4- The following table shows three estimates values for a project. Assume that manager is interested in knowing the risk of an actual cost exceeding $51,000 and the risk of an actual cost non exceeding $49,500. Cost ($) Activities Lowest Highest cost Most likely cost Set up site office 3100 3300 3500 Prepare site laydown yard and temporary fencing 5700 6000 7800 Rough grade site (cut and fill) 4800 5500 6500 Install exterior fire line 6130 7000 7570 and building fire riser Excavate foundations 12700 13500 14300 Excavate elevator pit 6300 6500 6700 Set reinforcing and anchor bolts 7100 8000 9500

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
4- The following table shows three estimates values for a project. Assume that manager is interested in knowing the risk of an actual cost
exceeding $51,000 and the risk of an actual cost non exceeding $49,500.
Cost ($)
Activities
Highest
cost
Lowest
Most likely
cost
Set up site office
3100
3300
3500
Prepare site laydown
yard and temporary
fencing
5700
6000
7800
4800
Rough grade site (cut
and fill)
5500
6500
Install exterior fire line
and building fire riser
6130
7000
7570
Excavate foundations
Excavate elevator pit
Set reinforcing and
12700
13500
14300
6300
6500
6700
7100
8000
9500
anchor bolts
Transcribed Image Text:4- The following table shows three estimates values for a project. Assume that manager is interested in knowing the risk of an actual cost exceeding $51,000 and the risk of an actual cost non exceeding $49,500. Cost ($) Activities Highest cost Lowest Most likely cost Set up site office 3100 3300 3500 Prepare site laydown yard and temporary fencing 5700 6000 7800 4800 Rough grade site (cut and fill) 5500 6500 Install exterior fire line and building fire riser 6130 7000 7570 Excavate foundations Excavate elevator pit Set reinforcing and 12700 13500 14300 6300 6500 6700 7100 8000 9500 anchor bolts
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.