EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7.S, Problem 13P
The Pullman Mfg., Inc., three-station work cell illustrated in Figure S7.8 has two machines at station 1 in parallel (The product needs to go through only one of the two machines before proceeding to station 2.) The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2.
a) What is the throughput time of the new work cell?
b) What is the bottleneck time of the new work cell?
c) If the firm operates 8 hours per day. 6 days per week, what is the weekly capacity of this work cell?
d) How did the addition of the second machine at workstation 2 affect the performance of the work cell from Problem S7.12?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before
proceeding to station 2.)
12 min/unit
Station 1
Machine A
Station 1
Machine B
12 min/unit
Station 2
4 min/unit
The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3.
a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number).
b) The bottleneck time of the new work cell is
minutes per unit (enter your response as a whole number).
Station 3
10 min/unit
part d
The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.)
SEE PICTURE
Answer C
Chapter 7 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Please do not give solution in image format thankuarrow_forwardThe Pullman Mig, Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 20 minunit Station 1 Machine A Station 1 Machine B 20 min/unit Station 2 6 min/unit Station 3 12 minunit The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3. a) The throughput time of the new work cell is 38 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 10 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 3 is 360 units (enter your response as a whole number). d) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation 3 is units (enter your response…arrow_forwardThe Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 3 minutes. The average traveling time (a round trip) is 27 minutes. a. How many Avis buses are traveling to and from the airport? Note: Round your answer to the nearest whole number. Number of Avis buses b. The branch manager wants to improve the service and suggests dispatching buses every 1.0 minute. She argues that this will reduce the average traveling time (a round trip) to 4.0 minutes. Is she correct? If your answer is negative, then what will the average traveling time be? average traveling time is minutesarrow_forward
- The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. Capacity: 20 units/hr Station 1 Machine A Station 2 Station 3 Station 1 Сарacity: Сарacity: Machine B 5 units/hr 10 units/hr Capacity: 20 units/hr a) The bottleneck time of the system is minutes per unit (enter your response as a whole number). b) V is the bottleneck station. c) The throughput time is minutes (enter your response as a whole number). d) If the firm operates 11 hours per day, 5 days per week, the weekly capacity of this work cell is units (enter your response as a whole number).arrow_forwardStudents are going through a three-step process to obtain their ID cards. Each student will spend 2 minutes at the registration desk before going to one of three cashiers to pay a fee for the ID card. After that, he/she will visit one of four ID processing stations to have his/her picture taken and ID card printed. Visits to the cashier and ID processing station take 10 and 20 minutes respectively. If the demand rate is 0.5 student per minute, how long does it take to process 20 students, assuming the system is full? Multiple Choice 100 minutes 127 minutesarrow_forwardThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 6 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 2 is whole number). units (enter your response as aarrow_forward
- A call center has been serving 900 customers per day, with a 10% capacity cushion. There have been complaints about the length of time customers have to wait before their call is answered. If the manager of the call center wants to double the capacity cushion, how much extra capacity is needed?arrow_forwardSuper Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. b. If weekly demand for the four products are A-148=180 units, B-356=310 units, B-457=280 units, and C-843=300 units, which station is the bottleneck, and is it capable of producing all the toys demanded? The bottleneck for Super Fun Industries is ▼ Station 1 Station 2 Station 3 Station 4 , with a utilization of ______%. (Enter your response rounded to one decimal place.)arrow_forwardNeed a,b,c Options for b and carrow_forward
- The three-station work cell at Pullman Mfg., Inc.is illustrated in Figure S7.8. It has two machines a t station I inparallel (i.e., the product needs to go through only one of the twomachines before proceeding to station 2). a) What is the throughput time of this work cell?b) What is the bottleneck time of this work cell?c) What is the bottleneck station?d) If the firm operates 8 hours per day, 6 days per week, what isthe weekly capacity of this work cell?arrow_forwardB. Draw and explain the flow charts of the Arrival Event and Service Completion Event.arrow_forwardSuper Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 12 hours a day, 5 days a week, and 8 hours on Saturday. a. If only toy A-148 is produced during a specific week, ____ units could be produced. (Enter your response rounded down to the nearest whole number.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY