Chapter 4, Problem 66APQ
To determine
Calculate the capitalized cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Cost analysis
Tech engineering is making a product for overseas market. The following cost data for the product has been
compiled.
Item
Selling price
Materials and purchased parts $25/unit
Direct Labor (per unit)
Fixed Cost
a) Calculate the breakeven volume for this product
Cost
$135
2 hrs at $20 per hour
$1,400,000
b) What is the profit per unit if 30000 units are sold
c) To reduce the breakeven volume to 15000 Units, what should be the selling price
In the breakeven analysis, fixed costs are constant. Over time these expenses can change. Give some examples of fixed costs that change over time.
What is meant by the implict and explicit cost.
Chapter 4 Solutions
Basics Of Engineering Economy
Ch. 4 - State two conditions under which the do-nothing...Ch. 4 - Prob. 2PCh. 4 - Prob. 3PCh. 4 - Prob. 4PCh. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prob. 8PCh. 4 - Prob. 9PCh. 4 - The costs associated with manufacturing a...
Ch. 4 - Prob. 11PCh. 4 - Prob. 12PCh. 4 - Prob. 13PCh. 4 - Prob. 14PCh. 4 - Prob. 15PCh. 4 - Prob. 16PCh. 4 - Prob. 17PCh. 4 - Prob. 18PCh. 4 - Prob. 19PCh. 4 - Prob. 20PCh. 4 - Prob. 21PCh. 4 - Prob. 22PCh. 4 - Prob. 23PCh. 4 - Prob. 24PCh. 4 - Prob. 25PCh. 4 - Prob. 26PCh. 4 - Prob. 27PCh. 4 - Prob. 28PCh. 4 - Prob. 29PCh. 4 - Prob. 30PCh. 4 - Prob. 31PCh. 4 - Two mutually exclusive projects have the estimated...Ch. 4 - Prob. 33PCh. 4 - Prob. 34PCh. 4 - Prob. 35PCh. 4 - Prob. 36PCh. 4 - Prob. 37PCh. 4 - The manager of engineering at the 900-megawatt...Ch. 4 - Prob. 39PCh. 4 - Prob. 40PCh. 4 - Prob. 41PCh. 4 - Three different plans were presented to the GAO by...Ch. 4 - The U.S. Army received two proposals for a turnkey...Ch. 4 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63APQCh. 4 - Prob. 64APQCh. 4 - Prob. 65APQCh. 4 - Prob. 66APQCh. 4 - Prob. 67APQCh. 4 - Prob. 68APQCh. 4 - Prob. 69APQCh. 4 - Prob. 70APQCh. 4 - Prob. 71APQ
Knowledge Booster
Similar questions
- The Lawn Ranger, a landscaping company, has total costs of $4,000 and total variable costs of$1,000. The Lawn Ranger's total fixed costs are Soloct pnarrow_forwardA cell phone company has a fixed cost of $1.200.000 per month and a variable cost of $21 per month per customer. The company charges $37 5 per month to its cell phone customers. a. What is the breakeven point for this company?arrow_forwardThe costs of producing a certain commodity consist of 125.00 per unit for labor and material cost and 320.00 per unit for other variable cost. The unit can be sold at 1,200.00. If the production capacity per month is 5,200 units, what maximum fixed amount can the company spend each month of breakeven? Answer: 3,926,000.00 Explain every process.arrow_forward
- The cost of producing a computer diskette is as follows: Material cost is $7.00 each, labor cost is $2.00 each, and another expense is $1.50 each. If the fixed expenses are $69,000/month, how many diskettes must be produced each month for break even if each diskette is worth $250?arrow_forwardAfter a six months of work on the projects site, your company collected the following information relating to work down so far on the project BAC=$156,478.00, planned value=$95,565.24, Earned value =$92, 985.56, Actual cost =$95986.60. calculate the cost and schedule permermance indices and interpret your resultsarrow_forwardThe net annual operating cost (AOC) for a water treatment filtration plant for a semi-conductor fabrication line was estimated to be $1.5 million per year. The estimate was based on the $200,000 per year cost of a 1-MGD plant. The exponent in the cost-capacity equation is 0.80. (a) What was the size of the larger plant? (b) Build a spreadsheet to answer the same question. (c) If the plant manager has limited the AOC to $1 million per year, use your spreadsheet to determine the maximum MGD size plant that can be planned.arrow_forward
- What is the total costing based on the following shipment? Dimensions: Weight: 4 pieces, 70 in L x 100 in W x 5 in H each piece. 100 kg each piece. Chargeable weight: 400 kg. Total charges CPT CDG airport, Paris, France Origin pick up fee: Origin handling fee: CAD $0.20/kg CAD $0.20 x 400 = CAD $80.00 CAD $45.00 /shipment CAD $45.00 CAD $45.00 Origin terminal handling charges: CAD $0.04/kg CAD $0.04 x 400 = CAD $16.00 NavCan surcharge: B13A Export Declaration: CAD $0.07/kg CAD CAD $0.07 x 400 = CAD $17.50/shipment CAD $28.00 CAD $17.50 Air freight: $17.50/shipment CAN $4.40/kg Fuel surcharge: CAD $0.15/kg CAD $4.40 x 400 CAD $0.15 x 400 CAD $1,760.00 CAD $60.00 Security surcharge: CAD $0.08/kg CAD $0.08 x 400 CAD $32.00 TOTAL $2,040.50 $2,038.50 $2,006.50 $2,667.47arrow_forwardEstimate the production in CCY per hour a roller if it is average speed will be 4 mph and it will cover 5.5 ft in one pass. The job specifications limit the compacted lift thickness to 5 in. and require four passes per lift. The company usually figures production based on 50-min hours.arrow_forwardWhen the TP falls, (a) the APLabor is zero, (b) the MPLabor is zero, (c) the APLabor is negative, or (d) the APLabor isdecliningarrow_forward
- A car wheel making company has the following data related to cost: Total Cost = $ 15000 + 1000X and Total Revenue = 2500X, where X is the number of wheel. Calculate the Breakeven Point.arrow_forwardall average cost can be calculated by deriving the per unit cost. True or Falsearrow_forwardGiven the selling price at P120 per unit; contribution margin at 25% and fixed cost at P250,000, the total variable expenses at the breakeven point would be? a.)350 000 b.)750 000 c.)450 000 d.)250 000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Economics: Applications, Strategies an...EconomicsISBN:9781305506381Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. HarrisPublisher:Cengage Learning
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning