Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
10th Edition
ISBN: 9780134181981
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 15, Problem 11DQ
Summary Introduction
To define: Assignment method
Introduction:
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question:
Consider the following linear program:
Max Z = 2*x + 3*y
subject to
3*x + 4*y >= 12
3*x + 2*y >= 9
y>= 1
x,y >= 0
The number of feasible corner points is:
0
1
2
3
None of the other answers are correct.
QUESTION 4 (SCHEDULING: JOHNSON'S RULE)
The following schedule was prepared by the production manager of Marymount Metal Shop:
Determine a schedule that will result in the earliest completion of all jobs on this list.
CUTTING
POLISHING
Job
ABCDEFG
(ii)
(iii)
(iv)
Start
0
2
6
11
15
17
20
Finish
2
6
11
15
17
20
21
Start
2615232
11
20
24
Finish
5
9
13
20
23
24
28
What is the optimal sequence?
Draw the time-phased chart.
What is the total completion time?
What is the total idle time at Polishing work centre?
Question 5:
The following figure shows the product structure tree of product A.
A
D
(2)
B
(2)
E
(1)
C
(1)
|
D
(3)
The company requires 200 units of product A in period 8 and 150 units in period 6. The on hand
inventory for products A, B, C, D and E are 50, 150, 40, 100, 70 respectively. The lead times for
products A, B, C, D and E are 1, 0, 2, 1, 1. Develop the MRP and specify gross and net
requirements, projected on-hand, planned order receipts, and planned order release for all the
products. Assume we use lot-for-lot ordering for all the products and not safety stock is required.
Chapter 15 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- QUESTION THREEGiven the LP below:a) Solve the problem using big M-methodMinimize Z = 3X1 +4X2s.t 4X1 + X2 ≥ 30−X1 − 4X2 ≤ −184X1 + 3X2 ≥ 28X1, X2, ≥ 0arrow_forwardQUESTION 10 A manufacturing facility is manufacturing a new tablet. The tables are formed by mother board, memory chips, and touch display. A tablets requires one mother board and 1 touch display. The motherboard requires two memory chips. Once that all pieces are in the plant it takes 2 weeks to assemble the final product. TH projected demand for weeks 6 to 10 are: 120, 170, 250, 200, and 125. The company has for week 6 already 60 tablets. The company also need to have at the end of week 10 an inventory of 50 tablets. Tablet (2 weeks) Touch display (1) Motherboard (1) (1 weeks) (1 weeks) Memory chip[s (2) (2 weeks) With the lot for lot policy, determine the planned order released for the memory chips and the starting week. Starting Week: Order Policy by Period:arrow_forwardQuestion 2 Colonial Furniture produces hand-crafted colonial style furniture. Plans are now being made for the production of rocking chairs, dining room tables, and/or armoires over the next week. These products go through two stages of production (assembly and finishing). The table in the next column gives the time required for each item to go through these two stages, the amount of wood required (fine cherry wood), and the corresponding unit profits, along with the amount of each resource available next week. Assembly Rocking Chair Dining 180 Room Table Armoire Available 100 120 3,600 (minutes) Finishing 60 80 80 2,000 (minutes) Wood 30 180 120 4,000 (pounds) Unit Profit $240 $720 $600 A linear programming model has been formulated in a spreadsheet to determine the production levels that would maximize profit. The solved spreadsheet model and corresponding sensitivity report are shown below. Answer the following questions (a-i) using the output please be brief. If there are two…arrow_forward
- QUESTION 5 A schedule for two processors has been created for the following project which has a finishing time of 30. A(6) B(11) Start C(1) F(5) G(4) D(9) FO ● H(5) E(8) ● Which is the following statements is applicable to the schedule? O A. The schedule is optimal because the finishing time is equal to the critical time. O B. The schedule is optimal because the finishing time is equal to the average time. End ● O C. The schedule is not optimal because the finishing time is greater than the critical time. O D. The schedule is not optimal because the finishing time is greater than the average time. O E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time. O F. The schedule is optimal because the finishing time is less than the critical time. O G. The schedule is optimal because the finishing time is less than the average time. OH. The schedule is not optimal because the finishing time is less than the critical time. OI. The…arrow_forwardQUESTION 5 (SCHEDULING: CYCLICAL SCHEDULING) 15.26 Daniel's Barber Shop at Newark Airport is open 7 days a week but has fluctuating demand. Daniel Ball is inter- ested in treating his barbers as well as he can with steady work and preferably 5 days of work with two consecutive days off. His analysis of his staffing needs resulted in the following plan. Schedule Daniel's staff with the minimum number of barbers. DAY MON. TUE. WED. THU. FRI. SAT. SUN. 6 5 5 5 6 4 3 Barbers neededarrow_forwardAllocate the tasks to workstations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks.arrow_forward
- Question 3: A catering company must have the following number of clean napkins available at the beginning of each of the next four days: day 1: 15, day 2: 12, day 3: 18, and day 4: 6. After being used, a napkin can be cleaned by one of two methods: fast service or slow service. Fast service costs $0.10 per napkin, and a napkin cleaned via fast service is available for use the day after it is last used. Slow service costs $0.06 per napkin, and a napkin cleaned via slow service is available two days after they were last used. New napkins can be purchased for a cost of $0.20 per napkin. Part A: Formulate the problem as a minimum cost transportation problem. Part B: Use Excel Solver to solve the problem (provide exact values for all variables and the optimal objective function).arrow_forwardQuestion 4 Sunny Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for (1) cutting and sewing and (2) delivery of each of the suits. Suit 1 2 3 Cut and sew 4 7 6 Deliver 2 7 5 Determine a sequence that will minimize the total completion time for these jobs. Determine the efficiency of the sequences.arrow_forwardQuestion: Pistons for automotive engines can be formed either by casting or forging technique. Traditional cast pistons are considered good enough by most engine tuners and builders when it comes to standard setups. They suffer no significant drawback in terms of compression and service life. Performance enthusiasts and custom engine builders prefer the use of forged pistons because they are more durable and easily customised to any configuration, which is essential for engine tuning. Cast pistons are made with the use of large, specialised equipment made up of a mould where the molten aluminium alloy is poured to create the piston shape. Forged pistons employ a single-cast billet of the alloy which is stamped into the required shape using a die. The shape of the die determines the size and shape of the piston. The productivity rates for both methods are different. How do i calculate this?: In this Question, we assume that one unit piston weighs 1.54kg. To calculate the cost per part…arrow_forward
- Question: B) Identify The Economic Order Quanitity And Consider The Implications For Making An Error In Calculating Economic Order Quanitity. This problem has been solved! See the answer b) Identify the economic order quanitity and consider the implications for making an error in calculating economic order quanitity.arrow_forwardTwo senior managers (Brad and Dave) at Alpine Inc. are disagreeing about the managerial skills needed by the person who will be chosen to lead the company's next product development project. Brad argues that the person needs strong technical skills and substantial knowledge about the latest technology relevant for the project, but Dave says that the person must first and foremost have strong conceptual skills in order to effectively manage the project. The statement that weakens Brad's argument is: Question 20 options: A) The existing product development manager with the strongest conceptual skills in the company also has the weakest technical skills. B) The project is complex and has unusual requirements. C) The existing product development manager with the weakest technical skills also has the weakest human relations skills. D) The project is very large and…arrow_forwardsolve this i want now before 11 clockarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.