The MXN Sdn.Bhd. has identified eight activities that would need to be implemented in order to complete the construction project as listed in the table below. Using the PERT three-estimate approach, the company has obtained the estimated duration and the precedence relationships for each activity. In addition, the company may get penalized if it fails to complete the project within 35 weeks. Activity A B с D E F G H Table 2: Project Description Immediate predecessor(s) None A A None B,C C C,D D,F E,G Optimistic a 2 A 4 7 3 2 SKT Time estimate (week) Most likely 3 m 6 8 6 13 7 4 Pessimistic b 7 9 8 16 13 17 9 9 (a) Construct the activity on the node (AON) network for this project. (b) Compute the expected activity time and the variance for each activity. (c) Determine the forward and backward pass, activity slack, and identify the critical path.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The MXN Sdn. Bhd. has identified eight activities that would need to be implemented in order to
complete the construction project as listed in the table below. Using the PERT three-estimate
approach, the company has obtained the estimated duration and the precedence relationships for
each activity. In addition, the company may get penalized if it fails to complete the project within
35 weeks.
Activity
A
B
с
D
E
F
G
H
Immediate
predecessor(s)
None
A
A
None
B,C
C,D
Table 2: Project Description
D, F
E, G
Optimistic
2
7
4
7
3
2
Time estimate (week)
SKT
AM
X
Most likely
m
6
8
13
7
9
6
Pessimistic
b
7
16
13
17
9
9
(a) Construct the activity on the node (AON) network for this project.
(b) Compute the expected activity time and the variance for each activity.
termine the forward and backward pass, activity slack, and identify the critical path.
Estimate the probability that all the activities on the current critical path will be completed
within 35 weeks.
(e) Estimate the probability that the company may get penalized due to the late project
completion.
Transcribed Image Text:The MXN Sdn. Bhd. has identified eight activities that would need to be implemented in order to complete the construction project as listed in the table below. Using the PERT three-estimate approach, the company has obtained the estimated duration and the precedence relationships for each activity. In addition, the company may get penalized if it fails to complete the project within 35 weeks. Activity A B с D E F G H Immediate predecessor(s) None A A None B,C C,D Table 2: Project Description D, F E, G Optimistic 2 7 4 7 3 2 Time estimate (week) SKT AM X Most likely m 6 8 13 7 9 6 Pessimistic b 7 16 13 17 9 9 (a) Construct the activity on the node (AON) network for this project. (b) Compute the expected activity time and the variance for each activity. termine the forward and backward pass, activity slack, and identify the critical path. Estimate the probability that all the activities on the current critical path will be completed within 35 weeks. (e) Estimate the probability that the company may get penalized due to the late project completion.
Expert Solution
steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.