The project will take The critical path is The late start on Activity C is The slack on Activity Cis The slack on Activity Dis The early start on Activity E is days. days. days. days. days.
The project will take The critical path is The late start on Activity C is The slack on Activity Cis The slack on Activity Dis The early start on Activity E is days. days. days. days. days.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question
Rr.6.

Transcribed Image Text:nt
rences
EX6-6 (Algo) From the following information, develop...
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack,
and identify the critical path. How many days will the project take?
ID
PARCDE
с
Description
Survey site
Excavate site.
Install power lines
Install drainage
Pour foundation
The project will take
The critical path is
The late start on Activity C is
The slack on Activity C is
The slack on Activity Dis
The early start on Activity E is
Predecessor
None
A
B
B
C, D
Time
4
6
1
3
days.
days.
days.
days.
days.
< Prev
2 of 20
Next >
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,