Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity (in hours) Immediate Predecessor(s) A 5.0 B 7.5 C 5.0 A D 8.0 B, C E 4.5 B, C F 7.7 D G 5.0 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 1 A C E F D B G Q Figure 2 전 A D E F B G Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: B D G Time Activity (in hours) Immediate Predecessor(s) A 5.0 B 7.5 C 5.0 A DEFC 8.0 B, C 4.5 Figure 2 A B, C 7.7 D G 5.0 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in 目 F B Figure 3 A E B E ☑ D F

MARKETING 2018
19th Edition
ISBN:9780357033753
Author:Pride
Publisher:Pride
Chapter6: Target Markets: Segmentation And Evaluation
Section: Chapter Questions
Problem 4SC
icon
Related questions
Question
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory
are as follows:
Time
Activity
(in hours) Immediate Predecessor(s)
A
5.0
B
7.5
C
5.0
A
D
8.0
B, C
E
4.5
B, C
F
7.7
D
G
5.0
E, F
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in
Figure 1
A
C
E
F
D
B
G
Q
Figure 2
전
A
D
E
F
B
G
Transcribed Image Text:Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity (in hours) Immediate Predecessor(s) A 5.0 B 7.5 C 5.0 A D 8.0 B, C E 4.5 B, C F 7.7 D G 5.0 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 1 A C E F D B G Q Figure 2 전 A D E F B G
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory
are as follows:
B
D
G
Time
Activity
(in hours) Immediate Predecessor(s)
A
5.0
B
7.5
C
5.0
A
DEFC
8.0
B, C
4.5
Figure 2
A
B, C
7.7
D
G
5.0
E, F
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in
目
F
B
Figure 3
A
E
B
E
☑
D
F
Transcribed Image Text:Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: B D G Time Activity (in hours) Immediate Predecessor(s) A 5.0 B 7.5 C 5.0 A DEFC 8.0 B, C 4.5 Figure 2 A B, C 7.7 D G 5.0 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in 目 F B Figure 3 A E B E ☑ D F
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College