(a) Construct a product structure and a gross material requirements plan for the dependent inventory items. Identify all level, parents and components. (b) Construct a net material requirements plan (Item S & T only) for the product structure and the following on hand inventory.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The demand for subassembly S is 100 units in week 7. Each unit of S requires one unit of T
and 0.5 unit of U. Each unit of T requires one unit of V, two units of W, and one unit of X.
Finally, each unit of U requires 0.5 units of Y nd three unit of Z. One from manufacturers all
items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V,
3 weeks to make W, 1 week to make X, 2 weeks to make Y and 1 week to make Z.
(a) Construct a product structure and a gross material requirements plan for the dependent
inventory items. Identify all level, parents and components.
(b) Construct a net material requirements plan (Item S & T only) for the product structure
and the following on hand inventory.
Items
On hand inventory
Items
On hand inventory
S
20
W
30
T
20
25
U
10
Y
15
V
30
10
Transcribed Image Text:The demand for subassembly S is 100 units in week 7. Each unit of S requires one unit of T and 0.5 unit of U. Each unit of T requires one unit of V, two units of W, and one unit of X. Finally, each unit of U requires 0.5 units of Y nd three unit of Z. One from manufacturers all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y and 1 week to make Z. (a) Construct a product structure and a gross material requirements plan for the dependent inventory items. Identify all level, parents and components. (b) Construct a net material requirements plan (Item S & T only) for the product structure and the following on hand inventory. Items On hand inventory Items On hand inventory S 20 W 30 T 20 25 U 10 Y 15 V 30 10
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.