Chapter 4, Problem 109P
Summary Introduction
To determine: The way to maximize the profit of Company F.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
There are two companies manufacturing drones. Company A manufactures mass market drones, while company B manufactures customised drones according to customers’ requirements. In 2020, company A produces 3,200 drones, 3% of which were found to be defective and cannot pass the quality check. Company A employs 5 workers working an average of 8 hours a day in the drone production, and they worked 200 working days in 2020.In contrast, company B produces 900 drones, 10% of which were found to be defective and cannot pass the quality check. Company B employs 3 workers working an average of 6 hours a day in the drone production, and they worked 170 days in 2020.
(a) If the drone manufacturing is seen as a process, what is considered as the output of the production processes of companies A and B and why?
(b) Measure the single-factor manpower productivity for the two companies.
(c) Is it reasonable to compare the manpower productivity of the two companies and reach a conclusion that one company…
A bhaliya
Three methods can be used for producing heat sensors for high-temperature furnaces. Method A will have a fixed cost of $140,000 per year and a production cost of $62 per part. Method B will have a fixed cost of $210,000 per year and a production cost of $28 per part. Method C will require the purchase of equipment costing $500,000. It will have a life of five years and a 25% of first cost salvage value. The production cost will be $53 per part. At an interest rate of 10% per year, determine the breakeven annual production rate between the two lowest cost methods.
Chapter 4 Solutions
Practical Management Science
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - You want to take out a 450,000 loan on a 20-year...Ch. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Memanarrow_forwardA solid steel shaft is to transmit a torque of 10kN - m If the shearing stress is not to exceed overline 45MPa find the minimum diameter of the shaft.A solid steel shaft is to transmit a torque of 10kN - m If the shearing stress is not to exceed overline 45MPa find the minimum diameter of the shaft. A solid steel shaft is to transmit a torque of 10kN - m If the shearing stress is not to exceed overline 45MPa find the minimum diameter of the shaft?arrow_forwardFRUIT COMPUTER COMPANY Fruit Computer Company manufactures memory chips in batches of ten chips. From past experience, Fruit knows that 80% of all batches contain 10% (1 out of 10) defective chips, and 20% of all batches contain 50% (5 out of 10) defective chips. If a good (that is, 10% defective) batch of chips is sent to the next stage of production, processing costs of $4000 are incurred, and if a bad batch (50% defective) is sent on to the next stage of production, processing costs of $16000 are incurred. Fruit also has the alternative of reworking a batch at a cost of $4000. A reworked batch is sure to be a good batch. Alternatively, for a cost of $400, Fruit can test one chip from each batch in an attempt to determine whether the batch is defective. QUESTIONS 1.Determine a strategy so Fruit can minimize the expected total cost per batch. 2.Compute the EVSI and EVPI.arrow_forward
- A company makes parts that cost $35.00 in material and labor. 92% of the parts are produced defect free and are sold for full price at $110 each. 2% of the parts made must be scrapped. Scrap parts are sold for $8.00 each. The remaining 6% of the parts made must be reworked at a cost of $12.00 each. After rework 1% still must be scrapped and the other 5% is sold at a discounted price of $90 each. a. Draw the tree diagram showing the quality cost situation. b. Determine the earnings per part. c. Determine the cost of poor quality (COPQ). d. Determine the earnings per part and COPQ if the rework operation was shut down and the parts that required reworking were just sold for scrap instead.arrow_forwardDigital Controis, Inc. (DCI), manufactures two models of a radar gun used by police to monitor the speed of automobiles. Model A has an accuracy of plus or minus 1 mile per hour, whereas the smaller model B has an accuracy of plus or minus 3 miles per hour. For the next week, the company has orders for 100 units of model A and 150 units of model B. Although DCI purchases all the electronic components used in both models, the plastic cases for both models are manufactured at a DCI plant in Newark, New Jersey. Each model A case requires 4 minutes of injection-molding time and 6 minutes of assembly time. Each model B case requires 3 minutes of injection-molding time and 8 minutes of assembly time. For next week, the Newark plant has 600 minutes of injection-molding time avallable and 1,080 minutes of assembly time availab The manufacturing cost is $10 per case for model A and $6 per case for model B. Depending upon demand and the time avalable at the Newark plant, DCI occasionally…arrow_forwardA large building may require an automated alarm system which monitors and controls all fire and security alarms in the building. Normally, the building is divided into zones and a number of alarms are associated with each zone. Alarms alert a central manned control area who may pass these on to the emergency services or may respond personally.Factors which have to be taken into account in building such a system are:Ø If the control area is unmanned and an alarm is activated this alarm should not be ignored if it is potentially serious. Emergency services should be automatically called.Ø Some but not all parts of the building may be equipped with sprinkler systems or systems to shut down electrical equipment. These should be activated if a fire alarm is confirmed. They should not be activated if there are people in the same room.Ø The building may be equipped with direction indicators which illuminate the route to the nearest exit. These should be activated when a fire alarm is…arrow_forward
- A Las Vegas, Nevada, manufacturer has the option to make or buy one of its component parts. The annual requirement is 20,000 units. A supplier is able to supply the parts for $10 per piece. The firm estimates that it costs $600 to prepare the contract with the supplier. To make the parts in-house, the firm must invest $50,000 in capital equipment, and the firm estimates that it costs $8 per piece to make the parts in-house. Assuming that cost is the only criterion, use breakeven analysis to determine whether the firm should make or buy the item. 1. What is the breakeven quantity? 2. Should the manufacturer Make or Buy? 3. What is the cost savings using your decision in number 2 (above)? Show the total cost for each scenario then the savings amount.arrow_forwardA roller coaster is being designed for a new theme park. Two "trains" are on the track at any given time. One train is being unloaded/reloaded while the other is moving along the track. The track itself takes 10 minutes to complete. The train being loaded should depart before the arriving train is no closer than one minute away. Each car of a train accommodates four people. Loading a car is estimated to take 6 seconds per passenger. Unloading is estimated to take 6 seconds per passenger. Suppose that (unlike actual roller coasters), only one car can be loaded or unloaded at a time. Unloading can NOT occur at the same time as loading. In order to maximize the number of potential passengers, how many cars should the train be made up of? Round your answer to the nearest whole car.arrow_forwardCompany ZWZ manufactures three products in a serial system; Product XA is manufactured in Stage 1, Product XB in Stage 2, and XC in Stage 3. Product XB has a sales potential in the market; hence, some of it can be sold at the end of Stage 2, and the remaining can be moved to Stage 3. The third stage produces Product XC, and then delivers it to customers. Two units of Product XA produced in Stage 1 are required for each unit of Product XB in Stage 2. In addition, four units of Product XB produced in Stage 2 are required for each unit of Product XC in Stage 3. Stage 1 can only use regular time; however, Stage 2 has the options of using regular time and overtime in manufacturing. On the other hand, Stage 3 has only one alternative, which is subcontracting. The pertinent data are provided below: Stage 2 Stage 1 11 No overtime No subcontracting No sales 0.07 Unit regular time cost (TL) Unit overtime cost (TL) Unit subcontracting cost (TL) Unit selling price (TL) Unit processing time (hrs)…arrow_forward
- A company owns a 5-year-old turret lathe that has a book value of $23,000. The present market value for the lathe is $18,000. The expected decline in market value is $1,700/year to a minimum market value of $4,080; maintenance plus operating costs for the lathe equal $4,470/year.A new turret lathe can be purchased for $46,000 and will have an expected life of 8 years. The market value for the turret lathe is expected to equal $46,000(0.70)k at the end of year k. Annual maintenance and operating cost is expected to equal $1,900. Based on a 12% MARR, should the old lathe be replaced now? Use an equivalent uniform annual cost comparison, a planning horizon of 7 years, and the cash flow approach.EUAC for keeping old turret lathe: $EUAC for replacing turret lathe: $arrow_forwardHalmar the Great has boasted to his hordes of followers that many a notorious villain has fallen to his awesome sword: His total of 500 victims consists of evil sorcerers, trolls, and orcs. These he has slain with a total of 600 mighty thrusts of his sword; evil sorcerers and trolls each requiring two thrusts (to the chest) and orcs each requiring one thrust (to the neck). When asked about the number of trolls he has slain, he replies, "I, the mighty Halmar, despise trolls four times as much as I despise evil sorcerers. Accordingly, four times as many trolls as evil sorcerers have fallen to my sword!" How many of each type of villain has he slain? sorcererstrollsorcsarrow_forwardMr. Ajit currently serves at a senior director with BSNL Mumbai. In his brigade of staff there are 10 supervisors and more than 200 telephone assistance operators. If any resident wants to call 197 for directory assistance ,he would be speaking with one of the employees from BSNL. Within this organisation the position of a telephone assistance operator requires high standards of communication ,a pleasant tone, good voice quality and familiarity with the company’s computer operator directories and software. The assistant also needs to be proactive in answering other queries asked by the caller. A major issue that is seen is that a lot of telephone assistance operators tend to leave the organisation , that turnover rates are high and people look unwilling. Mr. Ajit has noticed that upon joining, these telephone operators do not receive any detailed training. Being that it's a very busy workplace, these operators are given a short tour of the office and a five-page printed sheet that…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,