EBK PRINCIPLES OF OPERATIONS MANAGEMENT
10th Edition
ISBN: 8220102744059
Author: HEIZER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 3, Problem 23P
a)
Summary Introduction
To determine:The probability of completing the project in 17 months.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
b)
Summary Introduction
To determine:The probability of completing the project in 20 months.
c)
Summary Introduction
To determine:The probability of completing the project in 23 months.
d)
Summary Introduction
To determine:The probability of completing the project in 25 months.
e)
Summary Introduction
To compute: The due date that yields a 95% chance of completion.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
A company is willing to develop their rocket before the end of current financial
year which is now 28 weeks away. The chief engineer of the company has
decided to use PERT technique in order to plan, schedule and control program
of development for the data given in table below.
What is the probability that the program will be completed by the end of the
current financial year? (all durations are in weeks).
(i) G)
Optimum Duration
Most likely duration
Pesimistic duration
1
2
3
8
13
3
2
8
4
3
8
10
4
7
10
3
6.
3
8
4
9
10
4
8.
4
9.
5
7
9.
12
6.
5
11
7
9.
14
8
4.
00
2.
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14arrow_forwardKimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.arrow_forward1.) You have determined the following for a given project: Expected completion time of the project = 40 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 44 weeks? answer as a decimal and take it to four places.arrow_forward
- Need help solving C and D. D) Freeze Inc.’s CEO established as a goal for top management to complete the project on or before 22 weeks. What is the probability that this project will be completed on or before 22 weeks?arrow_forward11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 4. Part 2 a) The probability that the project will be completed in 20 months = ______ (round your response to four decimal places)arrow_forwardAnalyse the sensitivity analysis and summarise the implications of the analysis for the project, Property acquisition 50%, financing 70% and construction 50%.arrow_forward
- A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)arrow_forwardAnswer following 4 questions 1: The probability that the project would be completed within 40 days: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 2: The probability that the project would take longer than 40 days is: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 3: The probability that the project would be completed within 20 days: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the above 4: The probability that the project would take longer than 20 days to finish: Group of answer choices 0.0228 0.0456 0.4772 0.9772 None of the abovearrow_forward34arrow_forward
- The following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)arrow_forwardSuppose the due date of the project is 18 months and the probability of completing it is 75%, while the deviation from the mean is 1.8 months. What will be the expected time of completion?arrow_forwardCreate a risk matrix for this project:Event Cost ($000) ProbabilityEquipment breakdown 40 .20Vendor is late with key segment 200 .60Subcontractor has labor issues 140 .30Weather problems 15 UnknownFunding delays 50 .40 to .60Testing delays 20 .40Explain your reasoning for your placement of the events Weather problems and Funding delays.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY