9. Item WWW is produced in a transfer line. Determine daily output rate given the following processing times and unit transfer strategy between the machines.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
9. Item WWW is produced in a transfer line. Determine daily output rate given the
following processing times and unit transfer strategy between the machines.
1 process
3nd process
5th process
Machine J
process
4th process
Machine LL Machine D Machine RR Machine S
Unit process .15 hr
|.12
.18
.16
.12
time
Note: 2 shifts work. 8 hours/shift.
10. How can we increase the output in the above problem? Discuss and show results.
11. Item YYY is processed on machine M1 first and then machine M2. The desired
annual output is 5000 units. Unfortunately, there are quality issues and the scrap factor
for M1 is 0.05 and for M2 is 0.10. Determine how many units we have to start the
process with.
12. Repeat problem 11 if we could recover 2% of scraps on M1 and 4% of scraps on M2.
Transcribed Image Text:9. Item WWW is produced in a transfer line. Determine daily output rate given the following processing times and unit transfer strategy between the machines. 1 process 3nd process 5th process Machine J process 4th process Machine LL Machine D Machine RR Machine S Unit process .15 hr |.12 .18 .16 .12 time Note: 2 shifts work. 8 hours/shift. 10. How can we increase the output in the above problem? Discuss and show results. 11. Item YYY is processed on machine M1 first and then machine M2. The desired annual output is 5000 units. Unfortunately, there are quality issues and the scrap factor for M1 is 0.05 and for M2 is 0.10. Determine how many units we have to start the process with. 12. Repeat problem 11 if we could recover 2% of scraps on M1 and 4% of scraps on M2.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.