Metters Cabinets, Inc., needs to choose a production method for its new office shelf, the Maxistand. To help accomplish this, the firm has gathered the following production cost data:
Metters Cabinets projects an annual demand of 24,000 units for the Maxistand. The Maxistand will sell for $120 per unit. a) Which process type will maximize the annual profit from producing the Maxistand?
b) What is the value of this annual profit?
a)

To determine: The process type that will maximize the annual profit by producing the Maxistand.
Answer to Problem 9P
The process type that will maximize the annual profit by producing the Maxistand is the intermittent process.
Explanation of Solution
Given information:
Process type | Annual fixed cost of plant & equip |
Variable costs (Per Unit) ($) | ||
Labor | Material | Energy | ||
Mass customization | $1,260,000 | 30 | 18 | 12 |
Intermittent | $1,000,000 | 24 | 26 | 20 |
Repetitive | $1,625,000 | 28 | 15 | 12 |
Continuous | $1,960,000 | 25 | 15 | 10 |
Annual demand = 24,000 units
Maxistand selling price = $120 / unit
Calculation of number of units:
Let ‘x’ be the number of units. The units is calculated by multiplying annual fixed cost with ‘x’ and summing with the total variable cost and equating it with multiplying the Maxistand selling price with ‘x’.
Mass customization:
Intermittent:
Repetitive:
Continuous:
Identifying least cost process at x = 24000 units:
The least cost is calculated by multiplying variable cost with the value of ‘x’ and summing it with the annual fixed cost.
Mass customization:
Intermittent:
Repetitive:
Continuous:
The cost is lower for intermittent process ($2,680,000) with the break-even point of 20,000. The intermittent process will increase the annual profit.
Hence, the best process is the intermittent process.
b)

To determine: The annual profit by following the intermittent process.
Answer to Problem 9P
The annual profit is $200, 000
Explanation of Solution
Given information:
Process type | Annual fixed cost of plant & equip |
Variable costs (Per Unit) ($) | ||
Labor | Material | Energy | ||
Mass customization | $1,260,000 | 30 | 18 | 12 |
Intermittent | $1,000,000 | 24 | 26 | 20 |
Repetitive | $1,625,000 | 28 | 15 | 12 |
Continuous | $1,960,000 | 25 | 15 | 10 |
Annual demand = 24,000 units
Maxistand selling price = $120 / unit
Calculation of number of units:
Let ‘x’ be the number of units. The units is calculated by multiplying annual fixed cost with ‘x’ and summing with the total variable cost and equating it with multiplying the Maxistand selling price with ‘x’.
Mass customization:
Intermittent:
Repetitive:
Continuous:
Identifying least cost process at x = 24000 units:
The least cost is calculated by multiplying variable cost with the value of ‘x’ and summing it with the annual fixed cost.
Mass customization:
Intermittent:
Repetitive:
Continuous:
Calculation of annual profit:
The annual profit is calculated by multiplying the selling price with annual demand and subtracting it from the cost of the intermittent process.
The annual profit is $200, 000.
Want to see more full solutions like this?
Chapter 7 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardThe deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forwardA copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forward
- How do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forwardGiven how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forwardDo you feel there is anything positive about rework?arrow_forward
- Do you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forwardHave you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forward
- Research a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forwardDo you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub