Question
Chapter 4, Problem 110P
Summary Introduction
To determine: The way to maximize the number of consecutive days off received by these employees.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A manufacturing plant produces a product 'A' that requires one unit of 'B' and ½ unit of 'C'. Each unit of 'B' is comprised of one unit of 'D', two units of 'E', and one unit of 'F'. Each unit of 'C' requires ½ unit of 'G' and three units of 'H'. The manufacturing lead times for the components are as follows: 'A' - two weeks, 'B' - one week, 'C' - two weeks, 'D' - two weeks, 'E' - three weeks, 'F' - one week, 'G' - two weeks, 'H' - one week. There are 20 units in stock for each of these components. 100 units of 'A' are needed for delivery in seven weeks: a) Develop the product structure and indexed bill of materials for the product. b) Create a gross and net requirements plan for the manufacturer of the product.
Mr. Elf owns a show store. Currently, he has 10 pairs of shoes that require resoling and polishing. He has a machine that can resole one pair of shoes at a time, and the time required for
the operation varies with the type and condition of the shoe and the type of sole that is used. Shoes are polished on a machine dedicated to this purpose as well, and polishing is always
done after resoling. His assistant generally does the polishing while Mr. Elf does the resoling. The resoling and polishing times (in minutes) are:
Shoes
1
Resoling Time
14
Polishing Time
3
2
28
1
3
12
2
4
6
5
5
10
10
6
14
6
7
4
12
8
25
8
9
10
15
10
5
5
Determine the sequence in which these shoes should be repaired to minimize the total makespan for these 10 jobs, and answer the following questions.
Based on the optimal sequence: (Enter integer only)
1. The first job to be processed is Job
2. The third job to be processed is Job
3. The fourth job to be processed is Job
4. The fifth job to be processed is Job
5. The…
An industrial engineer has designed two alternative methods for accomplishing
a production job. Both methods involve the acquisition of the same working place
and other capital equipment to be used for this job only.
Method A calls for a crew consisting of three men each costing Php30/hr.
This method will result in the production of 10 units per hour of which two will be
reject.
Method B calls for a crew of two men each costing Php35/hr and should
result in the production of eight units per hour of which one will be reject.
The cost of the direct material lost in each reject is Php20. If a certain total
number of units is to be produced find which method is economical?
Chapter 4 Solutions
Practical Management Science
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - You want to take out a 450,000 loan on a 20-year...Ch. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- JOHNSON’S RULE Five specialty jobs at a La Crosse, Wisconsin, tool and die shop must be processed through two workcenters (drill press and lathe). The time for processing each job follows:Work (processing) Time for Jobs (hours)JOBWORK CENTER 1(DRILL PRESS) WORK CENTER 2(LATHE)A5 2B3 6C8 4D 10 7E 7 12arrow_forwardA company produces motor cycle seats. The company has two production lines. The production rate for line one is 50 seats per hour and for line two it is 60 seats per hour. The company has entered into a contract to supply1200 seats daily to another company. Currently, the normal operation period for each line is 8 hours. The production manager 4 | P a g eof the company is trying to determine the best daily operation hours for the two lines. He sets the priorities to achieve his goals as given below:- P1: produce and deliver 1200 seats daily- P2: limit the daily overtime operation hours of line one to 3 hours- P3: Limit the daily overtime operation hours of line two to 4 hours Formulate the problem as a GP model and then solve it by using graphical methodarrow_forwardThe Stratton Company produces two basic types of plastic pipe. Three resources are crucial to the output of pipe: extrusion hours, packaging hours, and a special additive to the plastic raw material. The following data represent next week’s situation. All data are expressed in units of 100 feet of pipe. Product Resource Type 1 Type 2 Resource Availability Extrusion Packaging Additive mix 4 hr 2 hr 2 lb 6 hr 2 hr 1 lb 48 hr 18 hr 16 lb The contribution to profits and overhead per 100 feet of pipe is $34 for type 1 and $40 for type 2. Formulate a linear programming model to determine how much of each type of pipe should be produced to maximize contribution to profits and to overhead, assuming that everything produced can be sold.arrow_forward
- A consulting company must hire 15 new associates per year to replace those who haveleft the company for other positions or have retired. The company employs 120 associates overall. How long is the average associate employed at the consulting company?arrow_forwardAn order for 200 units of a product is processed on work centers A and B. The set up time on A is 45 minutes and the run time is 5 minutes per piece. The set up time on B is 40 minutes and the run time is 8 minutes per piece. The wait time between the two operations is 2 hours. The move time between A and B is 15 minutes. Wait time after operation B is 1 hour and the move time into stores is 50 minutes. There is no queue at either work station. Calculate the total manufacturing lead time for the order.arrow_forwardA custom motor cycle shop is experiencing high demand from its customers for its services. The owner performs all tasks relating to customization. Assume each customer brings one motor cycle for customization. The owner needs to determine if he needs to add more help to meet customer demand. A week has 40 hours ( maximum amount of time for the owner to work) The maximum number of customizations that can be done per week is 10 bikes ( if there is no wasted time). The following is the data collected from observations for a typical week : Every Friday the shop is cleaned by the owner. This takes 4 hours. - 15 % of the customizations needs rework which takes 50 % more time than regular customization - 10 % of the customers will be called by the owner. This takes 2 hours per customer. Determine OEE. How should the owner handle the business ? Show all formulas used, calculations and results. Do on Blk Bd For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac).arrow_forward
- NewTel is a telephone company with a policy of filling positions internally through promotions, rather than hiring from outside. Until recently, the company had a strong engineering focus and tended to promote people to senior executive positions from the engineering areas. Consequently, almost all of the company's 14 senior executives joined the company over 20 years ago as junior engineers. There is increasing pressure on NewTel to become more market and service oriented. As a result, four people were hired last year from firms to fill new senior executive positions in marketing and service departments. The external hires were necessary because current employees were not sufficiently qualified. Now, there are signs of tension among senior executives, particularly during budget deliberations where there is limited discretionary spending on new corporate activities. The four new hires have been thwarted in their attempts to have the company invest more in marketing and customer…arrow_forwardA serial process has 5 steps – A (4), B(5), C(2), D(6), and E(3) – that have to be performed in this order. The numbers in parentheses are the times (in minutes) needed to process a unit. For each unit produced by this process, the process has a total idle time of: Group of answer choices 1 min 10 mins 6 mins 3 minsarrow_forwardExcellent Co. Ltd was incorporated in 2001 and has currently 4 zones (namely, North, South, East, and West) open and 4 supervisors available for assignment. It is estimated that a typical supervisor operating in each zone would bring in the following annual turnover: North: 126,000; South: 105,000; East: 84,000; West: 63,000 The 4 supervisors are also considered to differ in supervisory competencies. It is estimated that working under the same conditions, the company’s yearly turnover would be proportionately as follows: Supervisor I: 7; Supervisor II: 5; Supervisor III: 5; Supervisor IV: 4 How should the company allocate the best supervisor to the various zones in order to maximize its total annual turnover? [5]arrow_forward
- Company ZWZ manufactures three products in a serial system; Product XA is manufactured in Stage 1, Product XB in Stage 2, and XC in Stage 3. Product XB has a sales potential in the market; hence, some of it can be sold at the end of Stage 2, and the remaining can be moved to Stage 3. The third stage produces Product XC, and then delivers it to customers. Two units of Product XA produced in Stage 1 are required for each unit of Product XB in Stage 2. In addition, four units of Product XB produced in Stage 2 are required for each unit of Product XC in Stage 3. Stage 1 can only use regular time; however, Stage 2 has the options of using regular time and overtime in manufacturing. On the other hand, Stage 3 has only one alternative, which is subcontracting. The pertinent data are provided below: Stage 2 Stage 1 11 No overtime No subcontracting No sales 0.07 Unit regular time cost (TL) Unit overtime cost (TL) Unit subcontracting cost (TL) Unit selling price (TL) Unit processing time (hrs)…arrow_forwardKAPC, a pharmaceutical company located in rural Kansas, is finding it difficult to retain its employees, who frequently leave after just six months of working at KAPC for jobs at pharmaceutical companies paying higher wages in Chicago. To address its problem with labor turnover, human resource officers at KAPC decide to run an experiment. Of their next 100 newly hired employees, 25 will randomly be selected to receive a housing voucher worth up to $4,000 per year to offset property taxes. To take advantage of this program, the employee must not only be randomly selected into the program but she must also purchase a home. Of the 25 employees selected into the housing voucher program, 7 leave KAPC within 12 months of starting. Of the 75 employees not selected into the program, 37 leave KAPC within 12 months of starting.a. Provide a difference-in-differences estimate of the effect the housing voucher program has on retention at KAPC.b. Suppose KAPC spends $10,000 in hiring costs each time…arrow_forwardA large business process outsourcing company operates 5 days a week (Monday to Friday). The manager estimates that the minimum number of agents requires, a combined on-site and work-from-home (WFH) setup, to provide prompt service: 20 for Monday, 18 for Tuesday, 23 for Wednesday, 28 for Thursday, and 32 for Friday. Labor rules state that each agent must work for 3 days a week on-site. and 2 days in WFH setup. For example. an agent who works on-site Monday to Wednesday must be on WFH setup during Thursday and Friday. Also. the company wants at least 60% of the workforce daily to report on-site. Formulate the appropriate LP model for this problem to minimize the number of agents to be hired.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,