A company must decide which type of machine to buy, and how many units of that type, given the following information:
Product demand and processing times for the equipment are:
a. How many machines of each type would be required to handle demand if the machines will operate 8 hours a day, 250 days a year, and what annual capacity cushion in processing time would result for each?
b. With high certainty of annual demand, which type of machine would be chosen if that was an important consideration?
c. If purchasing and operating costs are taken into account, which type of machine would minimize total costs, given your answer for part a? Operating costs are $6/hr for type 1 and $5/hr for type 2.
a)

To determine: The number of machines of each type required to handle the demand and its capacity.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the number of machines of each type required and its capacity:
It is given that the machines will operate 60 minutes per hour, 8 hours per day and 250 days per year.
Determine the minutes available for machine type 1:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 1 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 1:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 1. Hence, the processing requirements of product 001 using machine type 1 is 48,000 minutes.
Determine the processing requirement of product 002 using machine type 1:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 1. Hence, the processing requirements of product 002 using machine type 1 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 1:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 1. Hence, the processing requirements of product 003 using machine type 1 is 90,000 minutes.
Determine the total processing requirement using machine type 1:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the needed number of machine type 1:
It is calculated by dividing the total processing requirement and available minutes for machine type 1. Hence, the needed number of machine type 1is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 1 needed and the available minutes for machine type 1. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
Determine the minutes available for machine type 2:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 2 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 2:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 2. Hence, the processing requirements of product 001 using machine type 2 is 72,000 minutes.
Determine the processing requirement of product 002 using machine type 2:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 2. Hence, the processing requirements of product 002 using machine type 2 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 2:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 2. Hence, the processing requirements of product 003 using machine type 2 is 54,000 minutes.
Determine the total processing requirement using machine type 2:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the needed number of machine type 2:
It is calculated by dividing the total processing requirement and available minutes for machine type 2. Hence, the needed number of machine type 2 is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 2 needed and the available minutes for machine type 2. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
b)

To determine: The machine type that can be chosen for the high and low certainty of demand.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the machine type that can be chosen for the high and low certainty of demand:
The machine with the high capacity cushion should be selected, if the firm faced high certainty of annual demand. hence, machine type 2 should be selected.
The machine with the low capacity cushion should be selected, if the firm faced low certainty of annual demand. hence, machine type 1 should be selected.
c)

To determine: The machine type that would minimize the total cost, if purchasing and operating costs are considered.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Operating cost is given as $6 per hour for type 1 and $5 per hour for type 2.
Determine the purchase cost for machine type 1:
It is calculated by multiplying the number of machines and cost of type 1 machine. Hence, the purchase cost for machine type 1 is $20,000.
Determine the total operating time for machine type 1:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $22,800.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 1 and total operating cost. Hence, the total cost is $42,800.
Determine the purchase cost for machine type 2:
It is calculated by multiplying the number of machines and cost of type 2 machine. Hence, the purchase cost for machine type 2 is $28,000.
Determine the total processing requirement using machine type 2:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $18,000.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 2 and total operating cost. Hence, the total cost is $46,000.
Hence, Machine type 1 would minimize the total cost.
Want to see more full solutions like this?
Chapter 5 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Sam's Pet Hotel operates 51 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $11.00 per bag. The following information is available about these bags: > Demand 95 bags/week > Order cost $52.00/order > Annual holding cost = 25 percent of cost > Desired cycle-service level = 80 percent >Lead time 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 95 bags is incorrect and actual demand averages only 75 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)arrow_forwardSam's Pet Hotel operates 50 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.50 per bag. The following information is available about these bags: > Demand = 95 bags/week > Order cost = $55.00/order > Annual holding cost = 35 percent of cost > Desired cycle-service level = 80 percent > Lead time = 4 weeks (24 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 95 bags is incorrect and actual demand averages only 75 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $ 10.64 higher owing to the error in EOQ. (Enter your response rounded to two decimal places.) b. Suppose that actual demand is 75 bags but that ordering costs are cut to only $13.00 by using the internet to automate order placing. However, the buyer does…arrow_forwardBUS-660 Topic 4: Intege... W Midterm Exam - BUS-66... webassign.net b Answered: The binding c... × W Topic 4 Assignment - BU... how to get more chegg... b My Questions | bartleby + macbook screenshot - G... C Consider the following m... As discussed in Section 8.3, the Markowitz model uses the variance of the portfolio as the measure of risk. However, variance includes deviations both below and above the mean return. Semivariance includes only deviations below the mean and is considered by many to be a better measure of risk. (a) Develop a model that minimizes semivariance for the Hauck Financial data given in the file HauckData with a required return of 10%. Assume that the five planning scenarios in the Hauck Financial Services model are equally likely to occur. Hint: Modify model (8.10)-(8.19). Define a variable d for each 5 - scenario and let d≥ Ŕ – R¸ with d¸ ≥ 0. Then make the objective function: Min 1 5 Σας Let Min s.t. 15 FS = proportion of portfolio invested in the foreign…arrow_forward
- On a daily basis, the van is dispatched from Maplewood Hospital to pickup blood and platelet donations made at its local donation centers. The distances in miles between all locations may be found in the table below. Click the icon to view mileage data for Vampire Van. a. The van travels from the Hospital (A) to (B) to (C) to (D) to (E) and then returns to the Hospital (A). What is the total number of miles that the van must travel using this route? Route ABCDEA requires a total distance of miles. (Enter your response rounded to one decimal place.) More Info Maplewood City Center Westbrook Hospital (A) Donation Site (B) Donation Site (C) Municipal Park Donation Site (D) Valley Hills Donation Site (E) Maplewood 3.1 5.3 3.2 4.4 Hospital (A) City Center 3.1 6.7 2.2 4.3 Donation Site (B) Westbrook 5.3 Donation Site (C) 19 6.7 | 6.2 2.5 Municipal Park 3.2 2.2 6.2 | 4.6 Donation Site (D) Valley Hills 4.4 4.3 2.5 4.6 Donation Site (E) - ☑arrow_forwardThe Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? 0.099 hours per motorcycle. (Enter your response rounded to three decimal places.) If mixed-model scheduling is used, how many of each model will be produced before the production cycle is repeated? The greatest common divisor of the production requirements is Therefore, the Harvey Motorcycle Company will produce Goldens, LX2000s, and Tigers. (Enter your responses as integers.)arrow_forwardThe Harvey Motorcycle Company produces three models: the Tiger, a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a large interstate tourer. The month's master production schedule calls for the production of 32 Goldens, 31 LX2000s, and 38 Tigers per 10-hour shift. What average cycle time is required for the assembly line to achieve the production quota in 10 hours? hours per motorcycle. (Enter your response rounded to three decimal places.)arrow_forward
- The binding constraints for this problem are the second and third constraints are binding. Min x1 + 2x2 s.t. x1 + x2 ≤ 300 2x1 + x2 ≥ 400 2x1 + 5x2 ≥750 X1, X220 (a) Keeping the second objective function coefficient fixed at 2, over what range can the first objective function coefficient vary before there is a change in the optimal solution point? The first objective coefficient can from a low of to a high of (b) Keeping the first objective function coefficient fixed at 1, over what range can the second objective function coefficient vary before there is a change in the optimal solution point? The second objective coefficient can from a low of to a high of (c) If the objective function becomes Min 1.5x₁ + 2x2, what will be the optimal values of x1 and x2? x1 = X2 = What is the value of the objective function at the minimum? (d) If the objective function becomes Min 7x₁ + 6x2, what constraints will be binding? (Select all that apply.) First Constraint Second Constraint Third Constraint…arrow_forward[-16.66 Points] DETAILS MY NOTES CAMMIMS16 4.E.008. 0/1 Submissions Used A linear programming computer package is needed. ASK YOUR TEACHER PRACTICE ANOTHER The Clark County Sheriff's Department schedules police officers for 8-hour shifts. The beginning times for the shifts are 8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m. An officer beginning a shift at one of these times works for the next 8 hours. During normal weekday operations, the number of officers needed varies depending on the time of day. The department staffing guidelines require the following minimum number of officers on duty: Time of Day 8:00 A.M. Noon Noon - 4:00 P.M. Minimum Officers Time of Day on Duty 4 7 4:00 P.M. - 8:00 P.M. 11 8:00 P.M. Midnight 6 Midnight 4:00 A.M. 4:00 A.M. -8:00 A.M. 3 7 Determine the number of police officers that should be scheduled to begin the 8-hour shifts at each of the six times (8:00 a.m., noon, 4:00 p.m., 8:00 p.m., midnight, and 4:00 a.m.) to minimize the total number…arrow_forwarddiscuss in detail the benefits of working in a teamarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning