The Hickory Company manufactures wooden desks. Management
The due dates reflect the need for the order to be at its next operation.
- Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.
- Comment on the performance of the two rules relative to these measures.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using the FCFS rule for scheduling, the sequence is
Sunny Park Tailors has been asked to make three different
types of wedding suits for separate customers. The table
below highlights the time taken in hours for cutting and
sewing (process 1) and delivery (process 2) of each of the
suits
Times Taken for Different Activities (hours)
Cut and Sew
Suit
1
2
3
7
4
5
Deliver
2
3
6
Assume that orders for suits have been listed in the above
table in the order in which they were received.
C
The Hickory Company manufactures wooden desks. Manage-ment schedules overtime every weekend to reduce the backlogon the most popular models. The automatic routing machineis used to cut certain types of edges on the desktops. The fol-lowing orders need to be scheduled for the routing machine:
The due dates reflect the need for the order to be at its nextoperation.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of average flowtime and average past due hours.b. Comment on the performance of the two rules relative tothese measures
Joan has a small design and tailoring shop making custom outfits for women. She has two employees. Each employee only begins working on a dress when a customer order has
been received and then she makes the dress from beginning to end. The average production time of a dress is 1.8 days, with a standard deviation of 2.1 days. Historically, Joan has
been receiving orders with interarrival times of one day on average. The interarrival times of orders have a coefficient of variation of one.
(Carry at least 4 decimal places in all intermediate calculations. Round your final answer to 2 decimal places.)
What is the expected waiting time, in days, between when an order is received and when production begins on the dress?
A. 9.12 days B. 6.50 days C. 1.23 days D.3.41 days
Chapter 10 Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Ch. 10 - List the types of costs incurred when employees...Ch. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Explain why management should be concerned about...Ch. 10 - The Barberton Municipal Division of Road...Ch. 10 - Bob Canton’s golf camp estimates the following...Ch. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Management at the Kerby Corporation has determined...Ch. 10 - Gretchen’s Kitchen is a fast-food restaurant...
Ch. 10 - Prob. 7PCh. 10 - Tax Prep Advisers, Inc. has forecasted the...Ch. 10 - Climate Control, Inc. makes expedition-quality...Ch. 10 - Prob. 11PCh. 10 - Gemini Inc. is using the Sales and Operations...Ch. 10 - Gerald Glynn manages the Michaels Distribution...Ch. 10 - Cara Ryder manages a ski school in a large resort...Ch. 10 - Prob. 15PCh. 10 - Prob. 17PCh. 10 - The Hickory Company manufactures wooden desks....Ch. 10 - Prob. 19PCh. 10 - The Mowry Machine Shop still has five jobs to be...Ch. 10 - If we use the same number of workers in each...Ch. 10 - Prob. 2AMECh. 10 - Prob. 3AMECh. 10 - Suppose the overtime cost is $3,300. What happens...Ch. 10 - Suppose the undertime cost is the same as the...Ch. 10 - Prob. 6AMECh. 10 - Prob. 1VCCh. 10 - Does Starwood employ a chase, level, or mixed...Ch. 10 - How would staffing for the opening of a new hotel...Ch. 10 - Explain the alternatives available to Darlene Fry...Ch. 10 - Prob. 2C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Jane Reed bakes breads and cakes in her home for parties and other affairs on a contract basis. Jane has only one oven for baking. One particular Monday morning she finds that she has agreed to complete five jobs for that day. Her husband John will make the deliveries, which require about 15 minutes each. Suppose that she begins baking at 8:00 A.M. (given) Determine the sequence in which she should perform the jobs in order tominimizea. Mean flow time.b. Number of tardy jobs.c. Maximum lateness.arrow_forwardCurrently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Upper AA 6 18 66 Upper BB 3 24 58 Upper CC 2 32 100 Upper DD 10 22 26 Upper EE 8 12 50 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Part 2 Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence 1 2 3 4 5 Customer D E A B C Part 3 Using…arrow_forward12-13 Mike Dreskin manages a large Los Angeles movie theater complex called Cinema I, II, III, and IV. Each of the four auditoriums plays a different film; the schedule is set so that starting times are staggered to avoid the large crowds that would occur if all four movies started at the same time. The theater has a single ticket booth and a cashier who can maintain an average service rate of 280 movie patrons per hour. Service times are assumed to follow an exponential distribution. Arrivals on a typically active day are Poisson distributed and average 210 per hour. To determine the efficiency of the current ticket operation, Mike wishes to examine several queue operating characteristics. a. Find the average number of moviegoers waiting in line to purchase a ticket. b. What percentage of the time is the cashier busy? c. What is the average time that a customer spends in the system? d. What is the average time spent waiting in line to get to the ticket window? e. What is the…arrow_forward
- Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The table below pertains to the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date, arriving order). Today is day 1. Job Process Time ABCD Work Center Work Center 10 20 3 4 3 3 3 5 4 1 Due DateArriving order 8 24 18 15 2143 D If the jobs are scheduled by the shortest process time (SPT) rule, the total idle time (total of both WCs) during day 1 through day end (last job finishing date) is: Hint: you need to first determine the job's operation order by SPT rule. Then in each work center, you need to schedule each job's start date and end date on both WCs. 12 11 10 9 None of themarrow_forwardHow do standard circular flow and expanded circular flow differ?arrow_forwardAssumMe a customer orders a product online. SupPpose that the product is delivered later in the weEek. The time between the order placement and order delivery is known as: a. waitT time b. queue time c. cycle time d. process timearrow_forward
- Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. The table below provides demand data: Grilled Vegetables Grilled Chicken Pastrami Demand per hour 25 9 12 There are up to five steps in the process of making sandwiches listed below with activity times (if no activity time, then than step is not done for that sandwich). Only 50% of customers want their sandwich toasted, no matter which sandwich is ordered. Step Grilled Vegetables(in minutes) Grilled Chicken(in minutes) Pastrami(in minutes) Cut bread 1 1 1 Grill 1.2 1.2 Slice meat 2 Toast 1.2 1.2 1.2 Wrap 0.8 0.8 0.8 Suppose Panini employs 1 worker at each step. a) Does Panini have enough capacity to fulfill the current demand for sandwiches? (b) What is the current capacity cushion for Panini? (as a %) c) If demand for Pastramis increase with the percentage indicated below, how much additional workers should Panini hire (if any), and where…arrow_forwardFive jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta R 20 10 S 25 30 T 30 20 U 35 35 V 15 25 Part 2 A. V−S−U−T−R B. V−R−U−S−T C. R−V−T−S−U D. S−U−T−V−R E. R−S−T−U−Varrow_forwardFour trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that hasonly a single service bay. The trucks are labeled in the order that they arrived at thedock. Assume the current time is 1:00 P.M. The times required to unload each truck and the times that the goods they contain are due in the plant are given in thefollowing table.Truck Unloading Time (minutes) Time Material Is Due1 20 1:25 P.M.2 14 1:45 P.M.3 35 1:50 P.M.4 10 1:30 P.M.Determine the schedules that result for each of the rules FCFS, SPT, EDD, andCR. In each case compute the mean flow time, average tardiness, and number oftardy jobs.arrow_forward
- Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Question Viewer Time Since Order Arrived Customer (days ago) Processing Time (days) Due Date (days from now) A 3 B 2 C 10 D E 8 6 22228 24 32 58 100 20 26 12 50 66 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence 1 2 3 4 5 Customer C D E A B Using the EDD (earliest due date) decision rule for sequencing the customers, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 2 3 4 5 Customer C D A E B The average flow time and average days past due for each option are: (Enter your responses…arrow_forwardDescribe scheduling needs in intermediate-volume systemsarrow_forwardFive jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence? O A. V OB. U O C. R OD. S O E. T Job R S T Alpha 20 23 50 26 55 Beta 34 35 20 26 75arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY