Question
Chapter 5.S, Problem 12DRQ
Summary Introduction
To determine: The manner in which the manager makes the decision for the given situation.
Situation: A manager uses the maximum expected monetary value (EMV) as a basis for making a capacity decision. In the process, the result obtained will be the virtual tie between two of the seven alternatives.
Introduction: Expected monetary value is an anticipated value for an investment. The expected monetary value is computed by multiplying every possible outcome with the likelihood of each outcome occurring and summing the all values. Investors use expected monetary values to select the scenario that provides a desired outcome.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What do you understand by capacity planning? Explain the decision tree modeling for capacity expansion
A manufacturer of ballet shoes has determined that its production facility has a design capacity of 300 shoes per week. Theeffective capacity, however, is 230 shoes per week. What is themanufacturer’s capacity utilization relative to both design andeffective capacity if output is 200 shoes per week?
An airline company must plan its fleet capacity and long-term schedule of aircraft usage. For oneflight segment, the average number of customers per day is 70, which represents a 65 percentageutilization rate of the equipment assigned to the flight segment. If demand is expected toincrease to 84 customers for this flight segment in three years, and management requires acapacity cushion of 25 percent, calculate the following:
i. the planned capacity requirement. ii. the maximum number of customers the flight segment can accommodate.iii. the efficiency rate of the flight segment assuming that the current effective capacity of theflight segment is 93 customers.
Chapter 5 Solutions
Operations Management
Ch. 5.8 - Explain the meaning of the phrase Hours versus...Ch. 5.8 - Prob. 1.2RQCh. 5.8 - Prob. 1.3RQCh. 5.8 - Prob. 1.4RQCh. 5.8 - Prob. 1.5RQCh. 5.S - Prob. 1DRQCh. 5.S - Prob. 2DRQCh. 5.S - Explain the term bounded rationality.Ch. 5.S - Prob. 4DRQCh. 5.S - Prob. 5DRQ
Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company has a factory that is designed so that it is most efi cient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardEstimate the cost of a 0.75 million gallon per day (MGD) induced-draft packed tower for air-stripping trihalomethanes from drinking water if the cost for a 2.9-MGD tower is $153,200. The exponent in the cost-capacity equation is 0.47. The cost of a 0.75 million gallon per day induced-draft packed tower is $arrow_forwardEvaluate capacity alternatives using decision trees?arrow_forward
- A company has a factory that is designed so that it is most eficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?arrow_forwardProblems 2 Helen Murvis, hospital administrator for Portland General Hospital, is trying to determine whether to build a large wing onto the existing hospital, a small wing, or no wing at all. If the population of Portland continues to grow, a large wing could return $150,000 to the hospital each year. If the small wing were built, it would return S$60,000 to the hospital each year if the population continues to grow. If the population of Portland remains the same, the hospital would encounter a loss of $85,000 if the large wing were built. Furthermore, a loss of $45,000 would be realized if the small wing were constructed and the population remains the same. Unfortunately, Helen does not have any information about the future population of Portland * Develop a decision table for this problem. * Determine the best decision using the following decision criteria 1. Мaximax 2. Маximin 3. Minimax Regret Hurwicz (use a coefficient of realism of 0.75) 5. Equal likelihood 6. Expected Value 7.…arrow_forwardSniparrow_forward
- The bus of company A has planned their capacity in terms of ‘bus-days’. Forecasts show expected annual demands for the next year to average 400,000 full-day passengers and 840,000 half-day passengers. The company has 61 buses, each with an effective capacity of 40 passengers a day for 300 days a year. Breakdowns and other unexpected problems reduce efficiency to 90%. They employ 86 drivers who work an average of 220 days a year, but illness and other absences reduce their efficiency to 85%. If there is a shortage of buses the company can buy extra ones for $110,000 or hire them for $100 a day. If there is a shortage of drivers they can recruit extra ones at a cost of $20,000 a year, or hire them from an agency for $110 a day. How can the company approach its tactical planning? Please recommend company A the best plan and explain in detail the reasons for the selectionarrow_forwardA biotech firm is considering abandoning its old plant, built 23 years ago, andconstructing a new facility that has 50% more square footage. The original cost of the old facility was $300,000, and its capacity in terms of standardizedproduction units is 250,000 units per year. The capacity of the new laboratoryis to be 400,000 units per year. During the past 23 years, costs of laboratoryconstruction have risen by an average of 5% per year. If the cost-capacity factor, based on square footage, is 0.80, what is the estimated cost of the newlaboratory?arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows: Machine CostA $40,000B $30,000C $80,000Product forecasts and processing times on the machines are as follows: Processing Time per Unit (minutes) Product Annual Demand A B C 1 16000 3 4 2 2 12000 4 4 3 3 6000 5 6 4 4 30000 2 2 1 a.) Assume that machines operate 10 hours a day, 250 days a year. If we only consider purchasing costs, which machine would have the lowest total cost? b.) Assume machines operate 10 hours a day, 250 days a year. If we select machine A, how many machine A do we need? (Use common sense to decide the answer.)arrow_forward
- An executive conference center has the physical ability to handle 1,100 participants. However, conference management personnel believe that only 1,000 participants can be handled effectively for most events. The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. What are the utilization and efficiency of the conference facility?arrow_forwardTonya Stephani is the front office manager/RM at the 200-room Hilton Garden hotel. Tonight, she has 100 stay-over rooms and 100 arrivals. Based on her own forecasts, she anticipates 10 no-shows tonight. The average rate to be paid by each arriving guest is $199.99. Tonya has a signed agreement with the local Sheraton hotel that states each property is willing (subject to blackout dates) to accept the other’s walks at the rate of $99.00 per night. Tonight, the Sheraton has available rooms and has agreed to take up to ten walked guests. The cost of transporting guests to the Sheraton and back, as well as other walk related costs incurred by the Hilton, average $15.00 per room. Assume Tonya decides to overbook by ten rooms. Excluding any potential no-show billings, how much extra room revenue will be gained from overbooking if Tonya indeed experiences ten no-shows but overbooks by ten rooms and thus achieves a 100 percent occupancy? How much extra cost will the hotel incur if it sells…arrow_forwardSuzy's Temporary Employee (STE) business, located in a big city, can do an online criminal background check in-house for $3.48 per search with a fixed cost of $30,000. A third-party online security firm offered to do a similar security search for $9.00 per person with an annual service contract with STE. If STE's forecast is 3,100 searches next year, should STE continue to do the search in-house or accept the third-party offer? Use the Excel template Break-Even to determine the best decision. Round your answer for the breakeven quantity to the nearest whole number and round your answer for the amount of saving/loss to the nearest dollar. Breakeven quantity: searches Since the demand forecast of 3,100 searches is than the breakeven quantity, STE outsource the work. STE $ by outsourcing.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,