Operations Management: Processes and Supply Chains (11th Edition)
11th Edition
ISBN: 9780133872132
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 10, Problem 20P
The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck opera lion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival.
- Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due.
- Which rule gives the best
schedule , in your judgment? Why?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Three jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table.
Job Processing Time (days) Due Date
A 2 8
B 6 6
C 5 13
Using the earliest due date (EDD) rule, the average tardiness of the five jobs is:
Write the Objectives of Workcenter Scheduling?
The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD.
Job
ProcessingTime at EngineLathe (hours)
TimeRemainingUntil Due Date(days)
Number ofOperationsRemaining
Shop TimeRemaining(days)
CR
S/RO
1
2
3
4
2.3
10.5
6.2
15.6
15
10
20
8
10
2
12
5
6.1
7.8
14.5
10.2
2.46
1.28
1.38
0.78
0.89
1.10
0.46
-0.44
Chapter 10 Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Ch. 10 - List the types of costs incurred when employees...Ch. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Explain why management should be concerned about...Ch. 10 - The Barberton Municipal Division of Road...Ch. 10 - Bob Canton’s golf camp estimates the following...Ch. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Management at the Kerby Corporation has determined...Ch. 10 - Gretchen’s Kitchen is a fast-food restaurant...
Ch. 10 - Prob. 7PCh. 10 - Tax Prep Advisers, Inc. has forecasted the...Ch. 10 - Climate Control, Inc. makes expedition-quality...Ch. 10 - Prob. 11PCh. 10 - Gemini Inc. is using the Sales and Operations...Ch. 10 - Gerald Glynn manages the Michaels Distribution...Ch. 10 - Cara Ryder manages a ski school in a large resort...Ch. 10 - Prob. 15PCh. 10 - Prob. 17PCh. 10 - The Hickory Company manufactures wooden desks....Ch. 10 - Prob. 19PCh. 10 - The Mowry Machine Shop still has five jobs to be...Ch. 10 - If we use the same number of workers in each...Ch. 10 - Prob. 2AMECh. 10 - Prob. 3AMECh. 10 - Suppose the overtime cost is $3,300. What happens...Ch. 10 - Suppose the undertime cost is the same as the...Ch. 10 - Prob. 6AMECh. 10 - Prob. 1VCCh. 10 - Does Starwood employ a chase, level, or mixed...Ch. 10 - How would staffing for the opening of a new hotel...Ch. 10 - Explain the alternatives available to Darlene Fry...Ch. 10 - Prob. 2C
Additional Business Textbook Solutions
Find more solutions based on key concepts
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
What is precedent, and how does it affect common law?
Business in Action
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Sunny Park Tailors has been asked to make three dif-ferent types of wedding suits for separate customers. The table below highlights the time taken in hours for (1) cutting and sewingand (2) delivery of each of the suits. Which schedule finishes sooner:first come, first served (123) or a schedule using Johnson’s rule?Times Taken for Different Activities (hours)SUIT CUT AND SEW DELIVER14 227 736 5arrow_forwardK Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received Darrow_forwardCategorize different scheduling procedures for various types of service operations, such as restaurants, hospitals, and airlinesarrow_forward
- Jack's Refrigeration Repair Service repairs and reconditions commercial icemakers at restaurants. Jack has four jobs to complete. Below are their processing times and due dates: Job Processing time (hours) Due date (hour) A 20 50 B 10 40 C 15 35 D 55 75 What is the average inventory if jobs are processed using the earliest due date rule?arrow_forwardThe Mowry Machine Shop still has five jobs to be processedas of 8 a.m. today (day 23) at its bottleneck operation. The daywhen the order arrived, processing time, and promised duedates are given in the following table. The jobs are listed inthe order of arrival.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of averageflow time and average days past due.b. Which rule gives the best schedule, in your judgment?Why?arrow_forwardFive jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 10 B 5 17 C 2 13 D 3 9 E 4 15 Using the earliest due date (EDD) rule, the average tardiness of the five jobs is:arrow_forward
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .arrow_forwardCompare the differences between flow classification and flow scheduling?arrow_forwardSunny Park Tailors has been asked to make three differenttypes of wedding suits for separate customers. The followingtable highlights the time taken in hours for (1) cutting and sewingand (2) delivery of each of the suits. Which schedule finishes sooner:first come, first served (123) or a schedule using Johnson's rule?arrow_forward
- A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forwardThe mowry machine shop still has five jobs to be processed as of 8A.M today (day 29) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in order of arrival: Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 12 4 10 B 7 3 24 C 5 10 16 D 3 8 7 E 1 4 13 Develope serpate schedules by using the FCF and EDS rules. Using FCF, the order is Using EDS, the order is The average flow time and average days past due are. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardIn a few words, explain how to prevent a process getting starved in priority scheduling.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY