Chapter 4.3, Problem 7P
Summary Introduction
To modify: The original model to minimize the objective function to minimize the weekly payroll and to identify if the previous solution is still optimal.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Consider Miller Chemicals that produces water purification crystals for swimming pools. The major inputs used in the production process are labor, raw materials and energy. The
labor costs are $200,000; raw materials costs are $80,000; and energy costs are $9,000.
Labor costs in year two are $350,000; raw materials costs $95,000; and energy costs $11,000.
Labor costs in year three are $350,000; raw materials costs $40,000; and energy costs $6,000.
Miller Chemical produced 100,000 pounds of crystal in year 1; 150,000 pounds of crystals in year 2, and 184,500 pounds of crystals in
year 3.
(Enter your
The productivity in year two increases/decreases by
numbers only. Do not separate them with a comma or other marks)
and the productivity from year one to year two increases/decreases by
Forrester and Cohen is a small accounting firm, managed by Joseph Cohen since the retirement in December of his partner Brad Forrester. Cohen and his 3 CPAs together bill 620 hours
per month. When Cohen or another accountant bills more than 155 hours per month, he or she gets an additional "overtime" pay of $63.20 for each of the extra hours: this is above and
beyond the $4,900 salary each draws during the month. (Cohen draws the same base pay as his employees.) Cohen strongly discourages any CPA from working (billing) more than 250
hours in any given month. The demand for billable hours for the firm over the next 6 months is estimated below:
Month
Jan.
Feb.
Mar.
Apr.
Estimate of Billable Hours
600
500
1,020
1,230
640
570
May
June
Cohen has an agreement with Forrester, his former partner, to help out during the busy tax season, up to 250 hours in any given month if needed, for an hourly fee of $120. Cohen will not
even consider laying off one of his colleagues in the case of a slow…
Forrester and Cohen is a small accounting firm, managed by Joseph Cohen since the retirement in December of his partner Brad Forrester. Cohen and his 3 CPAS together bill 640 hours per month. When Cohen or another accountant bills more than 160 hours per month, he or she gets an additional "overtime" pay of $63.80
for each of the extra hours: this is above and beyond the $5,100 salary each draws during the month. (Cohen draws the same base pay as his employees.) Cohen strongly discourages any CPA from working (billing) more than 245 hours in any given month. The demand for billable hours for the firm over the next 6 months is
estimated below:
Month
Estimate of Billable Hours
Jan.
600
Feb.
500
Mar.
1,020
Apr.
1,210
May
660
June
590
Cohen has an agreement with Forrester, his former partner, to help out during the busy tax season, up to 245 hours in any given month if needed, for an hourly fee of $135. Cohen will not even consider laying off one of his colleagues in the case of a slow…
Chapter 4 Solutions
Practical Management Science
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - You want to take out a 450,000 loan on a 20-year...Ch. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Question: 1. Which Process…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the traditional…arrow_forward
- A company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardAG Sdn Bhd is an upcoming unit trust company led by Mr. Boo. This type of business relies heavily on the number of clients they obtain. This strategy will ensure their long-term business sustainability. Boo urges his staff to seek and gather clients and at the same time to aggressively promote their unit trust funds. Being a single man, he works tirelessly day and night and expects his staff to do the same. His employees consist mainly of school leavers who are mostly from the Baby Boomers or Generation Y categories. Hence, marketing methods are all set by Boo himself and all the agents are to follow the step-by- step process. Q1. (a) Required: Guided by McGregor's Theory X and Theory Y, evaluate Boo's managerial style.arrow_forward
- Forrester and Cohen is a small accounting firm managed by Joseph Cohen since the retirement in December of his partner, Brenda Forrester. Cohen and his 3 CPAS together bill 620 hours per month. When Cohen or another accountant bills more than 155 hours per month, he or she gets an additional "overtime" pay of $63.20 for each of the extra hours. This is above and beyond the $4,900 salary each draws during the month. (Cohen draws the same base pay as his employees.) Cohen strongly discourages any CPA from working (billing) more than 250 hours in any given month. The demand for billable hours for the firm over the next 6 months is estimated below. attempted Cohen has an agreement with Forrester, his former partner, to help out during the busy tax season, up to 250 hours in any given month if needed, for an hourly fee of $135. Cohen will not even consider laying off one of his colleagues in the case of a slow economy. He could, however, hire another CPA at the same salary as business…arrow_forwardForrester and Cohen is a small accounting firm managed by Joseph Cohen since the retirement in December of his partner, Brenda Forrester. Cohen and his 3 CPAs together bill 640 hours per month. When Cohen or another accountant bills more than 160 hours per month, he or she gets an additional "overtime" pay of $62.50 for each of the extra hours. This is above and beyond the $5,000 salary each draws during the month. (Cohen draws the same base pay as his employees.) Cohen strongly discourages any CPA from working (billing) more than 250 hours in any given month. The demand for billable hours for the firm over the next 6 months is estimated below. Month Jan. Feb. Mar Apr. Estimate of Billable Hours 600 490 1,010 1,220 660 570 O May June Cohen has an agreement with Forrester, his former partner, to help out during the busy tax season, up to 250 hours in any given month if needed, for an hourly fee of $120. Cohen will not even consider laying off one of his colleagues in the case of a slow…arrow_forwardPlease step by step answer.arrow_forward
- A company makes four products that have the following characteristics: Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 of materials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for $135 but needs $105 of materials to produce. The processing requirements for each product on each of the four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardless of how much the worker is used. Answer the following…arrow_forwardPlease explain both subpartsarrow_forwardFormulate the situation as a system of inequalities. (Let x represent the number of dinghies the company can manufacture and y represent the number of rowboats.) A boat company manufactures aluminum dinghies and rowboats. The hours of metal work and painting needed for each are shown in the table, together with the hours of skilled labor available for each task. How many of each kind of boat can the company manufacture? (hours) Dinghy Rowboat Labor Available Metal Work 2 3 108 Painting 2 2 90 (labor for metal work) (labor for painting) x ≥ 0, y ≥ 0arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,