Question
Chapter 15, Problem 8P
a)
Summary Introduction
To determine: How many different bicycles can be produced by company B from given data.
Introduction: Material Requirement Planning is software-based inventory control for production planning and
b)
Summary Introduction
To determine: Modular bill for company B
c)
Summary Introduction
To determine: how many 26-inch bikes should Best Wheels plan to produce and How many 10-speed bikes? If sales are 10000
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
K
The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2
weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Suppose that in addition to 130 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week
8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).…
Number 14
Consider the following information.
PART X
Gross Requirements
Scheduled Receipts
Projected On-Hand Inventory 100
Q = 60, LT= 3 weeks, Safety Stock = 5
1
70
70
PART X
Gross Requirements
Scheduled Receipts
Projected On-Hand Inventory 100
Planned Order Releases
1
70
70
100
2
0
>
X
WEEK
3
40
Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your
answer is zero, enter "0".
2
0
4
0
100
WEEK
3
40
5
160
60
4
0
40
0
X
5
160
Check My Work
-60
0
Chapter 15 Solutions
Operations and Supply Chain Management 9th edition
Ch. 15 - Describe a production environment in which MRP...Ch. 15 - Explain with an example the difference between...Ch. 15 - What are the objectives, inputs, and outputs of an...Ch. 15 - How is a master production schedule created, and...Ch. 15 - What is the purpose of phantom bills, K-bills, and...Ch. 15 - What type of information is included in the item...Ch. 15 - Describe cycle counting. How does it improve...Ch. 15 - Describe the MRP process, including netting,...Ch. 15 - What are the inputs to capacity requirements...Ch. 15 - Discuss several assumptions of MRP and how they...
Ch. 15 - Explain how MRP could be applied to (a) the...Ch. 15 - How does MRP differ from ERP? Find a description...Ch. 15 - What are the capabilities of customer relationship...Ch. 15 - What ate the capabilities of supply chain...Ch. 15 - What is PLM? How does it relate to other business...Ch. 15 - Describe how the ERP systems from two different...Ch. 15 - Discuss the scope of ERP and difficulties in...Ch. 15 - Referring to the product structure diagram for...Ch. 15 - Construct a multilevel bill of material for...Ch. 15 - The classic One-Step step stool shown in the next...Ch. 15 - Draw a product structure diagram from the...Ch. 15 - Product A is assembled from two units of S1 and...Ch. 15 - The popular Racer Scooter comes in a variety of...Ch. 15 - Draw a product structure diagram from the bill of...Ch. 15 - Prob. 8PCh. 15 - Use the product structure diagram for item X shown...Ch. 15 - Kids World sells outdoor play equipment for...Ch. 15 - Complete the following MRP matrix for item A:Ch. 15 - Complete the following MRP matrix for Item X....Ch. 15 - Complete the MRP matrix below, then answer the...Ch. 15 - Alpha Corp. (a spinoff of Alpha Beta) makes...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...Ch. 15 - Just ERP Just Sofas (JS) had begun the year full...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 25 If safety stock is desired, it should be built into which portion of MRP? Select one: a. none b. finished goods c. raw materials d. any e. either raw materials or finished goodsarrow_forwardName four important items of information that should be ona typical purchase order.arrow_forwardSMARTPAK (Smart Backpack): Product Description: The SMARTPAK is a technologically advanced and functional luggage. Because of their physical, mechanical, and chemical qualities, your products will be trustworthy, user-friendly, and secure. The SMARTPAK is a convenient and safe way to move equipment and supplies. Task need to do: Identify machinery and equipment listed according to type and use. Specification,capacities, costs, and source must be described in detail, as well as the manner of transporting them at their costs. note: this is just a proposal so just assume everything, anything will do. just create it in your own way of understanding the product.arrow_forward
- X1= 29000 X2= 5 I need a clear step by step answer please :)arrow_forwardDifferentiate between 'order quantity' and 'order winners' providing examples 1000 wordsarrow_forward4. Identify the Order-winners and Order qualifiers for the following business: A mobile manufacturing company Car Renting companyarrow_forward
- Q4) A manufacturer provides specialized microchips. During the next 3 months its sales, costs, and available time are shown in the table. Month 1 Month 2 Month 3 There are no chips in stock at the beginning of the first month. It takes 1.5 hr of production time to produce a chip and costs $5 to store a chip from one month to the next. Determine a production schedule that meets the demand requirements, does not exceed the monthly production time limitations, and minimizes cost. Note that no chips should be in stock at the end of the 3 months. Use fmincon. Chips required Cost regular time ($/chip) Cost overtime ($/chip) Regular operation time (hr) Overtime (hr) 1000 100 110 2500 100 120 2200 120 130 2400 2400 720 2400 720 720arrow_forward2. Perform an ABC analysis for the data provided. Clearly explain why you classified items as A, B, or C. Annual Unit Item Usage 2400 Cost $19.51 $32.60 $10.20 $6.80 2 6200 3 8500 4 3200 6000 $4.50 $55.70 $3.60 $44.90 $35.62 750 7 8200 8 9000 5800 10 820 $82.60 $40.50 11 500 12 2000 $15.40 $14.60 $35.80 13 2400 14 6300 15 4750 $17.30 2700 $51.75 $42.90 $25.30 16 17 1600 18 1350 19 5000 $67.00 20 1000 $125.00arrow_forwardWhat is the Finished-goods inventory?arrow_forward
- 6arrow_forward|Product D is stocked only at the AMC Chemical Company's Dallas warehouse and at the company's plant warehouse in Akron. The sales director has forecast product sales from the Dallas warehouse to be 40 units per week for the next 8 weeks. Product D is manufactured at the firm's Akron plant using 2 units of ingredient X per unit of product D. Information: Ingredient X Projected available balance: 4 Units Schedule receipt in week 1: 320 units Safety stock quantity: 2 Product D in Dallas Product D in Plant Warehouse Warehouse Projected available balance: 85 Units Safety stock quantity: 5 units Lead time: 2 weeks Lot for lot size quantity Projected available balance: 2 Units Schedule receipt in week 1: 46 units Safety stock quantity: 8 units units Lead time: 1 week Lead time: 4 weeks Lot for lot size quantity Lot size quantity: 320 units Prepare the DRP records for product D at the Dallas warehouse and the plant warehouse as well as the MRP record for ingredient X (Assume ingredient X is…arrow_forwardWhat is quality and safety stock in simple words, and examples of it?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning