If 22 units of A are required in Week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned order releases for all components. (Leave the cells blank, whenever zero (0) is required.)
4.
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot (L4L) lot sizing is used for Items C, E, and F; lots of size 22, 50, and 200 are used for Items A, B, and D, respectively. Items A, B, D, and E have on-hand (beginning) inventories of 10, 15, 122, and 100, respectively; all other items have zero beginning inventories. We are
If 22 units of A are required in Week 10, use the low-level-coded bill-of-materials (product structure tree) to find the necessary planned order releases for all components. (Leave the cells blank, whenever zero (0) is required.)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 6 images