Concept explainers
a)
To determine: Thejob sequence, flow time, utilization metric, average number of jobs, and average lateness for EDD, SPT, LPT, and FCFS.
Introduction:
b)
To determine: The dispatching rule that has the best score in flow time.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
c)
To determine: The dispatching rule that has the best score in utilization metric.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
d)
To determine: The dispatching rule that has the best score in average lateness.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
e)
To determine: The dispatching rule that would be selected by Person X.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
Want to see the full answer?
Check out a sample textbook solutionChapter 15 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
- Question A.Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this line Fastarrow_forwardQuestion one: Suppose a radiology department uses FCFS to determine how to sequence patient x-rays. Assuming these data are representative, compare between FCFS and other scheduling rules should the radiology department be using and why Processing Time (Minutes) Due Time (Minutes from Now) Patient A 35 140 B 15 180 35 360 D 25 290 E 30 420 F 25 20 G 35 180 H 30 290 20 110 K 25 150 L 15 270 M 30 390 20 220 20 400 P 10 330 Q 10 80 R 15 230 20 370arrow_forwardFinite capacity scheduling Question 20 options: schedules jobs through a number of work centers, each with one or more machines. All of these choices are correct. is an extension of the theory of constraints. requires that jobs are scheduled whole (cannot be split).arrow_forward
- QUESTION 5 (SCHEDULING: CYCLICAL SCHEDULING) 15.26 Daniel's Barber Shop at Newark Airport is open 7 days a week but has fluctuating demand. Daniel Ball is inter- ested in treating his barbers as well as he can with steady work and preferably 5 days of work with two consecutive days off. His analysis of his staffing needs resulted in the following plan. Schedule Daniel's staff with the minimum number of barbers. DAY MON. TUE. WED. THU. FRI. SAT. SUN. 6 5 5 5 6 4 3 Barbers neededarrow_forwardQuestion fourThree jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B1 5 42 7 73 3 5Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardQuestion one: Suppose a radiology department uses FCFS to determine how to sequence patient x-rays. Assuming these data are representative, compare between FCFS and other scheduling rules should the radiology department be using and why Processing Time (Minutes) Due Time (Minutes from Now) Patient A 35 140 B 180 15 35 360 25 290 E 30 420 25 20 G 35 80 30 290 20 110 K 25 15 150 270 M 30 390 20 220 20 400 10 330 10 80 R 15 230 20 370 当 五犯 LEzlolalolclnarrow_forward
- Question Three Processing times (including setup times), and due dates for five jobs waiting to be processed at a work center are given in the following table. By Using the SPT rule determine the following: The sequence of jobs The average flow time The average job tardiness The average number of jobs at the work center Job Processing Time (hours) Hour Due A 17 15 B 10 25 C 5 20 D 7 32 E 11 38arrow_forwardQUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (ii) Illustrate the flow (throughput) times to complete the baking and decorating on atimeline chart.arrow_forwardQUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.arrow_forward
- Question four Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A 1 4 2 7 7 3 3 Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardQuestion attachedarrow_forwardQUESTION 6 The framing department has six jobs waiting to be processed as shown in Table 3 below. It is now time zero and all jobs are ready to begin. Each has only one operation remaining. Table 3 Jobs (In order of arrival) Processing Time Due Date A 5 12 B 7 18 C 8. 14 D 3 10 E 9 22 F 12 17 Using minimum flow time as the evaluation criterion, recommend the best rule to sequence the jobs from the list below: i. FCFS ii. SOT iii. EDD iv. STRarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.