The following table contains information concerning four jobs that are awaiting processing at a work center.
Sequence the jobs using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. Assume the list is by order of arrival.
b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.
c. Is one method superior to the others? Explain.
a)
1)
![Check Mark](/static/check-mark.png)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is A-B-C-D.
1)
![Check Mark](/static/check-mark.png)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is A-B-C-D.
2)
![Check Mark](/static/check-mark.png)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is D-C-B-A.
3)
![Check Mark](/static/check-mark.png)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is C-B-D-A.
4)
![Check Mark](/static/check-mark.png)
To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Processing time (days) | Due date (days) | Critical ratio |
A | 14 | 20 | 1.43 |
B | 10 | 16 | 1.6 |
C | 7 | 15 | 2.14 |
D | 6 | 17 | 2.83 |
Critical ratio for Job A:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job C:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Job A has the lowest critical ratio. Thus, it will be completed first. Hence, Job A would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job A:
As the processing time of job A is 14 days, completion day of completed day would be 14.
Job | Processing time (days) | Due date (days) | Critical ratio |
A | - | - | - |
B | 10 | 16 | 0.20 |
C | 7 | 15 | 0.14 |
D | 6 | 17 | 0.50 |
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job C:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job C has the lowest critical ratio. Hence, Job C would be completed next in the sequence of jobs after Job A.
Determine the critical ratio after the completion of Job A and Job C:
As the processing time of job A is 14 days and Job C is 7, completion day of completed day would be 21 (14+7).
Job | Processing time (days) | Due date (days) | Critical ratio |
A | - | - | - |
B | 10 | 16 | -0.50 |
C | |||
D | 6 | 17 | -0.67 |
Critical ratio for Job B:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Critical ratio for Job D:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job D has the lowest critical ratio. Hence, Job D would be completed next in the sequence of jobs after Job A and Job C.
As Job B is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is A-C-D-B.
b)
![Check Mark](/static/check-mark.png)
To determine: Average flow time, average tardiness, and average number of jobs for each method.
Introduction: Rules that are framed for providing the order in which the jobs need to be performed are termed as priority rules. These rules are more suitable for process-oriented facilities. The main purpose of priority rules are on-time completion of jobs, efficient utilization of services, and the maximizing the customer services.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
First Come First Served:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
A | 14 | 20 | 14 | 0 |
B | 10 | 16 | 24 | 8 |
C | 7 | 15 | 31 | 16 |
D | 6 | 17 | 37 | 20 |
Total | 37 | 68 | 106 | 44 |
Average | 9.3 | 17.0 | 26.5 | 11.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job A:
Flow time of Job A is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 8.
Tardiness of Job C:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job C is 16.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 20.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 26.5 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 11.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.86 jobs.
Shortest processing time:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
D | 6 | 17 | 6 | |
C | 7 | 15 | 13 | |
B | 10 | 16 | 23 | 7 |
A | 14 | 20 | 37 | 17 |
Total | 37 | 68 | 79 | 24 |
Average | 9.3 | 17.0 | 19.8 | 12.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job D and Job C:
Flow time of Job D and Job C is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 7.
Tardiness of Job A:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job A is 17.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 19.75 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 6.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.14 jobs.
Earliest Due Date:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
C | 7 | 15 | 7 | |
B | 10 | 16 | 17 | 1 |
D | 6 | 17 | 23 | 6 |
A | 14 | 20 | 37 | 17 |
Total | 37 | 68 | 84 | 24 |
Average | 9.3 | 17.0 | 21.0 | 8.0 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job C:
Flow time of Job C is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 1.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 6.
Tardiness of Job A:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job A is 17.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 21.00 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 6.0 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.27 jobs.
Critical ratio:
Job | Processing time (days) | Due date (days) | Flow time | Tardiness |
A | 14 | 20 | 14 | 0 |
C | 7 | 15 | 21 | 6 |
D | 6 | 17 | 27 | 10 |
B | 10 | 16 | 37 | 21 |
Total | 37 | 68 | 99 | 37 |
Average | 9.3 | 17.0 | 24.8 | 9.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job A:
Flow time of Job A is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job C:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job C is 6.
Tardiness of Job D:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job D is 10.
Tardiness of Job B:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job B is 21.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 24.75 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 9.25 days
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.68 jobs.
c)
![Check Mark](/static/check-mark.png)
To determine: The method which is superior to others.
Introduction: Rules that are framed for providing the order in which the jobs need to be performed are termed as priority rules. These rules are more suitable for process-oriented facilities. The main purpose of priority rules are on-time completion of jobs, efficient utilization of services, and the maximizing the customer services.
Answer to Problem 6P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) |
A | 14 | 20 |
B | 10 | 16 |
C | 7 | 15 |
D | 6 | 17 |
Determine the method which is superior to other:
Shortest Processing Time (SPT) is the method which is superior to other, as it is the method which would provide lowest value when compare to others.
Want to see more full solutions like this?
Chapter 16 Solutions
Operations Management
- What is an example of how someone would explain how their past personal and professional experience makes you a quality candidate for a teaching position at an Elementary School as a K-6 Teacher?arrow_forwardI need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.arrow_forwardHow can a local tourism and hospitality company successfully enter international markets?arrow_forward
- How was Circuit City Company collapsed? And what was the sequence of time and events or problems? How to solve the issues, and could you help identify positions or titles. Sanitize all names and use only fictitious data. What is synthesize the qualitative research methodology of Case Study research? Please give some examples. How to use the practical of Lean Six Sigma to develop a business-facing DMAIC-based case studyarrow_forwardBUSINESS MODEL CANVAS: U.S ARMY key partners: Key activities: Key Resources: Value Propositions: Buy-in & Support: Deployment: Benficiaries: Mission budget/cost: Mission Achievement/ Impact factors: Please at least 4 for each categoryarrow_forwardhow you would best conduct a performance evaluation meeting with a subordinate (where an employee would receive their performance evaluation from their supervisor). Importantly, detail how a supervisor can best gain the concurrence from an employee on the evaluation itself, and to ensure that the employee’s performance will be modified as a result of appraisal meeting.arrow_forward
- I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.arrow_forwardassume that you are police commander which leads and supervises the department’s internal affairs division. Your goal is to reduce civilian complainants against personnel in the department. Using what you have learned and at least three scholarly sources, document two changes you see the department can implement, whether it be training, planning, mitigating, and resolving, to improve police/community relations.arrow_forwardNess Engineering is a private limited company mainly engaged in the continuous production and assembly of domestic products. The annual turnover is $900,000,000. The largest area of expenditure is raw materials and components where the annual spend is approximately $450,000,000. The Managing Director, Bill, considers that profit margins are too small and has asked you to suggest how profitability might be increased. Bill suggests that this might be done by appointing additional sales staff and by an advertising campaign, which would, hopefully, increase turnover and thereby reduce overhead cost per item. You find that purchasing is little more than a post-office function. Specifications are received from the design or user departments and sent either to supplies designated by the directors or to the supplier providing the cheapest quotation. The company does, in fact, deal with many suppliers and issues many orders for low-cost items. All purchasing is done by manual means. None of the…arrow_forward
- The oasis outpost of Abu Ilan, in the heart of the Negev desert, has a population of 20 Bedouin tribesmen and 20 Farima tribesmen. El Kamin, a nearby oasis, has a population of 32 Bedouins and 8 Farima. A lost Israeli soldier, accidentally separated from his army unit, is wandering through the desert and arrives at the edge of one of the oases. The soldier has no idea which oasis he has found, but the first person he spots at a distance is a Bedouin. 1. What is the probability that he wandered into Abu Ilan? 2. What is the probability that he is in El Kamin?arrow_forward2-22 The lost Israeli soldier mentioned in Problem 2-21 decides to rest for a few minutes before entering the desert oasis he has just found. Closing his eyes, he dozes off for 15 minutes, wakes, and walks toward the center of the oasis. The first person he spots this time he again recognizes as a Bedouin. What is the posterior probability that he is in El Kamin?*Note* 2-21 The oasis outpost of Abu Ilan, in the heart of the Negev desert, has a population of 20 Bedouin tribesmen and 20 Farima tribesmen. El Kamin, a nearby oasis, has a population of 32 Bedouins and 8 Farima. A lost Israeli soldier, accidentally separated from his army unit, is wandering through the desert and arrives at the edge of one of the oases. The soldier has no idea which oasis he has found, but the first person he spots at a distance is a Bedouin. What is the probability that he has wandered into Abu Ilan? What is the probability that he is in El Kamin?arrow_forwardHello, please make an excel of this. Show all the cells thanks. some replied with a paper answer thank you I just cant understand the way the did it. Can someone show me all screenshots o fthis problem solved and in excel? i need to solver too for the constraints. I seen multiple times across other platforms that one of the chairs optimal solutions is 0 but they both have to be higher than 1 The Heinrich Company manufactures two types of plastic hangerracks (Foldaways and Straightaways) especially suited for mountingnear clothes dryers. Because permanent press clothing must be hungon hangers immediately after removal from the dryer, these items havebeen especially popular. However, there is some concern that thePreppie movement (popularized by its own handbook) will extinguishpolyester clothing; Heinrich is terribly interested in doing the best withthe resources it has while its products are still in demand. The firsttype of hanger rack, the Foldaway, requires 10 ounces of…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)