One unit of A is made of three units of B. one unit of C. and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B. C. E. and F have one-week lead times: A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 47, 47, and 197 are used for Items C, D, and E. respectively. Items C. E. and F have on-hand (beginning) inventories of 7, 47, and 147, respectively, all other items have zero beginning inventory. We are scheduled to receive 7 units of A in Week 2, 47 units of E in Week 1, and also 47 units of F in Week 1. There are no other scheduled receipts. If 27 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all components. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.) Item A CH=0 LT=2 SS=0 Item C CH=7 LT=1 SS-0 Q=47 Item B OH=0 LT=1 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements 1 2 34567 8

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Can you assist with Problem 3 Thank you kindly 

One unit of A is made of three units of B. one unit of C. and two units of D. B is composed of two units of E and one unit of D. C is
made of one unit of B and two units of E. E is made of one unit of F.
Items B. C. E. and F have one-week lead times: A and D have lead times of two weeks.
Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 47, 47, and 197 are used for Items C, D, and E.
respectively. Items C. E. and F have on-hand (beginning) inventories of 7, 47, and 147, respectively, all other items have zero beginning
inventory. We are scheduled to receive 7 units of A in Week 2, 47 units of E in Week 1, and also 47 units of F in Week 1. There are no
other scheduled receipts. If 27 units of A are required in Week 8. use the low-level-coded bill of materials to find the necessary
planned order releases for all components.
Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells
blank - be certain to enter "0" wherever required.)
Item A
CH=0
LT=2
SS=0
Q=L4L
Item C
OH=7
LT=1
SS=0
Item B
CH=0
LT=1
SS-O
Period
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
1
2
4
8
Transcribed Image Text:One unit of A is made of three units of B. one unit of C. and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B. C. E. and F have one-week lead times: A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 47, 47, and 197 are used for Items C, D, and E. respectively. Items C. E. and F have on-hand (beginning) inventories of 7, 47, and 147, respectively, all other items have zero beginning inventory. We are scheduled to receive 7 units of A in Week 2, 47 units of E in Week 1, and also 47 units of F in Week 1. There are no other scheduled receipts. If 27 units of A are required in Week 8. use the low-level-coded bill of materials to find the necessary planned order releases for all components. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.) Item A CH=0 LT=2 SS=0 Q=L4L Item C OH=7 LT=1 SS=0 Item B CH=0 LT=1 SS-O Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts 1 2 4 8
Q=L4L
Item D
OH = 0
LT=2
SS=0
Q = 47
Item E
OH = 47
LT=1
SS=0
Q = 197
Item F
OH = 147
LT=1
SS=0
Q=L4L
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Transcribed Image Text:Q=L4L Item D OH = 0 LT=2 SS=0 Q = 47 Item E OH = 47 LT=1 SS=0 Q = 197 Item F OH = 147 LT=1 SS=0 Q=L4L Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.