Concept explainers
Given the following information on job times and due dates, determine the optimal processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, find the average job flow time and the average job tardiness. Jobs are listed in order of arrival.
1)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e.
2)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is b-e-a-c-d-f.
3)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is e-b-a-c-f-d.
4)
To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 17P
Explanation of Solution
Given information:
Job | Job time (hours) | Due date (hours) |
a | 3.5 | 7 |
b | 2.0 | 6 |
c | 4.5 | 18 |
d | 5.0 | 22 |
e | 2.5 | 4 |
f | 6.0 | 20 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | 3.5 | 7 | 2. |
b | 2.0 | 6 | 3 |
c | 4.5 | 18 | 4 |
d | 5.0 | 22 | 4.4 |
e | 2.5 | 4 | 1.6 |
f | 6.0 | 20 | 3.33 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job e has the lowest critical ratio. Thus, it will be completed first. Hence, Job e would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job a:
As the processing time of job a is 2.5 hours, completion day of completed day would be 2.5.
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | 3.5 | 7 | 1.29 |
b | 2.0 | 6 | 1.75 |
c | 4.5 | 18 | 3.44 |
d | 5.0 | 22 | 3.90 |
e | |||
f | 6.0 | 20 | 2.90 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job a has the lowest critical ratio. Hence, Job a would be completed next in the sequence of jobs after Job e.
Determine the critical ratio after the completion of Job e and Job a:
As the processing time of job e is 2.5 hours and Job a is 3.5, completion day of completed day would be 6 (2.5+3.5).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | 2.0 | 6 | 0 |
c | 4.5 | 18 | 2.67 |
d | 5.0 | 22 | 3.20 |
f | 6.0 | 20 | 2.33 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job b has the lowest critical ratio. Hence, Job b would be completed next in the sequence of jobs after Job e and Job a.
Determine the critical ratio after the completion of Job e, Job a, and Job b:
As the processing time of job e is 2.5 hours, Job a is 3.5, and Job b is 2. Completion day of completed day would be 8 (2.5+3.5+2).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | |||
c | 4.5 | 18 | 2.22 |
d | 5.0 | 22 | 2.80 |
f | 6.0 | 20 | 2.00 |
Critical ratio for Job c:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job f has the lowest critical ratio. Hence, Job f would be completed next in the sequence of jobs.
Determine the critical ratio after the completion of Job e, Job a, Job b, and Job f:
As the processing time of job e is 2.5 hours, Job a is 3.5, Job b is 2, and Job f is 6.0. Completion day of completed day would be 14 (2.5+3.5+2+6).
Job | Job time (hours) | Due date (hours) | Critical ratio |
a | |||
b | |||
c | 4.5 | 18 | 2.22 |
d | 5.0 | 22 | 2.80 |
f |
Critical ratio for Job c:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: The procedure continues for all the jobs.
Job c has the lowest critical ratio. Hence, Job c would be completed next in the sequence of jobs.
As Job d is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is e-a-b-f-c-d.
Determine the average flow time and average tardiness:
First Come First Served:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
a | 3.5 | 7 | 3.5 | |
b | 2.0 | 6 | 5.5 | |
c | 4.5 | 18 | 10.0 | |
d | 5.0 | 22 | 15.0 | |
e | 2.5 | 4 | 17.5 | 13.5 |
f | 6.0 | 20 | 23.5 | 3.5 |
Total | 23.5 | 75.0 | 17.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job, b, Job c, and Job d:
Flow time of Job a, Job b, Job c, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 13.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 3.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 12.5 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 2.83 hours
Shortest processing time:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
b | 2.0 | 6 | 2.0 | |
e | 2.5 | 4 | 4.5 | 0.5 |
a | 3.5 | 7 | 8.0 | 1.0 |
c | 4.5 | 18 | 12.5 | |
d | 5.0 | 22 | 17.5 | |
f | 6.0 | 20 | 23.5 | 3.5 |
Total | 23.5 | 68.0 | 5.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job b, Job c, and Job d:
Flow time of Job b, Job c, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 1.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 3.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.33 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.83 hours
Earliest Due Date:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
e | 2.5 | 4 | 2.5 | |
b | 2.0 | 6 | 4.5 | |
a | 3.5 | 7 | 8.0 | 1.0 |
c | 4.5 | 18 | 12.5 | |
f | 6.0 | 20 | 18.5 | |
d | 5.0 | 22 | 23.5 | 1.5 |
Total | 23.5 | 69.5 | 2.5 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job e, Job b, Job c, and Job f:
Flow time of Job e, Job b, Job c, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 1.
Tardiness of Job d:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job d is 1.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.58 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.42 hours
Critical ratio:
Job | Job time (hours) | Due date (hours) | Flow time | Tardiness |
e | 2.5 | 4 | 2.5 | |
a | 3.5 | 7 | 6.0 | |
b | 2.0 | 6 | 8.0 | 2.0 |
f | 6.0 | 20 | 14.0 | |
c | 4.5 | 18 | 18.5 | 0.5 |
d | 5.0 | 22 | 23.5 | 1.5 |
Total | 23.5 | 72.5 | 4.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job e, Job a, and Job f:
Flow time of Job e, Job a, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job b:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job b is 2.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 0.5.
Tardiness of Job d:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job d is 1.5.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 12.08 hours.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.67 hours.
Want to see more full solutions like this?
Chapter 16 Solutions
Operations Management
- Processing time for eight projects, displayed in the sequence they arrived. Project P1 P2 P3 P4 P5 P6 P7 P8 Processing time (hours) 3 1 1 2 9 6 1 1.50 2. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow rate of the projects? Note: Round your answer to 2 decimal places. 3. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow time of the projects? Note: Round your answer to 1 decimal place. 4. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average inventory of the projects? Note: Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place. 5. Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow rate of the projects? Note: Round your answer to 2 decimal places. 6. Given the projects displayed in table above, if SPT is used to sequence…arrow_forwardAn independent accountant is planning to prepare tax returns for six of her clients.Prior to her actually preparing each return, her secretary checks the client’s file to besure all the necessary documentation is there and obtains all the tax forms needed forthe preparation of the return. Based on past experience with the clients, her secretaryestimates that the following times (in hours) are required for preparation of the returnand for the accountant to complete the necessary paperwork prior to filing each return:Client Secretary Time Accountant Time1 1.2 2.52 1.6 4.53 2.0 2.04 1.5 6.05 3.1 5.06 0.5 1.5In what order should the work be completed in order to minimize the total timerequired for all six clients?arrow_forwardGiven the projects displayed in Table 18.21, if SPT is used to sequence the jobs, what isthe average flow time of the projects (in hours)?arrow_forward
- Five jobs are planned to be scheduled. Each of the jobs must be processed on three machines (A, B, and C) in the same order. The processing times are listed below. Use Johnson's Rule to determine the optimal sequence of jobs. Job B 16 10 11 10 14 20 12 3 10 8 4 1 O a) 3-1-2-4-5 O b) Johnson's Rule is not an Optimal Technique O c) 1-2-3-4-5 O d) 5-4-3-1-2 O e) 5-4-3-2-1 O) 5-4-2-1-3 O e) 5-4-2-3-1 2345arrow_forwardFive jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job A B Processing Time (days) I5 Due Date 11 6 3 16 19 10 D E 15 Using the earliest due date (EDD) rule, the average lateness for the five jobs is decimal place. Round your answer to one Your Answer: Answerarrow_forwardGiven the projects displayed in Table 18.21, if FCFS is used to sequence the jobs, whatis the average flow time of the projects (in hours)?arrow_forward
- The table below shows processing times and due dates for five jobs. JOB PROCESSING DATE DUE TIME (DAYS) FROM TODAY A 8 12 4 9 3 6 10 11 20 (i) What is the average flow-time, if the Shortest Processing Time Rule (SPT) is used to sequence these jobs? (ii) What is the average lateness, and (iii) tardiness, if the Earliest Due Date Rule (EDD) is used to sequence these jobs? Select one: (i) Average Flow Time: 6.2 days (ii) Average Lateness: 7 days (iii) Average Tardiness: 5.8 days (i) Average Flow Time: 15 days (ii) Average Lateness: 6 days (iii) Average Tardiness: 5 days (i) Average Flow Time: 11.6 days (ii) Average Lateness: 3.4 days (iii) Average Tardiness: 5.8 days (i) Average Flow Time: 6.2 days (ii) Average Lateness: 4 days (iii) Average Tardiness: 5.2 days (i) Average Flow Time: 15 days (ii) Average Lateness: 5 days (iii) Average Tardiness: 6 days шarrow_forwardEight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forwardGiven the projects displayed in Table 18.21, if SPT is used to sequence the jobs, what isthe average inventory of the projects (in projects)?arrow_forward
- The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardThe data for five tax analysis jobs waiting to be processed by Martha at T. R. Accounting Service has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Questions 1. Use the shortest-processing-time (SPT) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus sign to enter negative lateness values, if any. Round the average values to two decimal places. Sequence Job Processing Time Due Date Flow Time Lateness Tardiness 1 2 3 4 5 Average 2. Use the earliest-due-date (EDD) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus…arrow_forwardGiven the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true? Job Processing time (days) Due date (in days) A 10 10 B 5 8 C 15 25 D 8 15 a.Jobs B and D will have no tardiness b.The tardiness for Job A is 12 days c.The average tardiness is 19.75 d.The average completion time is 6.5arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.