Concept explainers
a)
To determine: Thejob sequence, flow time, utilization metric, average number of jobs, and average lateness for EDD, SPT, LPT, and FCFS.
Introduction:
b)
To determine: The dispatching rule that has the best score in flow time.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
c)
To determine: The dispatching rule that has the best score in utilization metric.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
d)
To determine: The dispatching rule that has the best score in average lateness.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
e)
To determine: The dispatching rule that would be selected by Person X.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
Want to see the full answer?
Check out a sample textbook solutionChapter 15 Solutions
Operations Management
- Question one: Suppose a radiology department uses FCFS to determine how to sequence patient x-rays. Assuming these data are representative, compare between FCFS and other scheduling rules should the radiology department be using and why Processing Time (Minutes) Due Time (Minutes from Now) Patient A 35 140 B 180 15 35 360 25 290 E 30 420 25 20 G 35 80 30 290 20 110 K 25 15 150 270 M 30 390 20 220 20 400 10 330 10 80 R 15 230 20 370 当 五犯 LEzlolalolclnarrow_forwardQ. 3 What is the total makespan from Question 1? Question 1: Four floral arranging jobs are to be carried out across three stations: A (Arrange), B (Bag), C (crop) shown. The station sequences and job times in minutes are shown below, along with the due dates for each job. Using an "earliest due date" job dispatching priority rule, which, if any, of the jobs in will be late? Answer was Job 4 Group of answer choices a. 100 b. 130 c. 150 d. 170 e. 200arrow_forwardFinite capacity scheduling Question 20 options: schedules jobs through a number of work centers, each with one or more machines. All of these choices are correct. is an extension of the theory of constraints. requires that jobs are scheduled whole (cannot be split).arrow_forward
- Question 1 Four floral arranging jobs are to be carried out across three stations: A (Arrange), B (Bag), C (crop) shown. The station sequences and job times in minutes are shown below, along with the due dates for each job. Using an "earliest due date" job dispatching priority rule, which, if any, of the jobs in will be late? Tip: create a Gantt chart schedule before answering Questions 4 & 5. a. Jobs 2 & 3 b. Jobs 3 & 4 c. Job 3 d. Job 4 e. None of the jobs will be latearrow_forwardQuestion Three Processing times (including setup times), and due dates for five jobs waiting to be processed at a work center are given in the following table. By Using the SPT rule determine the following: The sequence of jobs The average flow time The average job tardiness The average number of jobs at the work center Job Processing Time (hours) Hour Due A 17 15 B 10 25 C 5 20 D 7 32 E 11 38arrow_forwardQuestion fourThree jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B1 5 42 7 73 3 5Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forward
- QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (ii) Illustrate the flow (throughput) times to complete the baking and decorating on atimeline chart.arrow_forwardQUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.arrow_forwardQuestion 12 Which of the following statements regarding PERT times is true? Pessimistic time estimate is an estimate of the minimum time an activity will require Optimistic time estimate is an estimate of the minimum time an activity will require Most likely time estimate is an estimate of the maximum time an activity will require Optimistic time estimate is an estimate of the maximum time an activity will requirearrow_forward
- Question four Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A 1 4 2 7 7 3 3 Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardQuestion 4: Six jobs waiting at a workstation will be processed in order, starting with the one with the shortest break time. In the table below, the time elapsed since the arrival of the works, the time remaining to the delivery and the processing time are given. According to this, create the work order and fill in the data in the relevant table.(fill in the second table in the photos)a) What is the average delay time with the generated order?b) How many hours is the average flow time?c) How many jobs will be delayed?d) How many jobs will not be delayed?arrow_forwardQuestion 3 Little’s LawA bank is processing job applications. Typical processing time for one application is 4 weeks. The bank can process 5 applications per week. The department is trying to improve efficiency by reduce the processing time to 2 weeks. What is the reduction of applications under review after the efficiency improvement?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.