9.4, determine the...Ch. 9 - Given the following network with activity times in...Ch. 9 - Given the following network with activity times in...Ch. 9 - A marketing firm is planning to conduct a survey...Ch. 9 - In one of the little-known battles of the Civil...Ch. 9 - A group of developers is building a new shopping...Ch. 9 - The management of a factory is going to erect a...Ch. 9 - Given the following network and probabilistic...Ch. 9 - The Farmers American Bank of Leesburg is planning...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
••• 4.13 As you can see in the following table, demand for heart transplant surgery at Washington General Hospi...
Operations Management
The break-even point in dollars per month. Introduction: Break-even point (BEP): The break-even point is measur...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Consider the sales data for Computer Success given in Problem 7. Use a 3-month weighted moving average to forec...
Operations Management: Processes and Supply Chains (11th Edition)
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forwardQUESTION 7 The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following Table 6: Table 6 Activity Description A B с D E F G H I J K Activity Description Order new machinery Plan new physical layout Determine safety changes in existing machinery Receive equipment Hire new employees Make plant alterations Make changes in existing machinery Train new employees Install new machinery…arrow_forwardA group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.arrow_forward
- A farm owner is going to erect a maintenance building with connecting electrical gen- erator and water tank. The activities, activity descriptions and estimated durations are given in the following table. Construct the AOA network for this project, identify the critical path and construct a Gantt chart for the project. Description Excavate Erect building Install generator Install tank Activity A Predecessor Duration 2 B A 6 A 4 D A E Install maintenance equipment В 4 F Connect generator and tank building B,C,D 5 G Paint finish В 3 H Check out facility E,F 2arrow_forwardThe following is the data available for a project: Activity Predecessor Expected Duration (Days) A - 12 B A 9 C B,E 3 D - 10 E D 6 F E 3 G - 2 H G 9 I E,H 2 Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity. Draw the network diagram for the project and determine the critical patharrow_forwardConstruct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:arrow_forward
- Consider a project for which the following activities and time estimates in weeks apply activity To tm tp 1-2 3 5 8 1-3 2 3 5 1-5 2 3 4 2-3 1 2 5 2-6 7 8 9 3-4 1 3 6 3-5 2 4 6 4-5 1 2 4 5-6 1 2 3 Draw the project network Compute the expected time and variance for each activity iii. Compute slack for each event and find the critical path Find the length of the critical path and the project duration Approximate the probability that activity 3 – 4 will have positive slack. What is the managerial implication of that probability?arrow_forwardIn one of the little-known battles of the Civil War, General Tecumseh Beauregard lost the Third Battle of Bull Run because his preparations were not complete when the enemy attacked. If the critical path method had been available, the general could have planned better. Suppose that the following planning network, with activity times in days, had been available: Determine the earliest and latest activity times and the activity slack for the network. Indicate the critical path and the time between the general’s receipt of battle orders and the onset of battle.arrow_forwardillustrate unscaled activity bar type of early start and late startarrow_forward
- You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities. ID Description A Prepare site BCDEFCHT G I J K Pour foundation Erect frame Roof Windows Doors Electrical с Rough-in frame D, E, F, G F, G H, I J Door opener Paint Cleanup The project will take The critical activities are Predecessor None A B с C The early start on Activity Dis The late start on Activity E is The slack on Activity E is The slack on Activity Fis Time (days) 6 1 5 2 3 3 5 2 1 5 days. days. days. days. days.arrow_forwardThe Farmer’s American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table: Determine the expected project completion time and variance and determine the probability that the project will be completed in 40 weeks or less.arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 4 6 А, В А, В 5 6 7 D 7 9 10 E B 4 6 F 1 2 G 5 8 10 H D, F 8 10 I E, G, H 3 4 5 a) What are the critical…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY