Question
Chapter 5, Problem 2P
Summary Introduction
Interpretation: The volume of output that gives the lowest average unit cost of production at a facility.
Introduction:
The average unit cost of production is equal to the total cost or expenditure incurred to produce a quantity of goods divided by the quantity produced. Also, the concept of economies of scale is used for the determination of the average unit cost of production with respect to the volume of output.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Calculate the Total Pallet Capacity in a Warehouse with the following data:
Many terminals’ studies reported that a freight car spends an average of 62% per cent of its time in either terminal yards or intermediate yards, which is does not producing any revenue. The car spends only 14 per cent of its time in line haul operations and, of this, only 6.6 per cent in revenue producing service; from the theoretical background that you have, analyze the activities that consume most of the freight car time and assess the added value of these activities.
A retail catalog operation employs a bank of six telephone operators who process orders using computer terminals. When a terminal breaks down, it must be disconnected and taken to a nearby electronic repair shop, where it is repaired. The mean time between terminal breakdowns is six working days, and the mean time required to repair a terminal is two working days (both exponentially distributed). As a result of lost sales, it costs the mail-order operation an estimated $50 per day in lost profits each day a terminal is out for repair. The company pays the electronics repair shop $3000 per year on a service agreement to repair the terminals. The company is considering the possibility of signing a new service agreement with another electronics repair shop that will provide subsitutute terminals while the broken ones are at the repair shop. However, the new service agreement would cost the mail-order operation $15,000 per year. Assuming that there are 250 working days in a year, determine…
Chapter 5 Solutions
Practical Operations Management
Ch. 5 - Prob. 1DQCh. 5 - Prob. 2DQCh. 5 - Prob. 3DQCh. 5 - Prob. 4DQCh. 5 - Prob. 5DQCh. 5 - Prob. 6DQCh. 5 - Prob. 7DQCh. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - Prob. 3P
Ch. 5 - Prob. 4PCh. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 1.1QCh. 5 - Prob. 1.2QCh. 5 - Prob. 1.3QCh. 5 - Prob. 1.4QCh. 5 - Prob. 2.1QCh. 5 - Prob. 2.2QCh. 5 - Prob. 2.3QCh. 5 - Prob. 3.1QCh. 5 - Prob. 3.2QCh. 5 - Prob. 3.3QCh. 5 - Prob. 3.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- State some of the possible factors that could be responsible for food not being available at the right time to reach the residents in a healthcare facility ?arrow_forwardCalculate the electric energy requirement when all the vehicles are electrified. Pick an industry, location, or use of transportation. Calculate its current (ICE) energy usage. (either by total fuel consumption or total distance traveled) Calculate its projected (EV) energy usage.arrow_forwardWhatYouNeed is an online retailer with operations in Northern Indiana. Their network includes five big warehouses. All of the warehouses are fully automated: packaging is performed by robots on top of electric conveyors. Although the company has saved a lot in labor costs by the use of this packaging line, it has resulted in some excessive waste of material. After some analysis of this waste issue, the company has discovered that the number of product types that are assigned to the packaging line is strongly correlated with the amount of wasted material. Based on this insight, their operations manager has built a mathematical expression that estimates the expected amount of waste from the packaging line as a function of the number of product types in it. The expression is as follows: W = (n-93)2 – (n-88) + 227 In this expression, n is the number of product types you are packing on the line and W is the hourly waste of packaging material (in lbs). Based on this expression, what is the…arrow_forward
- WhatYouNeed is an online retailer with operations in Northern Indiana. Their network includes five big warehouses. All of the warehouses are fully automated: packaging is performed by robots on top of electric conveyors. Although the company has saved a lot in labor costs by the use of this packaging line, it has resulted in some excessive waste of material. After some analysis of this waste issue, the company has discovered that the number of product types that are assigned to the packaging line is strongly correlated with the amount of wasted material. Based on this insight, their operations manager has built a mathematical expression that estimates the expected amount of waste from the packaging line as a function of the number of product types in it. The expression is as follows: W = (n-93)2 – (n-88) + 227 In this expression, n is the number of product types you are packing on the line and W is the hourly waste of packaging material (in lbs). Based on this expression, how much will…arrow_forwardA warehouse has 2 docks for unloading. The arrival rate of trucks at the warehouse is 5 trucks per hour (Poisson distributed). The unloading rate is 4 trucks per hour (Poisson distributed). The driver- truck combination represents a cost of S275 per day. Each dock plus labor represents a cost of $900 per day. What's the minimum dock-crew and driver-truck cost (pick nearest answer)? a. 2364.10 b. 0.75 c. 1345.00 d. 2670.76 e. 0.25arrow_forwardSniparrow_forward
- A company has a factory that is designed so that it is most eficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardA manufacturing firm has four plants and wants to find the most efficient means of meeting the requirements of its four customers. The relevant information for the plants and customers, along with shipping costs in dollars per unit, are shown in the table below: Factory (capacity) A (100) B (75) C (100) D (250) Customer 1 (125) $15 $20 $22 $21 Customer (requirement) Customer 2 Customer 3 How many arcs will the network have? (150) $10 $12 $20 $15 (175) $20 $19 $25 $28 Customer 4 (75) $17 $20 $14 $12arrow_forwardThis effect is concerned with the firm being able to engage with the customer at the right place/time—its ability to do so 24/7 from any location. Select one: Network effect Timeliness Effect Dynamic Effect Connected Effectarrow_forward
- The owner of a fast-food franchise has exclusive rights to operate in a medium-sized metropolitan area. The owner currently has a single outlet open, which has proved to be very popular and there are often waiting lines for customers. The owner is therefore considering opening one or more outlets in the area. What are the main key factors that the owner should investigate before making a final decision?arrow_forwardPlease provide Minimum of 3 Alternative Courses of Action.arrow_forwardFour regional less-than-truckload (LTL) carriers handle shipments traveling from Lexington, Kentucky, to Springfield, Illinois. All four companies say that their normalservice time to deliver these shipments is two business days. The four carriers competewith each other on the basis of price and service quality rating, as shown in the following table. The price reported in the table is the (nondiscounted) cost per hundredweight(cwt) of sending a 600-pound shipment from Lexington to Springfield at freight class70. The service quality rating measures a carrier’s loss and damage record and goesfrom 0 (poor quality) to 100 (high quality). Which of these LTL carriers are on the efficient frontier?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,