The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table: Duration Predecessor 11 Activity Description A Design Procure prototype parts Fabricate parts Assemble prototype
The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table: Duration Predecessor 11 Activity Description A Design Procure prototype parts Fabricate parts Assemble prototype
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:EX 6-23 (Algo) The CyClon project team has started...
The Cyclon project team has started gathering the information necessary to develop a project network-predecessor activities and
activity time in days. The results of their meeting are found in the following table:
Activity Description
A
B
C
D
K
Y
G
H
I
J
K
L
Design
Procure prototype parts
Fabricate parts
Assemble prototype
Laboratory test
Pield test
Adjust design
order stock components
Order custom components
Assemble test production unit
Test unit
Document results
Duration Predecessor
11
6
What is the ES for Activity D?
What is the LF for Activity H?
What is the slack for Activity C?
What is the slack for Activity H?
What is the slack for Activity 17
What is the length of the project?
What is the critical path?
8
9
10
9
10
11
A
A
B, C
D
F
G
G
H, I
3
Part A. Draw the project network. Compute the early, late, and slack times for each activity.
time periods
Part B. Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 6
days of work but it will take 5 days for the parts to be delivered. Likewise, Order stock components will take 4 days of work and 5 days
for delivery and Order custom components will take 5 days of work and 5 days for delivery. Reconfigure the CyClon schedule by

Transcribed Image Text:Part B. Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 6
days of work but it will take 5 days for the parts to be delivered. Likewise, Order stock components will take 4 days of work and 5 days
for delivery and Order custom components will take 5 days of work and 5 days for delivery. Reconfigure the CyClon schedule by
entering the three finish-to-start lags.
What impact did these lags have on the original schedule? [(Click to select)
What impact did these lags have on the amount of work required to complete the project? [(Click to select)
Part C. Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not
willing to approve additional resources. One team member pointed out that the network contained only finish-to-start relationships and
that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the
following relationships could be converted into start-to-start lags:
. Procure prototype parts could start 6 days after the start of Design.
Fabricate parts could start 9 days after the start of Design.
Laboratory test could begin 1 day(s) after the start of Assemble prototype.
Field test could start 5 days after the start of Laboratory test.
Adjust design could begin 7 days after the start of Field test.
Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design.
Test unit could begin 10 days after the start of Assemble test production unit.
Document results could start 3 days after the start of Test unit.
Reconfigure the Cyclon schedule by entering all nine start-to-start lags.
What is the ES for Activity D?
What is the LF for Activity H?
What is the slack for Activity C?
What is the slack for Activity H?
What is the slack for Activity 1?
What is the length of the project?
What is the critical path?
time periods
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.