PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
bartleby

Concept explainers

Question
Book Icon
Chapter 6.S, Problem 10P

a)

Summary Introduction

To determine: The value of σx .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 10P

The value of σx is 0.61.

Explanation of Solution

Given information:

The following information is given:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  1

Sample size is given as 5 and process standard deviation is given as 1.36.

Determine σx :

The standard deviation of the sample means denoted by σx¯ is calculated by the following formula

σx¯=σn

Here,

σ refers to process standard deviation

n refers to the sample size.

The given values are σ=1.36 and sample size n=5 , substitute the values in the above formula:

σx¯=σn=1.365=1.362.23=0.61

The standard deviation of the sample means σx¯=0.61

b)

Summary Introduction

To determine: The control limits for the mean chart if the value of z is 3.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 10P

The UCL value of x¯ is 11.83 and the LCL value is 8.17.

Explanation of Solution

Given information:

The following information is given:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  2

Sample size is given as 5 and process standard deviation is given as 1.36.

Determine the control limits for the mean chart if the value of z is 3:

Formulae to calculate control limits:

UCL=x¯¯+z×σx¯ (1)

LCL=x¯¯z×σx¯ (2)

Here,

The value of z=3

x¯¯ is the mean of the sample means

the standard deviation of the mean σx¯=0.61

Calculate the average for each sample:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  3

Working note:

Average for sample #1:

It is calculated by dividing the total of sample #1 and sample size.

Average=Total of Sample #1Sample size=515=10

Note: The same continues for all the samples.

Calculate the value of x¯¯ :

It is calculated by dividing the sum of average of all the samples and the number of samples. Hence, the value of x¯¯ is 10.

x¯¯=Average of all samplesNumber of samples=10+10+10.2+10.2+10.4+9.8+9.6+9.8+9.8+1010=10

Substitute the values in equation (1)to determine the value of UCL as follows:

UCL=x¯¯+z×σx¯=10+3×(0.61)=10+1.83=11.83

Hence, the UCL value is 11.83.

Substitute the values in equation (2) to determine the value of LCL as follows:

LCL=x¯¯z×σx¯=103×(0.61)=101.83=8.17

Hence, the LCL value is 8.17.

c)

Summary Introduction

To determine: The control limits for the range chart.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 10P

The UCL value of R-chart is 6.9795 and the LCL value is 0.

Explanation of Solution

Given information:

The following information is given:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  4

Sample size is given as 5 and process standard deviation is given as 1.36.

Determine the control limits for the mean chart if the value of z is 3:

Formulae to calculate control limits:

UCLR=D4×R¯ (3)

LCLR=D3×R¯ (4)

Here,

D3 refers to the lower range factor

D4 refers to the upper range factor

R¯ refers to the average range

Substitute the values in equation (3) to determine the value of UCL as follows:

UCLR=D4×R¯=2.115×3.3=6.9795

Hence, the UCL value is 6.9795.

Substitute the values in equation (4) to determine the value of LCL as follows:

LCLR=D3×R¯=0

Hence, the LCL value is 0.

d)

Summary Introduction

To determine: Whether the process is in control.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 10P

The process is in statistical control.

Explanation of Solution

Given information:

The following information is given:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  5

Sample size is given as 5 and process standard deviation is given as 1.36.

Plot the sample mean values in the x¯ control chart where UCLx¯=11.83 and LCLx¯=8.17

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  6

Plot the sample mean values in theR-control chart where UCLR=6.9795oz and LCLR=0

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 6.S, Problem 10P , additional homework tip  7

The sample range values lie well within the upper control limit and lower control limits.

The process is in statistical control.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
IM.82 A distributor of industrial equipment purchases specialized compressors for use in air conditioners. The regular price is $50, however, the manufacturer of this compressor offers quantity discounts per the following discount schedule: Option Plan Quantity Discount A 1 - 299 0% B 300 - 1,199 0.50% C 1,200+ 1.50% The distributor pays $56 each time it places an order with the manufacturer. Holding costs are negligible (none) but they do earn 10% annual interest on all cash balances (meaning there will be a financial opportunity cost when they put cash into inventory). Annual demand is expected to be 10,750 units. When there is no quantity discount (Option Plan A, the first row of the schedule listed above), what is the adjusted order quantity? (Display your answer to the nearest whole number.) 491 Based on your answer to the previous question, and based on the annual demand as stated above, what will be the annual ordering costs? (Display your answer to the…
Excel Please. The workload of many areas of banking operations varies considerably based on time of day.  A variable capacity can be achieved effectively by employing part-time personnel.  Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees.  Other considerations, however, may limit the extent to which part-time people can be hired in a given department.  The problem is to find an optimal workforce schedule that would meet personnel requirements at any given time and also be economical.   Some of the factors affecting personnel assignments are listed here:   The bank is open from 9:00am to 7:00pm. Full-time employees work for 8 hours (1 hour for lunch included) per day. They do not necessarily have to start their shift when the bank opens. Part-time employees work for at least 4 hours per day, but less than 8 hours per day and do not get a lunch break. By corporate policy, total part-time personnel hours is limited…
IM.84 An outdoor equipment manufacturer sells a rugged water bottle to complement its product line. They sell this item to a variety of sporting goods stores and other retailers. The manufacturer offers quantity discounts per the following discount schedule: Option Plan Quantity Price A 1 - 2,399 $5.50 B 2,400 - 3,999 $5.20 C 4,000+ $4.50 A large big-box retailer expects to sell 9,700 units this year. This retailer estimates that it incurs an internal administrative cost of $225 each time it places an order with the manufacturer. Holding cost for the retailer is $55 per case per year. (There are 40 units or water bottles per case.) Based on this information, and not taking into account any quantity discount offers, what is the calculated EOQ (in units)? (Display your answer to the nearest whole number.) Number Based on this information, sort each quantity discount plan from left to right by dragging the MOST preferred option plan to the left, and the LEAST preferred…

Chapter 6 Solutions

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning