The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 1 week to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z. 1 Click the icon to view the product structure and the time-phased product structure. In addition to 150 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Item S T U V W X Y Z Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release 1 2 3 Week 4 5 6 7 Lead Time (weeks) 2 2 2 1 2 1 2 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
8. The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm
manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 1 week to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z.
1
Click the icon to view the product structure and the time-phased product structure.
In addition to 150 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect
this change (type 0 if the input box is not used).
1: More Info
Level
0
1
Item
S
T
U
V
W
X
Y
Z
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
Gross req
Order release
The product structure.
T(1)
S
U (1)
2 V(2) W(2) X(2) Y(1) Z(2)
2
3
Week
4
5
6
7
1 2
V
NXZ
W
Lead Time
(weeks)
Y
T
U
The time-phased product structure.
3 4
Time in weeks
-LO
2
5
2
2
1
2
1
2
2
-SC
6
S
7
+
Transcribed Image Text:8. The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 1 week to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z. 1 Click the icon to view the product structure and the time-phased product structure. In addition to 150 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). 1: More Info Level 0 1 Item S T U V W X Y Z Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release Gross req Order release The product structure. T(1) S U (1) 2 V(2) W(2) X(2) Y(1) Z(2) 2 3 Week 4 5 6 7 1 2 V NXZ W Lead Time (weeks) Y T U The time-phased product structure. 3 4 Time in weeks -LO 2 5 2 2 1 2 1 2 2 -SC 6 S 7 +
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.