Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

Question
Book Icon
Chapter 5, Problem 35P

a)

Summary Introduction

Interpretation: Average total time truck spends waiting.

Concept introduction: The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further, if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise it tends to be too variable of a distribution.

a)

Expert Solution
Check Mark

Answer to Problem 35P

average total time truck spends waiting20 mins.

Explanation of Solution

Given information:

  (λ)=15 per hour(μ)=18 trucks per hour

Explanation:

Average number of waiting

  LQ = λ2μ( μλ)= 15218( 1815)=22518(3)=4.16average wait timedelayWQ =LQλ=4.1615=0.27average system timeWS = 1( μλ)=1( 1815)=0.33×60=20 mins.

b)

Summary Introduction

Interpretation: Probability of arriving truck must wait.

Concept introduction: The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise it tends to be too variable of a distribution.

b)

Expert Solution
Check Mark

Answer to Problem 35P

probability of arriving truck must wait 0.1416 or 14.12%.

Explanation of Solution

Given information:

  (λ)=15 per hour(μ)=18 trucks per hour

Explanation:

Probability of 0 in the system

  P0 = 1-(λμ)P0=1( 15 18)=0.17 or 17%

Probability of N number in a queue at least 1 in the queue

  PN=P0×( λ μ)NN= number of customerN=1P1=0.17×( 15 18)1=0.1416 or 14.12%

c)

Summary Introduction

Interpretation: Trucks waiting in line.

Concept introduction: The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further, if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise, it tends to be too variable of a distribution

c)

Expert Solution
Check Mark

Answer to Problem 35P

4.17 trucks waiting in line

Explanation of Solution

Given information:

  (λ)=15 per hour(μ)=18 trucks per hour

Explanation:

Average number of customers waiting

  LQ = λ2μ( μλ)= 15218( 1815)=4.166 or 4.17

d)

Summary Introduction

Interpretation: Trucks at the weigh station

Concept introduction: The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further, if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise, it tends to be too variable of a distribution

d)

Expert Solution
Check Mark

Answer to Problem 35P

3 trucks at the weigh station.

Explanation of Solution

Given information:

  (λ)=15 per hour(μ)=18 trucks per hour

Explanation:

Average number of trucks in the system

  LS =λ( μλ)=15( 1815)=3

e)

Summary Introduction

Interpretation: Probability of no more than 3 trucks at weigh station.

Concept introduction: The M/M/1 queue assumes poison arrivals, exponential service times, and a single server serving customers in a FCFS fashion. Poisson arrivals are a reasonably good assumption for unscheduled systems. Further, if there is a mix of many different types of jobs the exponential distribution can be realistic for service times. Otherwise, it tends to be too variable of a distribution.

e)

Expert Solution
Check Mark

Answer to Problem 35P

0.096 probability of no more than 3 trucks at weigh station.

Explanation of Solution

Given information:

  (λ)=15 per hour(μ)=18 trucks per hour

Explanation:

N = not more than 3 trucks

  PN=( λ μ)N(1λμ)=( 15 18)3(1 15 18)=0.096

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L