Textbook Question
Chapter 7, Problem 7.20MCQ
Basix Inc. calculates direct manufacturing labor variances and has the following information:
Actual hours worked: 200
Standard hours: 250
Actual rate per hour: $12
Standard rate per hour: $10
Given the information above, which of the following is correct regarding direct manufacturing labor variances?
- a. The price and efficiency variances are favorable.
- b. The price and efficiency variances are unfavorable.
- c. The price variance is favorable, while the efficiency variance is unfavorable.
- d. The price variance is unfavorable, while the efficiency variance is favorable.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Davenport Industries is working on its direct labor budget for the next two months. Each unit of output requires 0.48 direct labor hours. The direct labor rate is $9.20 per direct labor hour. The production budget calls for producing 7,200 units in July and 7,800 units in August. If the direct labor workforce is fully adjusted to the total direct labor hours needed each month, what would be the total combined direct labor cost for the two months?
What was the dollar amount of underallocated or overallocated manufacturing overhead?
The following monthly data are taken from Ramirez Company at July 31: Sales salaries, $520,000; Office salaries, $104,000; Federal
income taxes withheld, $156,000; State income taxes withheld, $35,000; Social security taxes withheld, $38,688; Medicare taxes
withheld, $9,048; Medical insurance premiums, $12,500; Life insurance premiums, $9,500; Union dues deducted, $6,500; and Salaries
subject to unemployment taxes, $61,000. The employee pays 40% of medical and life insurance premiums. Assume that FICA taxes
are identical to those on employees and that SUTA taxes are 5.4% and FUTA taxes are 0.6%.
1. & 2. Using the above information, complete the below table and prepare the journal entries to record accrued payroll, including
employee deductions, and cash payment of the net payroll (salaries payable) for July.
3. Using the above information, complete the below table.
4. Record the accrued employer payroll taxes and other related employment expenses and the cash payment of all liabilities…
Chapter 7 Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Ch. 7 - What is the relationship between management by...Ch. 7 - What are two possible sources of information a...Ch. 7 - Distinguish between a favorable variance and an...Ch. 7 - What is the key difference between a static budget...Ch. 7 - Why might managers find a flexible-budget analysis...Ch. 7 - Describe the steps in developing a flexible...Ch. 7 - List four reasons for using standard costs.Ch. 7 - How might a manager gain insight into the causes...Ch. 7 - List three causes of a favorable direct materials...Ch. 7 - Describe three reasons for an unfavorable direct...
Ch. 7 - How does variance analysis help in continuous...Ch. 7 - Why might an analyst examining variances in the...Ch. 7 - Prob. 7.13QCh. 7 - When inputs are substitutable, how can the direct...Ch. 7 - Benchmarking against other companies enables a...Ch. 7 - Metal Shelf Companys standard cost for raw...Ch. 7 - All of the following statements regarding...Ch. 7 - Amalgamated Manipulation Manufacturings (AMM)...Ch. 7 - Atlantic Company has a manufacturing facility in...Ch. 7 - Basix Inc. calculates direct manufacturing labor...Ch. 7 - Flexible budget. Sweeney Enterprises manufactures...Ch. 7 - Flexible budget. Bryant Companys budgeted prices...Ch. 7 - Flexible-budget preparation and analysis. Bank...Ch. 7 - Flexible budget, working backward. The Clarkson...Ch. 7 - Flexible-budget and sales volume variances....Ch. 7 - Price and efficiency variances. Sunshine Foods...Ch. 7 - Materials and manufacturing labor variances....Ch. 7 - Direct materials and direct manufacturing labor...Ch. 7 - Price and efficiency variances, journal entries....Ch. 7 - Materials and manufacturing labor variances,...Ch. 7 - Journal entries and T-accounts (continuation of...Ch. 7 - Price and efficiency variances, benchmarking....Ch. 7 - Static and flexible budgets, service sector....Ch. 7 - Flexible budget, direct materials, and direct...Ch. 7 - Variance analysis, nonmanufacturing setting. Joyce...Ch. 7 - Comprehensive variance analysis review. Ellis...Ch. 7 - Possible causes for price and efficiency...Ch. 7 - Material-cost variances, use of variances for...Ch. 7 - Direct manufacturing labor and direct materials...Ch. 7 - Direct materials efficiency, mix, and yield...Ch. 7 - Direct materials and manufacturing labor...Ch. 7 - Direct materials and manufacturing labor...Ch. 7 - Use of materials and manufacturing labor variances...Ch. 7 - Direct manufacturing labor variances: price,...Ch. 7 - Direct-cost and selling price variances. MicroDisk...Ch. 7 - Variances in the service sector. Derek Wilson...Ch. 7 - Prob. 7.47P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- At the beginning of the year, Vanguard Systems, Inc. determined that estimated overhead costs would be $720,000, while actual overhead costs for the year totaled $770,000. Furthermore, it was determined that the estimated allocation basis would be 75,000 direct labor hours, while direct laborers actually worked 78,000 hours. What was the dollar amount of underallocated or overallocated manufacturing overhead?arrow_forwardWhat are impaired assets and its pros and cons?arrow_forwardMing Chen started a business and had the following transactions in June. a. Owner invested $60,000 cash in the company along with $15,000 of equipment. b. The company paid $2,000 cash for rent of office space for the month. c. The company purchased $18,000 of additional equipment on credit (payment due within 30 days). d. The company completed work for a client and immediately collected $1,600 cash. e. The company completed work for a client and sent a bill for $7,300 to be received within 30 days. f. The company purchased additional equipment for $5,000 cash. g. The company paid an assistant $2,400 cash as wages for the month. h. The company collected $4,500 cash as a partial payment for the amount owed by the client in transaction e. i. The company paid $18,000 cash to settle the liability created in transaction c. j. The owner withdrew $1,500 cash from the company for personal use.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY