Joe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of the process includes washing and drying the clothes; the second step is pressing the clothing. Joe wants to minimize the amount of time it takes to do all the jobs. The five jobs waiting to be processed are shown here. Job Wash and Dry (hours) Press (hours) A 5 4 B 3 4 C 2 3 D 7 5 E 4 2 Wash and Dry Using FCFS, assume the jobs arrive in the order shown (A, then B, then C, etc.). Show the beginning time for each job and ending time for the whole process adding hours throughout the process. A -0 number of hours B-5 number of hours C-8 number of hours D-10 number of hours E-17 number of hours A B C D E 0 enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours Press
Joe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of the process includes washing and drying the clothes; the second step is pressing the clothing. Joe wants to minimize the amount of time it takes to do all the jobs. The five jobs waiting to be processed are shown here.
Job |
Wash and |
Press |
---|---|---|
A |
5 |
4 |
B |
3 |
4 |
C |
2 |
3 |
D |
7 |
5 |
E |
4 |
2 |
Wash and Dry
Using FCFS, assume the jobs arrive in the order shown (A, then B, then C, etc.). Show the beginning time for each job and ending time for the whole process adding hours throughout the process.
A -0 number of hours
B-5 number of hours
C-8 number of hours
D-10 number of hours
E-17 number of hours
A
B
C
D
E
0
enter a number of hours
enter a number of hours
enter a number of hours
enter a number of hours
enter a number of hours
enter a number of hours
Press