Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 16, Problem 21P
Summary Introduction
To determine: The sequence that would minimize the total set up time.
Introduction:
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following table contains order-dependent setup times for four jobs. For safety reasons, jobC cannot follow job A, nor can job A follow job C. Determine the processing sequence that willminimize the total setup time. (Hint: There are 12 alternatives.)Following Job’sSetup Time (hrs.)SetupTime (hrs.) A B C DPrecedingjobA 2 — 5 × 4B 1 7 — 3 2C 3 x 2 — 2D 2 4 3 6 —
Brown's Machining has three jobs with the routings and processing times (in minutes) as indicated on its drill press, lathe, milling machine, and grinder. It uses an LWR dispatching rule.
Job 1: D(15), L(25), G(45)
Job 2: D(20, M(25), G(30)
Job 3: G(25), L(25), D(15), M(15)
What time is Job 1 completed?
Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun’s manufacturing plant is open 16 hours a day, 5 days a week, and 8 hours on Saturday.
A-148
B-356
B-457
C-843
Processing Time Station 1
6 min
5 min
0 min
8 min
Processing Time Station 2
4 min
4 min
5 min
2 min
Processing Time Station 3
5 min
7 min
4 min
2 min
Processing Time Station 4
3 min
0 min
10 min
1 min
a. If only toy A-148 is produced during a specific week, how many units could be produced? b. If weekly demand for the four products are A-148 = 200 units, B-356 = 250 units, B-457 = 250 units, and C-843 = 300 units, which station is the bottleneck, and is it capable of producing all the toys demanded?
Chapter 16 Solutions
Operations Management
Ch. 16 - Why is scheduling fairly simple for repetitive...Ch. 16 - Prob. 2DRQCh. 16 - What are Gantt charts? How are they used in...Ch. 16 - Prob. 4DRQCh. 16 - Briefly describe each of these priority rules: a....Ch. 16 - Why are priority rules needed?Ch. 16 - What problems not generally found in manufacturing...Ch. 16 - Explain forward and backward schedulings and each...Ch. 16 - Prob. 9DRQCh. 16 - Prob. 10DRQ
Ch. 16 - Prob. 11DRQCh. 16 - What general trade-offs are involved in sequencing...Ch. 16 - Prob. 2TSCh. 16 - Prob. 3TSCh. 16 - One approach that can be effective in reducing the...Ch. 16 - Doctors and dentists offices frequently schedule...Ch. 16 - Prob. 3CTECh. 16 - Use the assignment method to determine the best...Ch. 16 - Rework Problem 1, treating the numbers in the...Ch. 16 - Assign trucks to delivery routes so that total...Ch. 16 - Develop an assignment plan that will minimize...Ch. 16 - Use the assignment method to obtain a plan that...Ch. 16 - The following table contains information...Ch. 16 - Using the information presented in the following...Ch. 16 - The following table shows orders to be processed...Ch. 16 - A wholesale grocery distribution center uses a...Ch. 16 - The times required to complete each of eight jobs...Ch. 16 - Prob. 11PCh. 16 - A shoe repair operation uses a two-step sequence...Ch. 16 - The following schedule was prepared by the...Ch. 16 - The production manager must determine the...Ch. 16 - A foreman has determined processing times at a...Ch. 16 - Given the information in the following table,...Ch. 16 - Given the following information on job times and...Ch. 16 - Prob. 18PCh. 16 - The following table contains order-dependent setup...Ch. 16 - The following table contains order-dependent setup...Ch. 16 - Prob. 21PCh. 16 - Given this information on planned and actual...Ch. 16 - Given the following data on inputs and outputs at...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Prob. 1CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 9arrow_forwardCalculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Job CR 103 Job Due Date Duration (days) 103 214 10 205 223 7 309 217 11 412 219 5 517 217 15 Assume that all jobs arrived on day 180; today's date is 200.arrow_forwardAt the University Hospital, five blood samples must bescheduled through a blood-testing laboratory. Eachsample goes through up to four different testing stations.The times for each test and the due dates for eachsample are as follows:Sample Test Station/Hours Due Date (hours)1 A/1, B/2, C/3, D/1 62 B/2, C/3, A/1, D/4 103 C/2, A/3, D/1, C/2 84 A/2, D/2, C/3, B/1 145 D/2, C/1, A/2, B/4 12a. Using a Gantt chart, schedule these five samples in priority order of earliest due date first.b. Assume that the capacity of each test station (A, B, C and D) is doubled. Prepare an FCS for this situation.c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed.arrow_forward
- The following jobs are waiting to be processed at JulieMorel’s machine center:JOB DATE ORDER RECEIVED PRODUCTIONDAYS NEEDED DATE ORDER DUEA 110 20 180B 120 30 200C 122 10 175D 125 16 230E 130 18 210 In what sequence would the jobs be ranked according to the fol-lowing rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning cal-endar is day 130, and none of the jobs have been started or sched-uled. Which rule is best?arrow_forwardThe three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. Capacity: 20 units/hr Station 1 Machine A Station 1 Machine B Station 2 Capacity: Station 3 Capacity: 12 units/hr 10 units/hr Capacity: 20 units/hr a) The bottleneck time of the system is minutes per unit (enter your response as a whole number). b) is the bottleneck station. c) The throughput time is minutes (enter your response as a whole number). d) If the firm operates 11 hours per day, 5 days per week, the weekly capacity of this work cell is response as a whole number). units (enter yourarrow_forwardA production line is to be designed for a job with four tasks. The task times are 2.7 minutes, 0.4 minutes, 0.6 minutes, and 2.7 minutes. After line minutes, and the smallest possible assigned cycle time is minutes. (Round balancing, the largest possible assigned cycle time is answers to one decimal place.) OA. 6.4, 2.7 OB. 3.1, 2.3 OC. 1.6, 0.6 OD. 2.7, 0.4 OE. 6.0, 1.6arrow_forward
- Super Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. a. If only toy A-148 is produced during a specific week, ____ units could be produced. (Enter your response rounded down to the nearest whole number.)arrow_forwardStation 1 Machine A 20 min/unit Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 3 8 min/unit A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. The process time of each machine/station is indicated in the flowchart. What is the process time of this system measured in minutes/unit?arrow_forwardJack's Refrigeration Repair Service repairs and reconditions commercial icemakers at restaurants. Jack has four jobs to complete. Below are their processing times and due dates: Job Processing time (hours) Due date (hour) A 20 50 B 10 40 C 15 35 D 55 75 What is the average inventory if jobs are processed using the earliest due date rule?arrow_forward
- PROBLEM 10 The Graphic Palette is a firm in Charleston, South Carolina, that does graphic artwork and produces color and black-and-white posters, lithographs, and banners. The firm’s owners, Kathleen and Lindsey Taylor, have been approached by a client to produce a spectacularly colored poster for an upcoming arts festival. The poster is more complex than anything Kathleen and Lindsey have previously worked on. It requires color screening in three stages, and the processing must proceed rapidly to produce the desired color effect. By suspending all their other jobs, they can devote three machines to the first stage, four to the second stage, and two to the last stage of the process. Posters that come off the machines at each stage can be processed on any of the machines at the next stage. However, all the machines are of different models and of varying ages, so they cannot process the same number of posters in the specified time frame necessary to complete the…arrow_forwardA Manufacturing Corp. with three-station work cell has the process displayed below. Each workstation has only one worker to the assigned activity. Single order arrives every 7.5 hours. c) What is the cycle time corresponding to maximum throughput and actual throughput?d) Suppose that a second parallel machine is added at station 2. What is the new bottleneck timeand new throughput time of the system? How did the addition of the second machine at workstation 2 affect the performance of the work cell?arrow_forwardThe following five overhaul jobs a re waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days.Assume that all jobs arrived on day 180; today's date is 200 Using the critical ratio scheduling rule, in what sequence would the jobs be processed?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY