Interpretation: types of process.
Concept introduction: The four primary types of processes for producing goods and services are' '5" Projects, Job Shop Process, Flow Shop Process, and Continuous Flow Process.
Projects are process for producing unique products for a specific time and budget allotted.
- The job Shop process is organized around general-purpose equipment which is used to produced customized parts for different customers.
- Flow shop processes are organized around a fixed sequence of activities and process steps to produce a limited variety of similar products.
Finally, the Continuous Flow process is about producing highly standardized products with very large batches and volumes.

Explanation of Solution
A) iPads
iPads are produced in large volumes and sold across the world. There are only a few variants of the product. The manufacturer presumably buys all the parts from the supplier and assembles it in its facility. Therefore, a fixed sequence of activities and process steps is followed. All these attributes suggest that the type of the process Is: Flow shop process.
B) Wedding
Wedding has fixed dates for start and completion and every wedding is a unique outcome due to the specific needs of the families involved. The entire event can be subdivided into smaller tasks or milestones which need to be coordinated and completed to realize the outcome within time and budget. All these attributes match with Project
C. Paper
The product is highly standardized. There are very few variants existing. The batch sized for producing a variant is huge and so is the volume of production. The process Is extremely standardized and generally not very adaptive to customization. Therefore, the type of continuous process
D. Tax preparation
The service requires a similar set of resources (Including human skills and competence). These resources are equivalent to the general-purpose equipment. However, the service is customized based on the individualized requirement of the clients. The appropriate process type is the job shop process.
Want to see more full solutions like this?
Chapter 7 Solutions
OM6 ONLINE-LMS INTEGRATED ACCESS
- Because my tutor and I didnt get it rightarrow_forwardOperations Managementarrow_forwardHow does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forward
- My last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forwardThere's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forward
- Menu Item Sales and Cost Data Taco Salad: Number Sold: 127; Item Cost: $0.71; Selling Price: $3.25 Lasagna: Number Sold: 48; Item Cost: $0.92; Selling Price: $4.67 Chicken: Number Sold: 31; Item Cost: $1.20; Selling Price: $3.00 Green Beans: Number Sold: 14; Item Cost: $0.20; Selling Price: $1.00 Corn: Number Sold: 13; Item Cost: $0.24; Selling Price: $1.00 Rice: Number Sold: 9;Item Cost: $0.13; Selling Price: $1.00 Menu Item Classification: Low contribution margin, low menu mix % DOG High contribution margin, low menu mix % PUZZLE Low contribution margin, high menu mix % PLOWHORSE High contribution margin, high menu mix o/o STAR QUESTION 1 Complete the menu analyses worksheet below. Calculations will be done using the information above. Restaurant: Date: MealPeriod: (A) ☐ (B) (C) (D) (E) (F) (G) (H) (1) (J) Menu Mix Popularity % Item Item Sold/(Menu Mix Menu Menu Item Food Menu Contribution Contribution Contribution Category Item Mix %): (B/K) Cost Selling Margin Price Margin (E-D)…arrow_forward1) Around the Clock Production of Fire Nozzles View the videos Around the Clock Production of Fire Nozzles 1 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=132KoZwS0yMEgsToDUsZjJe (9.44 minutes, Ctrl+Click on the link) and Around the Clock Production of Fire Nozzles 2 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=44JM0cKtFLqHP5bad6KOHAm (7.43 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 12 and/or 13) after watching these videos. Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Cyberdyne Systems stocks and sells Cyberdyne glucose meters. The firm gathered the following information from its South Pasadena office: Demand = 19,500 units per year Ordering cost = $25 per order Holding cost = $4 per unit per year The firm’s operations manager wants to calculate the: a) EOQ for the glucose meters. b) Annual holding costs for the…arrow_forwardIn the following problems assume, unless otherwise stated, that S = $40, σ = 30%, r =8%,and δ =0. 13.1 Suppose you sell a 45-strike call with 91 days to expiration. What is delta? If the option is on 100 shares, what investment is required for a delta-hedged portfolio? What is your overnight profit if the stock tomorrow is $39? What if the stock price is $40.50?arrow_forward
- Question 1 M&H company ltd. sells television sets and has collected monthly sales data (in units) for the past 12 months as shown in table 1below: TABLE 1 Month Sales (Units) 1 120 2 135 3 150 4 165 5 180 6 200 7 195 8 210 9 225 10 240 11 255 12 270 Using the data provided, answer the following questions: a. Using a 3-month weighted moving average with weights 0.5, 0.3, and 0.2 (most recent month having the highest weight), calculate the forecast for month 13. [2 marks] b. If the company applies an exponential smoothing method with a smoothing constant (a) = 02, and assumes an initial forecast of 120 units for Month 1, calculate the forecast for month 13. [6 marks] c. Calculate the Mean Absolute Deviation (MAD) for the exponential smoothing method and weighted moving average method using the actual sales data for Months 4 to 12 and determine which method is more accurate. [8 marks] d. Compute the values of a (intercept) and b (slope) using the least squares method. [7 marks] e. Use the…arrow_forwardQuestion 4 MGM12026 Production and Operations Management semester il 2024 A company operates a manufacturing plant that produces two products, A and B. The plant has the following capacity data: . . Design Capacity: 15,000 machine hours per month Effective Capacity: 12,000 machine hours per month Actual Output (Utilized Capacity): 10,000 machine hours per month Additionally, the plant produces Product A and Product B, with the following production data: Product Demand (Units) Processing Time Contribution Margin ($ (hours per unit) per unit) A 3,000 2.5 40 B 4,000 1.5 30 a. Calculate the plant's i. Capacity Utilization [3 marks] ii. Effective Capacity Utilization [3 marks] iii. Efficiency. Interpret the results. [3 marks] b. Compute the total machine hours required to meet full demand for both products. [5 marks] c. Determine whether the plant has sufficient capacity to meet full demand. If not, calculate the shortfall in machine hours. [3 marks] d. Using the contribution margin per…arrow_forwardQuestion 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning