Question
Chapter 7, Problem 5PA
Summary Introduction
Interpretation: Utilization rate needs to measured using the given information with the help of the Resource Utilization formula.
Concept Introduction: Resource utilization is an important analytic to measure the capacity of the system. Utilization refers to the ratio of resources used to resources available.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A 30,000-seat college football stadium is used 18 times for games, concerts, andgraduation ceremonies. Each event averages four hours and assumes the stadium isfull for each event.The stadium is available 365 days a year from 6 am to midnight. What is stadium(seat) utilization?Can you think of one or two other assets that have such low resource utilization?
The staff training center at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 1800 employees per year. Since the training center was first put in use, the program has become more complex, so that 1400 now represents the most employees that can be trained per year. In the past year, 1350 employees were trained. Calculate the efficiency and the utilization of this system.
An executive conference center has the physical ability to handle 1,100 participants. However, conference management personnel believe that only 1,000 participants can be handled effectively for most events. The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. What are the utilization and efficiency of the conference facility?
. A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled maintenance of their…
A 30,000-seat college football stadium is used 20 times for games, concerts, and graduation ceremonies in a year. Each event averages 6 hours and assumes the stadium is full for each event. The stadium is available 365 days a year from 6 am to midnight. What is stadium (seat) utilization using?
Chapter 7 Solutions
OM6 ONLINE-LMS INTEGRATED ACCESS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A 30,000-seat college football stadium is used 20 times for games, concerts, and graduation ceremonies in a year. Each event averages 6 hours and assumes the stadium is full for each event. The stadium is available 365 days a year from 6 am to midnight. Find the stadium (seat) utilization.arrow_forwardA company has a factory that is designed so that it is most eficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardUnder ideal conditions, a picture frame manufacturing facility can produce 480 frames per day. Under normal conditions, the company schedules 434 frames per day. If the production manager sets the output rate to 382 frames per day, what is the resulting capacity cushion?arrow_forward
- The staff training centre at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 2100 employees per year. Since the training centre was first put in use, the program has become more complex, so that 1500 now represents the most employees that can be trained per year. In the past year, 1350 employees were trained. a) Calculate the efficiency and the utilization of this system. b) If the number of employees who signed up for training next year is 1475, what is the efficiency and utilization rate for next year?arrow_forwardA company has a factory that is designed so that it is most efficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardTeddy Fields is the kitchen manager at the Tanron Corporation International Headquarters. The facility he helps manage serves 3,000 employees per day. Teddy very much needs an additional dishwasher. He is now interviewing Wayne, who is an excellent candidate with five years of experience and who is now washing dishes at the nearby Roadway restaurant. Teddy normally starts his new dishwashers at $12.00 per hour. Wayne states that he currently makes $13.25 per hour; a rate that is higher than all but one of Teddy's current dishwashers. Wayne states that he simply will not leave his current job to take a “pay cut.” Should Teddy offer to hire Wayne at a rate higher than most of his current employees? Why or why not? (2 paragraphs)arrow_forward
- An airline company must plan its fleet capacity and itslong-term schedule of aircraft usage. For one flight seg-ment, the average number of customers per day is 70,which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand isexpected to increase to 84 customers for this flight seg-ment in three years, what capacity requirement should beplanned? Assume that management deems that a capacitycushion of 25 percent is appropriate.arrow_forwardAn airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, the average number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand is expected to increase to 92 customers for this flight segment in three years, what capacity requirement should be planned? Assume that management deems that a capacity cushion of 15 percent is appropriate. The needed capacity requirement is_____________customers per day. (Enter your response rounded up to the next whole number.)arrow_forwardAn airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, the average number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand is expected to increase to 80 customers for this flight segment in three years, what capacity requirement should be planned? Assume that management deems that a capacity cushion of 15 percent is appropriate. The needed capacity requirement is enter your response here customers per day. (Enter your response rounded up to the next whole number.)arrow_forward
- Taco House Taco House has a special on Wednesday nights from 5:00-10:00 PM: $5 for a Mega Taco. There are two cooks on duty during this time. They have an 80% utilization and a 90% efficiency. If it requires 4 minutes to prepare a Mega Taco, approximately how many Mega Tacos is Taco House able to produce during the Wednesday night special? Group of answer choices 108 162 216 153 182 144arrow_forwardA company has a factory that is designed so that it is most efi cient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardA train company runs trains every 15 minutes, however during peak time, they run at every 7.5minutes. Is this an example of capacity leading or lagging?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY