Concept explainers
In all of the exercises involving variances, use “F” and “U” to designate favorable and unfavorable variances, respectively.
E8-1 through E8-5 use the following data:
The standard operating capacity of Tecate Manufacturing Co. is 1,000 units. A detailed study of the manufacturing data relating to the standard production cost of one product revealed the following:
- 1. Two pounds of materials are needed to produce one unit.
- 2. Standard unit cost of materials is $8 per pound.
- 3. It takes one hour of labor to produce one unit.
- 4. Standard labor rate is $10 per hour.
- 5. Standard
overhead (all variable) for this volume is $4,000.
Each case in E8-1 through E8-5 requires the following:
- a. Set up a
standard cost summary showing the standard unit cost. - b. Analyze the variances for materials and labor.
- c. Make journal entries to record the transfer to Work in Process of:
- 1. Materials costs
- 2. Labor costs
- 3. Overhead costs
(When making these entries, include the variances.)
- d. Prepare the
journal entry to record the transfer of costs to the finished goods account.
Standard unit cost;
1,000 units were started and finished.
Case 1: All prices and quantities for the cost elements are standard, except for materials cost, which is $8.50 per pound.
Case 2: All prices and quantities for the cost elements are standard, except that 1,900 lb of materials were used.
a.
Provide a standard cost summary providing the standard unit cost.
Explanation of Solution
Provide a standard cost summary providing the standard unit cost.
Materials—2 lb @ $8 | $16 |
Labor—1 hr @ $10 | $10 |
Factory overhead | $4 |
Standard unit cost | $30 |
Figure (1)
b.
Examine the variances for materials and labor.
Explanation of Solution
Case 1:
Calculate material price variance:
Working note:
Calculate Actual Quality:
Case 2:
Calculate materials quantity variance:
Note: There are no labor variances in these cases.
c.
Prepare journal entries.
Explanation of Solution
Case 1:
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $16,000 | ||
Materials Price Variance | $1,000 | ||
Materials | $17,000 | ||
(to record the entry for direct materials cost when the materials are issued into production) |
Table (1)
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $10,000 | ||
Payroll | $10,000 | ||
(to record the entry for direct labor cost) |
Table (2)
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $4,000 | ||
Applied Factory overhead | $4,000 | ||
(to record the entry applying factory overhead to work in process) |
Table (3)
Case 2:
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $16,000 | ||
Materials Quantity Variance | $800 | ||
Materials | $17,000 | ||
(to record the entry for direct materials cost when the materials are issued into production) |
Table (4)
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $10,000 | ||
Payroll | $10,000 | ||
(to record the entry for direct labor cost) |
Table (5)
Date | Account Title and Explanation | Debit ($) | Credit($) |
Work in Process | $4,000 | ||
Applied Factory overhead | $4,000 | ||
(to record the entry applying factory overhead to work in process) |
Table (6)
d.
Prepare the journal entry.
Explanation of Solution
Case 1 and case 2:
Date | Account Title and Explanation | Debit ($) | Credit($) |
Finished Goods | $30,000 | ||
Work in process | $30,000 | ||
(to record the entry for finished goods at standard cost) |
Table (7)
Want to see more full solutions like this?
Chapter 8 Solutions
Principles of Cost Accounting
Additional Business Textbook Solutions
FINANCIAL ACCT.FUND.(LOOSELEAF)
Horngren's Accounting (12th Edition)
Managerial Accounting (4th Edition)
Principles Of Taxation For Business And Investment Planning 2020 Edition
Financial Accounting (12th Edition) (What's New in Accounting)
Principles of Accounting Volume 1
- The management of Golding Company has determined that the cost to investigate a variance produced by its standard cost system ranges from 2,000 to 3,000. If a problem is discovered, the average benefit from taking corrective action usually outweighs the cost of investigation. Past experience from the investigation of variances has revealed that corrective action is rarely needed for deviations within 8% of the standard cost. Golding produces a single product, which has the following standards for materials and labor: Actual production for the past 3 months follows, with the associated actual usage and costs for materials and labor. There were no beginning or ending raw materials inventories. Required: 1. What upper and lower control limits would you use for materials variances? For labor variances? 2. Compute the materials and labor variances for April, May, and June. Identify those that would require investigation by comparing each variance to the amount of the limit computed in Requirement 1. Compute the actual percentage deviation from standard. Round all unit costs to four decimal places. Round variances to the nearest dollar. Round variance rates to three decimal places so that percentages will show to one decimal place. 3. CONCEPTUAL CONNECTION Let the horizontal axis be time and the vertical axis be variances measured as a percentage deviation from standard. Draw horizontal lines that identify upper and lower control limits. Plot the labor and material variances for April, May, and June. Prepare a separate graph for each type of variance. Explain how you would use these graphs (called control charts) to assist your analysis of variances.arrow_forwardRecompute the variances from the second Acme Inc. exercise using $0.0725 as the standard cost of the material and $14 as the standard labor cost per hour. How has your explanation of the variances changed?arrow_forwardplease solve and show full work with steps for better understanding Compute the direct materials variance, including its price and quantity variances. Note: Indicate the effect of each variance by selecting favorable, unfavorable, or no variance.arrow_forward
- The cost analyst for Sheffer Systems collected the following data concerning direct materials: Actual production 36,100 units Direct materials purchased (actual) Standard cost of materials purchased Standard direct materials costs per unit produced Standard price times actual amount of materials used Required: Compute the direct materials cost variances. Note: Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option. Direct Materials Price variance Efficiency variance Total direct materials cost variance $ 716,500 720,300 17 628,200 Farrow_forwardSchematize pertormance analysis and comment on variances. Following is the data of a manufacturing concern. From the figures given below, calculate: () Materials Cost Variance (W) Material Price Varlance (H) Material Usage Variance Product X During a particular period 160 tons of output was undertaken. The standard price per unit of materials is $20. The materials required for actual production were 4,000 units. An amount of $16,000 was spent on purchasing the materlals. The standard quantity of materials requlred for producing one fon of output is 120 units. Product Y The standard quantity of materlals required for producing one ton of output is 240 unils. The standard price per unit of materials is $24. During a porticular period d40 fons of production were 24.000 units. An amount of $48.000 was spent on purchasing the materials output was undertaken. The materials required for octualarrow_forwardCompute for controllable variance.arrow_forward
- The following data relate to product no. 89 of Des Moines Corporation: Direct material standard: 5 square feet at $3.30 per square foot Direct material purchased: 37,000 square feet at $3.60 per square foot Direct material consumed: 36,400 square feet Manufacturing activity: 7,200 units completed Assume that the company computes variances at the earliest point in time. AJThe direct-material quantity variance is: B)The direct-material price variance is:arrow_forward1. For direct materials: a. Compute the price and quantity variances. b. The materials were purchased from a new supplier who is anxious to enter into a long- term purchase contract. Would you recommend that the company sign the contract? Explain. 2. For labor employed in the production of Fruta: a. Compute the rate and efficiency variances. b. In the past, the 10 persons employed in the production of Fruta consisted of 4 senior workers and 6 assistants. During June, the company experimented with 5 senior workers and 5 assistants. Would you recommend that the new labor mix be continued? Explain. 3. Compute the variable overhead rate and efficiency variances. What relation can you see between this efficiency variance and the labor efficiency variance?arrow_forward5) The following data relate to product no. 89 of Mansion Corporation. Direct material standard: 3 square feet at $2.50 per square foot Direct material purchased 30,000 square feet at $2.60 per square foot Direct material consumed: 29,200 square feet Manufacturing activity: 9,600 units completed Assume that the company computes variances at the earliest point in time. The direct-material quantity variance is: A) S1,040F B) S1,000U. C) S2,000F D) $1,000F. E) S1,040U.arrow_forward
- Franklin Manufacturing Company established the following standard price and cost data: Sales price $ 8.60 per unit Variable manufacturing cost $ 3.90 per unit Fixed manufacturing cost Fixed selling and administrative cost Franklin planned to produce and sell 2,300 units. Actual production and sales amounted to 2,400 units. Required a. Determine the sales and variable cost volume variances. b. Classify the variances as favorable or unfavorable, d. Determine the amount of fixed cost that will appear in the flexible budget. e. Determine the fixed cost per unit based on planned activity and the fixed cost per unit based on actual activity. Complete this question by entering your answers in the tabs below. $ 2,700 total $ 700 total Req A and B Reg D a. Determine the sales and variable cost volume variances. b. Classify the variances as favorable or unfavorable. Note: Select "None" if there is no effect (i.e., zero variance). Sales Variable manufacturing Reg E Volume Variancesarrow_forwardCompute for the variances of the problem using the information given. Answer the numbers only up to two decimal places. A. Compute for Direct Materials Spending Variance B. Compute for Direct Materials Price Variance C. Compute for Direct Materials Quantity Variancearrow_forwardCompute for the variances of the problem using the information given. Answer the numbers only up to two decimal places. A. Compute for Labor Efficiency Variance B. Compute for Labor Spending Variance C. Compute for Labor Rate Variancearrow_forward
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College