The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weeks) Crash Time (weeks) Cost to Crash ($ per week) Immediate Predecessor(s) A 6 5 150 None B 8 6 200 None с 4 3 150 A D 4 3 200 A E 1 1 B F 3 3 C, D G 3 2 200 D, E H 3 3 1 350 F Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity Time according to schedule (weeks) A 6 Activity F G Time according to schedule (weeks) 3

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs
and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Activity
А
ABCDEFGH
с
I
Activity
A
B
пооо D
Normal Time
(weeks)
6
8
4
4
1
3
3
3
3
D
E
Crash Time
(weeks)
5
6
3
3
1
3
2
1
3
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
Time according to
schedule (weeks)
6
8
4
Cost to Crash
($ per week)
150
200
150
200
4
1
Activity
FLI -
200
350
G
H
Immediate Predecessor(s)
None
None
A
A
B
3
3
3
3
C, D
D, E
F
G
Time according to
schedule (weeks)
D
Transcribed Image Text:The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity А ABCDEFGH с I Activity A B пооо D Normal Time (weeks) 6 8 4 4 1 3 3 3 3 D E Crash Time (weeks) 5 6 3 3 1 3 2 1 3 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) 6 8 4 Cost to Crash ($ per week) 150 200 150 200 4 1 Activity FLI - 200 350 G H Immediate Predecessor(s) None None A A B 3 3 3 3 C, D D, E F G Time according to schedule (weeks) D
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.