Textbook Question
Chapter 3, Problem 8P
Roger Ginde is developing a program in
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
d) What is the slack time for each individual activity?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s)
A
(BCDEFG
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project =
d) Slack time for each of the activities is:
days.
B
A, D
с
E, F
Activity
A
B
CDEFG
Slack Time
Time (days)
3
GANGG
5
2
10
4
8
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature
could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s)
A
BCDEFG
с
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project =
d) Slack time for each of the activities is:
days.
Activity
A
B
C
ס ח ד 0
F
B
A, D
C
E, F
G
Slack Time
Time (days)
4
6
1
103510
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Roger Ginde is developing a program in supplychain management certification for managers. Ginde haslisted a number of activities that must be completed beforea training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in theaccompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forwardProject Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processarrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.arrow_forward
- Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes. What is the critical path? What is the project duration? What is the latest start for Activity 4 "Secure patent?"?arrow_forwardGiven is a Project with network diagram and activity times as shown below. Activity Time (wks) A 13 B 5 Start с 14 A c) The Slack time of Activity C = Blank 3 weeks D D a) The Earliest Start (ES) time of Activity I = Blank 1 weeks 9 b) The Latest Start (LS) time of Activity B = Blank 2 weeks f) The Project Completion time = Blank 6 weeks d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks e) The Latest Finish (LF) time of Activity B = Blank 5 weeks B F E 12 E F LL 17 H G 9 J H 15 - 15 J 2arrow_forwardYou may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Start Optimistic Time (hr) Most Probable Time (hr) Start Floor Buffing Paint Mixing Naturally, paint mixing precedes the painting activities. Also, (a) Construct the PERT/CPM network for this problem. Floor Sanding 4 Paint Mixing 4 0.5 3 3 Paint Wall Paint Ceiling Paint Ceiling Paint Wall 5 5 1 4 7.5 Floor Sanding Pessimistic Time (hr) Floor Buffing Finish 6 Finish 6 ceiling painting and floor sanding must be dor 1.5 11 9 i Start Start prior to floor buffing. Floor Sanding Paint Mixing Floor Buffing Paint Mixing Paint Ceiling Paint Wall Paint Wall Paint Ceiling Floor Buffing Floor Sanding Finish Finisharrow_forward
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = ☐ days. d) Slack time for each of the activities is: Activity Immediate Predecessor(s) Time (days) A 4 B 7 2 B 10 A, D с 3 5 E, F 12 Activity A Slack Time B с D E F Garrow_forwardActivities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Normal Crashed Completion time (week) Crashed Cost Completion Time (week) 7 per week A 7 B $500 C 4 3 $700 $600 A A, C В, D D, E D 7 E F 10 9. $800 9 8 $400 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. ii. Find the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the drawn diagram of the project and hence the completion time of the project and the critical path.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY