a)
To determine: The number of machines of each type required to handle the demand and its capacity and the machine that would have lower total cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
a)
Answer to Problem 11P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per unit | ||
A | B | C | ||
1 | 16,000 | 3 | 4 | 2 |
2 | 12,000 | 4 | 4 | 3 |
3 | 6,000 | 5 | 6 | 4 |
4 | 30,000 | 2 | 2 | 1 |
Determine the number of machines of each type required and its capacity:
It is given that the machines will operate 60 minutes per hour, 10 hours per day and 250 days per year.
Determine the minutes available for all types of machine:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type A, type B, and type C is 150,000 minutes per year.
Determine the processing requirement of product 1 using machine type A:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type A. Hence, the processing requirements of product 1 using machine type A is 48,000 minutes.
Determine the processing requirement of product 2 using machine type A:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type A. Hence, the processing requirements of product 2 using machine type A is 48,000 minutes.
Determine the processing requirement of product 3 using machine type A:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type A. Hence, the processing requirements of product 3 using machine type A is 30,000 minutes.
Determine the processing requirement of product 4 using machine type A:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type A. Hence, the processing requirements of product 4 using machine type A is 60,000 minutes.
Determine the total processing requirement using machine type A:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type A is 186,000 minutes.
Determine the needed number of machine type A:
It is calculated by dividing the total processing requirement and available minutes for machine type A. Hence, the needed number of machine type A is 2 machines.
Determine the processing requirement of product 1 using machine type B:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 64,000 minutes.
Determine the processing requirement of product 2 using machine type B:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 48,000 minutes.
Determine the processing requirement of product 3 using machine type B:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 36,000 minutes.
Determine the processing requirement of product 4 using machine type B:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 60,000 minutes.
Determine the total processing requirement using machine type B:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type B is 208,000 minutes.
Determine the needed number of machine type B:
It is calculated by dividing the total processing requirement and available minutes for machine type B. Hence, the needed number of machine type B is 2 machines.
Determine the processing requirement of product 1 using machine type C:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 32,000 minutes.
Determine the processing requirement of product 2 using machine type C:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 36,000 minutes.
Determine the processing requirement of product 3 using machine type C:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 24,000 minutes.
Determine the processing requirement of product 4 using machine type C:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 30,000 minutes.
Determine the total processing requirement using machine type C:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type C is 122,000 minutes.
Determine the needed number of machine type C:
It is calculated by dividing the total processing requirement and available minutes for machine type C. Hence, the needed number of machine type C is 1 machine.
Determine the total cost considering purchase cost of machine type A:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.
Determine the total cost considering purchase cost of machine type B:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $60,000.
Determine the total cost considering purchase cost of machine type C:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.
Hence, Buying 2 of the B machines at a total cost of $60,000 have lower total cost.
b)
To determine: The machine that would have lower total cost considering operating cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
b)
Answer to Problem 11P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per unit | ||
A | B | C | ||
1 | 16,000 | 3 | 4 | 2 |
2 | 12,000 | 4 | 4 | 3 |
3 | 6,000 | 5 | 6 | 4 |
4 | 30,000 | 2 | 2 | 1 |
Operating cost for machine A is $10 per hour, operating cost for machine B is $11 per hour, and operating cost for machine C is $12 per hour.
Calculate the total cost considering both purchasing cost and operating cost for machine A:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Calculate the total cost considering both purchasing cost and operating cost for machine B:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Calculate the total cost considering both purchasing cost and operating cost for machine C:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Hence, buying two B machines would have lower total cost.
Want to see more full solutions like this?
Chapter 5 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to use my forecast numbers to generate a Master Production Schedule (MPS) I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022 April 2023 I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.arrow_forwardSolve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forward
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,