Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9780078024108
Author: William J Stevenson
Publisher: McGraw-Hill Education
Question
Book Icon
Chapter 7.S, Problem 3P

a)

Summary Introduction

To determine: The number of days for first 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for first 10 installations is 56.93 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for first 10 installations:

At 85% learning curve, and 10 unit number, the unit factor is 7.116 (using learning curve coefficient table)

T110=8×7.116=56.93days (1)

The times for all 10 installations are calculated by multiplying first unit of 8 with the unit factor 7.116 which yields 56.93 days.

Hence, the number of days for first 10 installations is 56.93 days.

b)

Summary Introduction

To determine: The number of days for second 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for second 10 installations is 42.29 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for second 10 installations:

To calculate the number of days for second 10 installations which is from 11 to 20, the numbers of days of installations for 1 to 20 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 10.

Number of installation of first 20 units:

At 85% learning curve, and 20 unit number, the unit factor is 12.402 (using learning curve coefficient table)

T120=8×12.402=99.22days

The times for all 20 installations are calculated by multiplying first unit of 8 with the unit factor 12.402 which yields 99.22 days.

From the computed number of days, subtract the number of needed for first 10 installations,

Timefor11-20installations=(Timefor1-20installations-Timefor1-10installations)=99.22-56.93=42.29days

Hence, the number of days for second 10 installations is 42.29 days.

c)

Summary Introduction

To determine: The number of days for last 10 installations.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

c)

Expert Solution
Check Mark

Answer to Problem 3P

The number of days for last 10 installations is 37.51 days.

Explanation of Solution

Given information:

Initial unitT1=8daysLearningcurve=85%

Formula:

Tn=T1×Unitfactor

Calculation of number of days for last 10 installations:

To calculate the number of days for last10 installations which is from 21 to 30, the numbers of days of installations for 1 to 30 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 20.

Number of installation of first 30 units:

At 85% learning curve, and 30 unit number, the unit factor is 17.091 (using learning curve coefficient table)

T130=8×17.091=136.73days

The times for all 30 installations are calculated by multiplying first unit of 8 with the unit factor 17.091 which yields 136.73 days.

From the computed number of days, subtract the number of needed for first 20 installations,

Timefor21-30installations=(Timefor1-30installations-Timefor1-20installations)=136.73-99.22=37.51days

Hence, the number of days for final 10 installations is 37.51 days.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Items removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG    SORT            STORD            KNUJ            STUFF            FUDG
Could you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?
Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?

Chapter 7 Solutions

Operations Management (McGraw-Hill Series in Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,