To determine: The sensitivity to the problem in terms of the probability estimate of 0.35.
Introduction: Decision making is the procedure of selecting choices by identifying a decision, obtaining information and evaluating alternative resolutions. Always, step-by-step decision making process can help to make more deliberate, and thoughtful decisions in the organization.
a)
Answer to Problem 8P
Explanation of Solution
Given information:
It is given that the lease of theme part is about to expire. The management should decide whether to renew the lease for another 10 years or relocate the motel. The details about the two alternatives are as follows:
Options | Motel approved | Motel rejected |
Renew | $500,000 | $4,000,000 |
Relocate | $5,000,000 | $100,000 |
Determine the sensitivity of the problem:
The graph shown below contains the range of values of probability of approved motel where the alternative is optimal:
If the value is low, renewal is best with the highest expected value.
If the value is high, relocate is best with the highest expected value
Slope of renew:
Equation for renew:
Slope of relocate:
Equation for renew:
Determine the intersection between two lines:
It can be determined by equaling the equations of renew and relocate.
Optimal ranges are as follows:
Renew:
Relocate:
b)
To determine: The sensitivity to the problem in terms of the probability estimate of 0.45.
Introduction: Decision-making is the process that helps to make decision. It is the process of choosing a best alternative by evaluating many alternatives.
b)
Answer to Problem 8P
Explanation of Solution
Given information:
It is given that the lease of theme part is about to expire. The management should decide whether to renew the lease for another 10 years or relocate the motel. The details about the two alternatives are as follows:
Options | Motel approved | Motel rejected |
Renew | $500,000 | $4,000,000 |
Relocate | $5,000,000 | $100,000 |
Determine the sensitivity of the problem:
The graph shown below contains the range of values of probability of approved motel where the alternative is optimal:
If the value is low, renewal is best with the highest expected value.
If the value is high, relocate is best with the highest expected value
Slope of renew:
Equation for renew:
Slope of relocate:
Equation for renew:
Determine the intersection between two lines:
It can be determined by equaling the equations of renew and relocate.
Optimal ranges are as follows:
Renew:
Relocate:
Conclusion: It is given that the percentage is 0.45 which is less than .4643. Hence, renew should be selected.
c)
To determine: The range of payoff for renew reject for the selected alternative.
Introduction: Decision-making is the process that helps to make decision. It is the process of choosing a best alternative by evaluating many alternatives.
c)
Answer to Problem 8P
Explanation of Solution
Given information:
It is given that the lease of theme part is about to expire. The management should decide whether to renew the lease for another 10 years or relocate the motel. The details about the two alternatives are as follows:
Options | Motel approved | Motel rejected |
Renew | $500,000 | $4,000,000 |
Relocate | $5,000,000 | $100,000 |
The estimated payoff except for $4 million and the probability of approval is 0.35.
Determine the payoff:
Renew:
X should be plugged in instead of 4,000,000 in the above equation
Relocate:
Equal the equations of renew and relocate to solve x:
Equations of renew and relocate should be equaled to determine the value of x.
The original decisions at payoff is $4,000,000 should be decreased to $2,523,077 for the decision to change from renew to relocate.
When x is $2,523,077, there would be indifference between renew and relocate.
When x is less than $2,523,077, the decision would be changed to relocate.
Want to see more full solutions like this?
Chapter 5 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- In Benefit/cost ratio analysis, if the salvage value is used to recover the first cost, it is being considered as: Select one: a. negative cost b. cost c. benefit d. disbenefit =================== Ali takes out a loan at 10 percent compounded annually for 7 years. At the end of this period, he pays off the loan at a value of $23,384.61. What amount did he borrow? Select one: a. $12,000.00 b. $15,000.00 c. $14,000.00 d. $13,000.00 ============= While considering the engineering economy concepts, the most important tense almost all exercises deal with is the annual worth. Select one: True False Ans allarrow_forwardkindly answer b c d as per the guidelines, pls answer it manually thanks!arrow_forward(see attached image, kindly answer it based on your knowledge, thank you!)arrow_forward
- Suppose that the management of Theme Park, Inc., has decided that there is a.35 probability that the motel’s application will be approved.a. If management uses maximum expected monetary value as the decision criterion, which alternative should it choose?b. Represent this problem in the form of a decision tree.c. If management has been offered the option of a temporary lease while the town planning boardconsiders the motel’s application, would you advise management to sign the lease? The leasewill cost $24,000.arrow_forward( Use an excel sheet to show formulas used )arrow_forwardA national survey indicated that 30% of adults conduct their banking online. It also found that 40% are under the age of 50, and that 25% are under the age of 50 and conduct their banking online. A. What is the probability that an individual conducts banking online given that the individual is under the age of 50? B. Are Banking Online and Age independent? Explain.arrow_forward
- In November 2023, a certified investment property appraiser was hired to appraise the value of a 72,000 square foot Safeway anchored neighborhood shopping center in Fremont, California that was last sold in 2014 to a foreign investment company based in the Cayman Islands for $26 million. The November 2023 appraised value represents the: a. Actual market value of that property b. Actual purchase price of that property c. Actual replacement cost of that property d. Actual opinion of value by that appraiserarrow_forward11. Bakery Products is considering the introduction of a new line of pastries. In order to produce the new line, the bakery is considering either a major or a minor renovation of its current plant. Bill Wicker, head of operations, has developed the following conditional values table: Alternatives Favorable Market Unfavorable Market Major renovation $100,000 -$90,000Minor renovation $40,000 -$20,000 Do nothing $0 $0 Assume that the probability of a favorable market is equal to the probability of an unfavorable market.Part 2a) Choose the appropriate decision tree showing payoffs and probabilities.A.MinorFavorable40,000Unfavorable-20,000UnfavorableFavorableMajor100,000-90,000Do…arrow_forwardA manager is quite concerned about the recent deterioration of a section of the roof on a building that houses her firm's computer operations. According to her assistant there are three options which merit consideration: I, II, and III. Moreover, there are three possible future conditions that must be included in the analysis: A, which has a probability of occurrence of .25; B, which has a probability of .6; and C, which has a probability of .15. If condition A materializes, I will cost $12,000, II will cost $20,000, and III will cost $16,000. If condition B materializes, the costs will be $15,000 for I, $18,000 for II, and $14,000 for III. If condition C materializes, the costs will be $10,000 for I, $15,000 for II, and $19,000 for III. (A) Draw a decision tree for this problem. (B) Using expected monetary value, which alternative should be chosen?arrow_forward
- A manager is quite concerned about the recent deterioration of a section of the roof on a building that houses her firm’s computer operations. According to her assistant there are three options which merit consideration: I, II, and III. Moreover, there are three possible future conditions that must be included in the analysis: A, which has a probability of occurrence of .25; B, which has a probability of .6; and C, which has a probability of .15. If condition A materializes, I will cost $12000, II will cost $20000, and III will cost $16000. If condition B materializes, the costs will be $15000 for I, $18000 for II, and $14000 for III. If condition C materializes, the costs will be $10000 for I, $15000 for I, and $19000 for III. (A) Draw a decision tree for this problem. (B) Using expected monetary value, which alternative should be chosenarrow_forwardOption 2: Raise prices by 50%. If this occurs, there is a 75% chance that an Entrepreneur will set up in competition this year. The board’s estimate of its annual profit in this situation would be as follows: 2A: With new competitor 2B: Without new competitor Probability Profit (Sh.) Probability Profit (Sh.) 0.25 150,000 0.5 200,000 0.5 120,000 0.3 150,000 0.25 80,000 0.2 100,000 Option 3: Expand the car park quickly at a cost of Sh. 50,000 keeping prices theSame. The profits are then estimated to be like 2B above, except that the probabilities would be 0.6, 0.3 and 0.1 respectively. Required: Draw a decision tree for the above problem, including all the relevant data. Using expected values analyze the decision tree and recommend the best option to the owners of the car park.arrow_forwardAn oil company must decide whether or not to drill an oil well in a particular area that they already own. The decision maker (DM) believes that the area could be dry , reasonably good or a bonanza. See data in the table which shows the gross revenues for the oil well that is found. Decision Dry (D) Reasonably good(G) Bonanza(B) Drill $0 $85 $200 m Abandon $0 $0 $0 Probability 0.3 0.3 0.4 Drilling costs 40M. The company can take a series of seismic soundings ( at a cost of 12M) to determine the underlying geological structure. The results will be either “no structure”, “open structure or “closed structure”. The reliability of the testing company is as follows that is, this reflects their historical performance. Note that if the test result is “no structure” the company can sell the land to a developer for 50 m, otherwise (for the other results) it can abandon the drilling idea at no benefit to itself.…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.