Book Icon
Chapter 15, Problem 5DQ
Summary Introduction

To determine: The advantages and disadvantages of Shortest Processing Time (SPT) rule.

Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, a job with the shortest duration would be served first. Then, the process would be going on from the shortest to largest duration

Blurred answer
Students have asked these similar questions
QUESTION #4 Four delivery trucks are in a queue at a Tool Company with only one service bay. The trucks are identified by the sequence in which they arrived at the Company. Assume the time is 10:00 a.m. The table shows the times necessary to unload each vehicle and the periods when the commodities they contain are expected in the factory. Determine the schedules that result for each of the rules SPE, CR EDD, and FSFC. In each case compute the average tardiness, the number of tardy jobs, and mean flow time. Truck 1 2 3 4 5 Unloading Time (minutes) 23 16 39 12 30 Time Material is Due 10:15 AM 10:40 AM 10:55 AM 10:30 AM 10:40 AM
Question 7 Station 1 Machine A 20 min/unit Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 3 8 min/unit A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. What is the process time of this system measured in minutes/unit?
A Maving to another question will sae this response. Question 24 Copy of Table 10.10 A work center has the following five jobs waiting to be processed (all times are shown in days): Job Arrival Processing Due 12 29 16 11 31 13 12 25 1 8 Use the infomation in Table 10.10. What is the average flow time using the FCFS rule (Answer to 2 decimal places)? (CSLOS 1,2,3) Moving to another question will save this response.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.