Textbook Question
Chapter 15, Problem 5P
Product A is assembled from two units of S1 and three units of S2. S1 is made of one unit of C1, four units of C2, and one unit of C3. S2 is made of three units of C2 and two units of C3.
- a. Draw a product structure diagram for product A.
- b. How many C3s are needed to fill an order for 100 As?
- c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 As are needed by day 7?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to
assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?
Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?
Product M is made of 2 units of N and 3 unit of P. N is made of 2 units of R and 4 units of S. R is made of 1
unit of S and 3 units of T. P is made of 2 units of T and 4 units of U.
a) Show the BOM (product structure tree).
b) If 100 M are required, how many units of each component are needed?
Chapter 15 Solutions
Operations and Supply Chain Management 9th edition
Ch. 15 - Describe a production environment in which MRP...Ch. 15 - Explain with an example the difference between...Ch. 15 - What are the objectives, inputs, and outputs of an...Ch. 15 - How is a master production schedule created, and...Ch. 15 - What is the purpose of phantom bills, K-bills, and...Ch. 15 - What type of information is included in the item...Ch. 15 - Describe cycle counting. How does it improve...Ch. 15 - Describe the MRP process, including netting,...Ch. 15 - What are the inputs to capacity requirements...Ch. 15 - Discuss several assumptions of MRP and how they...
Ch. 15 - Explain how MRP could be applied to (a) the...Ch. 15 - How does MRP differ from ERP? Find a description...Ch. 15 - What are the capabilities of customer relationship...Ch. 15 - What ate the capabilities of supply chain...Ch. 15 - What is PLM? How does it relate to other business...Ch. 15 - Describe how the ERP systems from two different...Ch. 15 - Discuss the scope of ERP and difficulties in...Ch. 15 - Referring to the product structure diagram for...Ch. 15 - Construct a multilevel bill of material for...Ch. 15 - The classic One-Step step stool shown in the next...Ch. 15 - Draw a product structure diagram from the...Ch. 15 - Product A is assembled from two units of S1 and...Ch. 15 - The popular Racer Scooter comes in a variety of...Ch. 15 - Draw a product structure diagram from the bill of...Ch. 15 - Prob. 8PCh. 15 - Use the product structure diagram for item X shown...Ch. 15 - Kids World sells outdoor play equipment for...Ch. 15 - Complete the following MRP matrix for item A:Ch. 15 - Complete the following MRP matrix for Item X....Ch. 15 - Complete the MRP matrix below, then answer the...Ch. 15 - Alpha Corp. (a spinoff of Alpha Beta) makes...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The best fits using exponential smoothing, trend analysis, and linear regression for the given data. Introducti...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Consider the sales data for Computer Success given in Problem 7. Use a 3-month weighted moving average to forec...
Operations Management: Processes and Supply Chains (11th Edition)
What is precedent, and how does it affect common law?
Business in Action
What is a qualitative forecasting model, and when is its use appropriate?
Operations Management
1.10 Brown’s, a local bakery, is worried about increased costs—particularly energy. Last year’s records can pro...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Product M is made of two units of N and two of P. N is made of two units of R and four units of S. Ris made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forwardProduct A consists of two units of Subassembly B, three units of C, and one unit of D. B is composed of four units of E and three units of F. C is made of two units of H and three units of D. H is made of five units of E and two units of G.a. Construct a simple bill-of-materials (product structure tree).b. Construct a product structure tree using low-level coding.c. Construct an indented parts list.d. To produce 100 units of A, determine the number of units of B, C, D, E, F, G, and H required.arrow_forwardRefer to this product tree: A hierarchical diagram that depicts the subassemblies and components that are needed to produce and/or assemble a product P.P requires 2 components of A, 3 components of B and 4 components C. A further requires 3 components of M and 4 components of N. B further requires 4 components of C and 5components of D. If 1000 Ps are needed, and on-hand inventory consists of 200 Ps and 100 each of all other components and subassemblies, how many Cs are needed? Multiple Choice 9200 3200 12300 12200 3100arrow_forward
- Product A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of E.Subassembly C requires one part of D and one part of F. a. Draw a product structure tree (BOM) for this product. b. How many parts are needed to make 300 units of finished product?arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forwardConsider the following product structure. If the demand for product A is 50 units, how many units of component E will be needed? OA. 100 OB. 250 O C. 300 O D. 4 OE. 200 Show transcribed image text C (1) B(2) D (1) D (1) A C (3) E (2) D (1) F (1) G (2)arrow_forward
- Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)arrow_forwardProduct A is made from components B, C, and D. Item B is asubassembly that requires two units of C and one unit of E.Item D also is an intermediate item, made from two unitsof F. All other usage quantities are two. Draw the BOM forproduct A.arrow_forwardIf a work order instructs you to package 620 boxes of product and each product contains 2 bags of 50 sheets of film, how many sheets of film will need to be produced?arrow_forward
- Can you assist me with Problem 7 errors. Thank you greatlyarrow_forwardThe following table lists the components needed to assemble an end item. Assume there is no on-hand inventories. Item Direct Components End item A(4), B(5), C(4) A E(3), F(2) B D(3), E(5) C F(4) D E F E(4) If 3 units of the end item are to be assembled, how many units of component E are needed? Input should be an exact number.arrow_forward15.5. Product A is assembled from two units of S1 and three units of S2. S1 is made of one unit of C1, four units of C2, and one unit of C3. S2 is made of three units of C2 and two units of C3. a. Draw a product structure diagram for product A. b. How many C3s are needed to fill an order for 100 As? c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days, and components take three days. When should an order be released for C3 if the 100 As are needed by day 7?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY