Question
Book Icon
Chapter 6.S, Problem 6P
Summary Introduction

To develop: Appropriate control chart and determine whether there is any cause for concern in the cutting process.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given information:

The following information is given:

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 6.S, Problem 6P , additional homework tip  1

Develop appropriate control chart:

To check whether the process is in control, create the appropriate control charts for the mean x¯ and the range R¯ .

Determine mean of the averages:

It can be calculated by taking the average of all given values for x¯ .

Mean of the average=Sum of x¯ valuesTotal hours=(3.25+3.10+3.22+3.39+3.07+2.86+3.05+2.65+3.02+2.85+2.83+2.97+3.11+2.83+3.12+2.84+2.86+2.74+3.41+2.89+2.65+3.28+2.94+2.64)24=71.5724=2.982

Hence, the mean of averages x¯¯=2.982

Determine mean of the ranges:

It can be calculated by taking the average of all given values for R.

Mean of the average=Sum of x¯ valuesTotal hours=(0.71+1.18+1.43+1.26+1.17+0.32+0.53+1.13+0.71+1.33+1.17+0.40+0.85+1.31+1.06+0.50+1.43+1.29+1.61+1.09+1.08+0.46+1.58+0.97)24=24.5724=1.024

Hence, the mean of ranges is R¯=1.024 .

Determine the upper control limit and lower control limit of x¯ -chart:

Determine the upper control limit (UCL) and the lower control limit (LCL) of the x¯ chart using the following equations:

UCL=x¯¯+A2×R¯ (1)

LCL=x¯¯A2×R¯ (2)

Here, the overall mean x¯¯=2.982 , the average range R¯=1.024 and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 4, the Mean factor is A2=0.729 (Refer the S6.1 table (Factors for computing control chart limits (3 sigma))).

Substitute into the equation (1),

UCL=x¯¯+A2×R¯=2.982in.+0.729×1.024in.=3.7285in.

Substitute into the equation (2),

LCL=x¯¯A2×R¯=2.982in.0.729×1.024in.=2.2355in.

Hence, the upper control limit is UCL=3.7285in. and the lower control limit is LCL=2.2355in. for mean.

Determine the upper control limit and lower control limit of R¯ -chart:

Determine the upper control limit (UCLR) and lower control limit (LCLR) of the R¯ chart using equations:

UCLR=D4×R¯ (3)

LCLR=D3×R¯ (4)

Here,

D3 refers to the lower range factor

D4 refers to the upper range factor

R¯ refers to the average range

Given the sample size of 4 for σ=3 , Lower range factor D3=0 and Upper range factor D4=2.282 (Refer the S6.1 table (Factors for computing control chart limits (3 sigma))).

Substitute into the equation (3),

UCLR=D4×R¯=2.282×1.024in.=2.3368in.

Similarly, substitute in equation (4),

LCLR=D3×R¯=0×1.024in.=0in.

Hence, the upper control limit is UCLR=2.3368in. and the lower control limit is LCLR=0in. .

Draw the control chart for the sample means:

The process mean is x¯¯=2.982 , UCL=3.7285in. , and LCL=2.2355in. .

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 6.S, Problem 6P , additional homework tip  2

Observe that all the sample means are well within the control limits. The first five observations are above the mean of the averages.

Draw the control chart for the sample range:

The average range is R¯=1.024 , UCLR=2.3368in. , and LCLR=0in. .

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 6.S, Problem 6P , additional homework tip  3

Observe that all the sample ranges are well within the control limits

Hence, the process seems to be in “statistical control”. (However, a process for making precision wires obviously should not have so much of variation in the mean or in the range.)

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Problem 5: Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this project are listed in the table below along with their costs and completion times in weeks. Activity Normal Crash Normal Crash Immediate Time Time Cost Cost Predecessor A 4 3 2,000 2,600 B 2 1 2,200 2,800 A C 3 3 500 500 A D 8 4 2,300 2,600 A E 6 3 900 1,200 B, D F 3 2 3,000 4,200 C, E G 4 2 1,400 2,000 F a. What is the project expected completion date? b. What is the total cost required for completing this project on normal time? c. If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.with diagram
not use ai please

Chapter 6 Solutions

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,