Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 5, Problem 37P

a)

Summary Introduction

Interpretation:customer officer during time period.

Concept introduction:The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise it tends to be too variable of a distribution.

a)

Expert Solution
Check Mark

Answer to Problem 37P

The customer officer is busy 75% of the time.

Explanation of Solution

Given information:the scenario meets the assumptions of M/M/1 model

  arrival rate(λ) = 9 cars per houras the officer takes 5 minutes to inspect and release the car,the number of cars relaesed per minute is 15service rate(μ)=60×15=12 cars per hour

Explanation:

  we need to find the utilization,ρ.this is given as the ratio of arrival rate to the service rate.the utilization.ρ=λμ=912=0.75=75%.

b)

Summary Introduction

Interpretation: average wait to speak to the officer andthe probability that someone will be able to speak immediately upon arrival.

Concept introduction:The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise it tends to be too variable of a distribution.

b)

Expert Solution
Check Mark

Answer to Problem 37P

average wait to speak to the officer 15 minutes.

the probability that someone will be able to speak immediately upon arrival is 0.25.

Explanation of Solution

Given information:

  arrival rate(λ) = 9 cars per houras the officer takes 5 minutes to inspect and release the car,the number of cars relaesed per minute is 15service rate(μ)=60×15=12 cars per hour

Explanation:

Average wait time to speak to the office, Wq  is given using below formula

  Wq=λμ( μλ)average wait time is as given belowWq=912( 129)=936=14=0.25 hours=0.25×60 mins=15 mins

The probability that someone will be able to speak immediately upon arrival is the same as the probability of there being no cars in the system. This probability P0 is given as:

  P0=1λμ=1912=134=10.75=0.25

c)

Summary Introduction

Interpretation:the average cars present at the border crossing plaza during that time period.

Concept introduction:The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise it tends to be too variable of a distribution.

c)

Expert Solution
Check Mark

Answer to Problem 37P

the average cars present at the border crossing plaza during that time period is 3 cars.

Explanation of Solution

Given information:

  arrival rate(λ) = 9 cars per houras the officer takes 5 minutes to inspect and release the car,the number of cars relaesed per minute is 15service rate(μ)=60×15=12 cars per hour

Explanation:

The average cars present at the plaza during that period, L is given using the below formula

  L=λ2μ( μλ)+λμhence the average cars present at the plaza is as belowL=9212( 129)+912=8112×3+0.75=2.25+0.75=3

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY